Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 31716
Docket No. MW-31378
96-3-93-3-251
The Third Division consisted of the regular members and in addition Referee
Robert L. Hicks when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Denver and Rio Grande Western Railroad Company
STATEMENT OF CLAIM:
"(1) The Agreement was violated when the Carrier assigned outside
forces (Luco Salt Lake Steel) `...picked up rail, spikes and plates at
different locations (Grand Junction west yard - 160 rail -- Delta - 60
rail -- Austen 50 rail - also misc. spikes, plates and rail throughout
the Montrose branch. ***' beginning November 12, 1991 and
continuing (System File D-92-02).
(2) The Agreement was further violated when the Carrier failed to give
the General Chairman fifteen (15) days' advance written notice
of
its intent to contract out the work in Part (1) above as required by
Article IV
of
the May 17, 1968 National Agreement.
(3) As a consequence
of
the violations referred to in Parts (1) and/or (2)
above, machine Operator L. T. Bartlett and employes assigned to
the Grand Junction Section, the Delta Section and the Peonia
Section subsequent to November 12, 1991 shall each be allowed
eight (8) hours' pay per day at their respective straight time rates
and that they shall be compensated at their time and one-half rates
for hours worked outside the regular assigned hours commencing
November 12, 1991 and continuing until the violation cease."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
Form 1 Award No. 31716
Page 2 Docket No. MW-31378
96-3-93-3-251
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute were given due notice of hearing thereon.
From the Statement of Claim. it is the Organization's position that Carrier
violated various Rules and Agreements by contracting work that is theirs by Agreement
and did so without advance notice.
The Carrier responds stating no Rules and/or Agreements were violated.
particularly the Contracting Out Agreement, as it contracted no work. It did sell "as
is, where is" scrap material with the purchaser coming on the property to retrieve that
which it bought.
The Carrier, in its response to the claim presented at the first level, stated:
"...Should you wish we can make available the pertinent sales documents
for your inspection ...."
Before this Board, the Organization argues that the Carrier never substantiated
its defense. The Board finds, however, that the Organization failed to avail itself of the
opportunity to review the documents they are now contending are improperly before this
Board as part of Exhibit A of the Carrier's Submission.
A like situation prevailed in a dispute resolved by the Board in Third Division
Award 30901. Following is an excerpt from that Award:
"...the Carrier advise the Organization that `...a copy of the contract .. is
available in our offices for your inspection, should you so desire.' Under
the circumstances, the Organization cannot argue that the Carrier did not
produce a copy of the contract on the property ...."
Form 1 Award No. 31716
Page 3 Docket No. NIW-31378
96-3-93-3-251
This is a sale of scrap material on an "as is where is" basis. The Contracting
Rules are not applicable to this situation, nor is there any evidence that the scrap
merchant made any judgment as to what was salvageable and what was not.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above. hereby orders that
an award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 25th day of September 1996.