Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 31668
Docket No. MW-31216
96-3-93-3-184

The Third Division consisted of the regular members and in addition Referee Robert Richter when award was rendered.

(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company
( (Eastern Lines)

STATEMENT OF CLAIM:





Form 1 Award No. 31668
Page 2 Docket No. MW-31216
96-3-93-3-184

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The Organization filed this claim on February 18, 1992 alleging the Carrier used an outside contractor to cut brush from Mile Post 158 in Garrison, Texas, working toward Shreveport. It furnished a letter from an I&R Foreman in support of its case. The letter was written on May 8, 1992, some three months after the claim was filed. In the letter the foreman states the work began in the first week of December, but no work was performed for three weeks around Christmas and New Year's. The letter indicates the work ceased on January 30, 1992. By its own evidence only 17 calendar days are involved. However, no evidence has been produced that the contractor worked any or all of these days.


The Organization argues the Carrier violated Article 36 of the Agreement when it failed to give notice of the contracting out of the work in question. It claims that Track Department laborers have customarily and historically performed the work of removing excessive vegetation around grade crossings.


The Carrier's position is that it has contracted out the work of weed and brush control to Asplundh since 1986. It has furnished copies of these contracts. It also argues that the Scope Rule is general in nature, and that the Organization has failed to prove the work of brush cutting belongs exclusively to maintenance of way employees. The Carrier has never given the Organization advance notice of the contracting out of this work.

Form 1 Award No. 31668
Page 3 Docket No. MW-31216
96-3-93-3-184

The Organization counters the Carrier by arguing that the past contracts only dealt with chemical weed spraying and did not including brush cutting. It also took the position that the exclusive position taken by the Carrier only applies when other crafts are involved, not outside contractors.


From the correspondence in the record it appears the Organization concedes the contracting out of the use of Chemical Weed Spray is not work belonging to the Track Department It appears the only contention is that the contractor's use of chain saws to cut brush violates the Agreement.


The Organization has the burden to prove the Agreement has been violated. It alleges the outside contractor cut brush using chain saws beginning January 13, 1992. However, a review of the file reveals not one scintilla of evidence that the work in question was done on the claim dates.










Inasmuch as the Carrier has shown that it has contracted with Asplundh for the control of weed and vegetation along its right-of-way since 1986, the Organization has failed to show the work is within the scope of the Agreement.


The Organization has failed to show the alleged work was actually performed, and that the work performed by the contractor since 1986 is work covered by the Scope Rule.

Form 1 Award No. 31668
Page 4 Docket No. MW-31216
96-3-93-3-184



      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 29th day of August 1996.