Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 31798
Docket No. MW-31330
96-3-93-3-252
The Third Division consisted of the regular members and in addition Referee
Robert L. Hicks when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM:
"(1) The Agreement was violated when the Carrier assigned outside
forces (Randall O'Reilly Inc.) to perform Bridge and Building
Subdepartment work (removing existing gravel, building forms and
pouring concrete) at Fisher Road Material Yard in Columbus, Ohio
on August 14, 15, 16, 19, 20, 21, 22 and 23, 1991 (System Docket
MW-2415).
(2) As a consequence of the violation referred to in Part (1) above,
Claimants R. L. Ritterbeck, C. T. Julian, L. J. Sacher and D. D.
Philbin shall each be allowed sixty-two (62) hours' pay, at their
respective rates, for the two hundred and forty-eight (248) manhours expended by the outside forces
work."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21,1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
herein.
Form 1 Award No.
31798
Page 2 Docket No.
VYW-31330
96-3-93-3-252
Parties to said dispute were given due notice
of
hearing thereon.
On July 5, 1991, the Carrier served the following notice:
"This is to advise that we intend to contract for the installation of a 10,000
square foot concrete pad at the Columbus MW Material Yard. The
project will include the clearing and removal of an existing 10" stone base
and redistributing it prior to laying the concrete pad.
The pad will be used to support exterior pallet racks for C&S and surplus
MW material and must be completed quickly (on or about July 22. 1991)
for the anticipated inbound shipments
of
material.
This work must be done quickly and our B&B employees are actively
involved in other work. Our estimates indicate,
if
our employees were
available, the completion of the project would be extended by eight days.
Further, the total cost
of
the project would be increased by $7,497 which
represents a net difference
of
28% based on the following:
1. Estimate the use
of 3
operators for 3-1/2 days to do
excavation and set up forms. $ 2,345
2. 4 men for 10 days to do concrete work 9,382
3. Material costs: 320 yards
of
concrete 517,360
reinforcing 4,800
form material 300 22.460
Total $34,187
Contractor's bid - $26,690"
After the conference, the Carrier contracted to have the work done. The
contractor expended 248 man-hours over eight days, commencing August 14, 1991, and
completed the work on August 23, 1991.
Form 1 Award
No. 31798
Page 3 Docket
No. MW-31330
96-3-93-3-252
The Organization filed claim contending that the Carrier was in violation
of
the
Scope
of
the Agreement, as well as Rule I.
The Carrier's defense is as follows:
"Our investigation has determined that we provided you with notice
of
our
intent to contract this work on July 5, 1991. We explained that said work
had to be completed quickly and that all B&B employees were fully
occupied in the performance
of
other work. We also pointed out that this
use of the contractor would save the Carrier approximately $7500.
It must be also noted that while each of the Claimants were fully employed
during the claim period, three of the Claimants were also observing
vacation during a portion of the claim period and thus cannot be
considered available on those dates.
Based on the foregoing, this claim is devoid of merit, and is denied."
As is evident, the Carrier's defense is:
1 - savings to Carrier by using an outside force;
2 - unavailability of Claimants as they were fully occupied: and
3 - expediency in completing the project.
Regarding the need for expediency, a review of the record finds that although
there may have been a need to complete the project quickly, the actual facts do not bear
this out. The July 10 suggested conference date did not materialize as the
Organization's request for a conference was not received until July 11, and was not held
until July 31. The project started on August 14, and was completed on August 23. It
may have been a good faith argument by the Carrier, but unfortunately the actual
events do not support the claim of expediency.
Form 1 Award No.
31798
Page
4
Docket No.
i~M-31330
96-3-93-3-252
The cost factor argument, although not contained in the Scope as a sufficient
reason to contract, has been upheld in Third Division Award 28999. An analysis of that
Award, however, finds that it is not on all fours with this situation. In that Award, the
Carrier stated that the contractor would do the work "for $3000 less than the Carrier
would expend to rent the specialized equipment needed for performing just the leveling
work, a small part of the project."
Third Division Award 31388 is more in line with this dispute regarding the cost
factor:
"...the Carrier also mentions that it could have the work done by a
contractor at less expense than would be entailed in using its own forces.
This appears to admit that Carrier forces were capable of performing the
work, no doubt through previous experience therein. Beyond this,
however, the Board must be concerned with the Agreement as written by
the parties and not with whether compliance is more or less costly than
non-compliance."
The cost factor argument in this dispute is not persuasive.
Regarding the unavailability of the Claimants because they were already engaged
in other projects, thus the necessity to contract is an argument that has not been
accepted and is not considered in this case.
Based solely upon that which the parties stated in various exchanges in the onproperty handling, the
it has in other cases, that the Claimants suffered no lost earnings as each received
compensation on each of the claim dates. This is an issue that has been argued in
numerous other disputes, but on this Carrier it has not been too successful. See Awards
24 and 41 of Special Board of Adjustment No. 1016, Award 7 of Public Law Board No.
3781 and Third Division Award 30181.
One other factor regarding the compensation due issue is that Carrier pointed out
that three of the Claimants were, at various times that coincided with dates the
contractor performed this work, off on paid vacation. If the Claimants would have been
assigned-to do this work, there is nothing to indicate that each would have postponed
their vacation to another time, thus Carrier may deduct from the hours claimed, the
hours each was on vacation.
Form
1
Award No. 31798
Page 5 Docket No.
~iNIW-31330
96-3-93-3-252
AWARD
Claim sustained in accordance with the Findings.
This Board, after consideration of the dispute identified above, hereby orders that
an award favorable to the Claimant(s) be made. The Carrier is ordered to make the
Award effective on or before 30 days following the postmark date the Award is
transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order
of
Third Division
Dated at Chicago, Illinois, this 26th day
of
December 1996.