Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 31676
Docket No. MW-31467
96-3-93-3-462
The Third Division consisted of the regular members and in addition Referee
Robert Richter when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company
( (Eastern Lines)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned an outside
concern (Wayne West) using five (5) trucks to perform truck
driving work of hauling track panels from El Paso, Texas to Mile
Post 499.27 near Sanderson, Texas on July 12 and 13, 1992 (System
File MW-92-120/MofW 92-162 SPE).
(2) The Agreement was further violated when the Carrier failed to
furnish the General Chairman with fifteen (15) day's advance
written notice of its plan to contract out the above-described work
in accordance with Article 36.
(3) As a consequence of the violation referred to in Parts (1) and/or (2)
above, Machine Operators L. E. Dube, D. D. Baker, J. A. Bobb, L.
Harvey and D. L. Johnson shall each be allowed twenty-four (24)
hours' pay at their respective time and one-half rate."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved In this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21, 1934.
Form 1 Award No. 31676
Page 2 Docket No. MW-31467
96-3-93-3-462
This Division
of
the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute waived right
of
appearance at hearing thereon.
On Sunday, July 12, 1992, a derailment occurred on the Carrier's track at
Feodona, Texas, which blocked the main line, stopping all traffic. The Carrier used an
outside trucking company to haul track panels from El Paso, Texas, to the derailment
site. It took five trucks to haul the track panels.
The Organization filed this claim alleging that the hauling
of
track material is
reserved for maintenance
of
way employees. It further alleges the Carrier failed to
serve notice
of
its intent to contract out the work.
The Carrier argues that an emergency existed and because
of
the emergency it
had the right to use the contractors to haul the track panels. The Carrier cites
numerous awards to support its position. In particular, it cites Third Division Award
26677, involving the same parties with similar circumstances to this case. In that case
the Board held as follows:
"OPINION OF BOARD: On February 6, 1984, a derailment occurred at
Schriever, Louisiana, causing severe damage to the main track and an
interruption in service. The main track was out
of
service on February 6
and 7, 1984. For purposes
of
repairing the damaged track, Carrier
contracted with outside forces to haul paneled track and switches from
Houston to Schriever, triggering the Claim herein. Claimants were all
heavy duty Truck Drivers qualified to perform the work involved. On the
two days
of
the activity to repair the track all Claimants were either being
used to haul material to the site
of
the derailment or were otherwise fully
employed.
The Organization argues that the outside forces should not have
been called until Carrier exhausted the roster
of
available employees
covered by the Agreement. Further, it is maintained that Carrier was
obligated by Rule 36 to give fifteen days notice
of
its intent to contract out
work. Even recognizing the fact
of
an emergency, the Organization insists
that Claimants had the right to the work, on an overtime basis if
necessary, prior to the utilization
of
outside forces.
Form 1 Award No. 31676
Page 3 Docket No. MW-31467
96-3-93-3-462
Carrier avers that clearly an emergency existed on the two days
involved herein. Under the circumstances, Carrier insists that it had great
latitude in dealing with the crisis and acted appropriately. Additionally,
Carrier notes that it would have been patently impossible to give the
fifteen days notice specified in Article 36 under the circumstances of this
emergency situation. Carrier also stated that it used five of the Claimants
to do the work of hauling material to the site of the derailment.
It is clearly acknowledged that the circumstances in this dispute
involved an emergency. This Board has held that in an emergency Carrier
may take whatever action it deems appropriate to cope with its problems;
see Third Division Awards 13316, 12777, 15597 and many similar
holdings. It is also apparent that the provisions of Article 36 are
inapplicable under the circumstances and were not violated by Carrier in
this dispute. The Claim must be denied."
A careful review of the file in this case does not reveal a reason to deviate from
the above cited Award.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders that
an award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 29th day of August 1996.