Form 1 N.\ I 10N kL IWLROAD :)LDJC'ST~IENT BOARD
THIRD DIVISION
Award No. 31866
Docket No. NIW-30809
97-3-92-3-643
The Third DiNision consisted of the regular members and in addition Referee
Dana E. Eischen when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPCTE:
(Consolidated Rail Corporation
STATEMENT OF CL MINI:
"(1) The .agreement was violated when the Carrier assigned outside
forces (Brian Bedford Roofing Company) to perform Bridge and
Building Subdepartment work (roof repairs) at the Conrail Repair
Shop, Easton, Pennsvfvania on the Philadelphia Division beginning
January 15, 1991 and continuing. (System Docket MW-1966)
(2) The Agreement was further violated when the Carrier failed to give
the General Chairman prior written notification of its intent to
contract out said work to outside forces as required by the Scope
Rule and by its failure to assert a 'good faith' effort to reduce such
subcontracting as stipulated within the December 11, 1981 Letter
of Agreement.
(3)
.As
a consequence of the violations referred to in Parts (1) and/or (2)
above, B&B Foreman D. Brulia and B&B Mechanics F. Hernandez,
G. Sanchez, G. Sell and S. Takacs shall each be compensated at
their respective straight time and time and one-half rates of pay for
an equal proportionate share of the total number of man-hours
expended by the outside forces performing said work and Claimant
Hernandez shall receive all benefits and credits for vacation in
connection therewith."
FINDIN . :
The Third Division of the Adjustment Board, upon the whole
record and all the
evidence, finds that:
Form I Award No. 31866
Page 2 Docket No. MW-30809
97-3-92-3-643
The carrier or carriers and the employee or employees involved in this dispute
are respectiNely carrier anti employee within the meaning of the Railway Labor Act, as
appro%ed June 21. 193-1.
This Division of the .adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute
Ns
ere giNen due notice of hearing thereon.
Claimant B. Brulia has established and holds seniority as a B&B Foreman.
Claimants Hernandez, Sanchez, Sell and Takacs are B&B Mechanics. Each of the
Claimants held regular assignments in their respective classifications on the
Philadelphia Division, however Claimant Hernandez was furloughed from Carrier's
service at the time this dispute arose.
In a letter dated October 25, 1990, Carrier gave the Organization notice of its
intention to contract out the installation of galvanized roof on the repair shop in Easton,
PA. The work commenced on January 15, 1991, and continued on four additional days
to complete the project. On January 17, 1991, the Organization filed a claim alleging
a violation of the Scope Rule and the December 11, 1981 Letter of Agreement. In
addition to monetary damages on behalf of Messrs. Brulia, Sanchez, Sell and Takacs,
the Organization also claimed credits for vacation, S.U.B. benefits and insurance
coverage for Claimant Hernandez.
Carrier denied the claim, and in an appeal letter dated March 8, 1991, the claim
was progressed to Carrier Manager-Labor Relations. Subsequent to a April 11, 1991
conference, the Manager denied the claim on grounds that the work in dispute was "not
repair work as envisioned by the agreement" and asserting that Carrier's forces "lacked
the expertise°° to do the work.
In its reply to Carrier's denial, the Organization alleged:
"The claimants are qualified to perform this work in question and the
Organization will submit statements to support this claim.
However, if the claimants were not qualified to perform this work, which
they are, this would not give Conrail the right to contract out work.
The Organization is requesting Conrail to specify what rule in the current
Form l Award 1o. 31866
Pa"e 3 Docket -'o. `IW-30809
97-3-92-3-6.83
BNl\1
E .kgreentent that allows Conrail to freely contract out NIAV work. It is up
to the carrier to halve lower management (supervision) that are fully qualified in
performing the ~Nork they are to supervise. It is obvious that the current B&B
supervision assigned to this area cannot perform the task of simple roof
installation. The
BNIIN
E employees should not loose work opportunities to
unqualified management. In this case, Conrail should have hired a supervisor
form Bedford's Contracting that can properly supervise the NVW employees in
performing this tNpe of work. Again, this is a classic example of Conrail
management not being qualified to perform the tasks for which they are being
paid to perform."
In a letter dated \oNember 13, 1991, Carrier reiterated that Claimants were "not
qualified" for the work in question and asserted that "this type of roof has never been
installed on the Dig ision." Carrier challenged the Organization to submit "verifiable
evidence" in support of its position. The Organization ultimately submitted a statement
from Claimants Brulia and Sell asserting that roofs "similar" to the one in dispute
"were done in 1976 under the supervision of Structural Supervisor J. Herman."
As in all Scope Rule claims, it is imperative to focus precisely and specifically
upon the work in dispute: in this case the installation of a new galvanized steel roof on
a Carrier-owned building. Given the unique language of this particular Scope Rule, the
Organization meets its burden of proving work reservation by convincing evidence of
a custom, practice and tradition of performance of this work by Agreement-covered
employees and/or actual performance on the effective date of the 1982 Conrail/BMagreement. See Third Division Awards 30515, 30100.
The work involved in this dispute is not expressly reserved by the language of
the
Scope Rule. Equivocal statements submitted by two of the Claimants are inadequate to
convincingly carry the burden of proving a mutually recognized custom, practice or
tradition of reserved performance of the disputed work or actual performance
on the
Agreement's effective date, by Agreement-covered employees. Based on the record,
this
claim must be denied.
AWARD
Claim denied.
Form I Award No. 31866
Page 4 Docket No. :MW-30809
97-3-92-3-643
This Board, after consideration of the dispute identified above, hereby orders that
an award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENTT BO
By Order of Third Division
Dated at Chicago, Illinois, this 4th day of March 1997.