Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 32013
Docket No. MW-31704
97-3-93-3-735

The Third Division consisted of the regular members and in addition Referee Nancy F. Murphy when award was rendered.

(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company
( (Eastern Lines)

STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and ail the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Form 1 kward No. 32013
Page 2 Docke ' No. MW-31704
97-3-93-3-735



M. H. Martinez (Claimant) has been employed by Carrier for approximately 18 vears, and has established and holds seniority as a machine operator. He was assigned as such on a ballast regulator, under the supervision of Roadmaster W. Zunker and was working in the vicinity of HebromOlle, Texas at the time of the incident giving rise to this dispute.


On September 15. 1992, Claimant was operating a ballast regulator in the vicinity of Mile Post (MP) 704. The ballast regulator, which normally works directly behind a tamper, is used for filling in the track and "dressing" it for final inspection. Claimant had been instructed, by his supervisor, to perform work at MP 701 while the tamper raised and lined track near MP 704.6. After Claimant had finished the assigned work at NIP 701, he traveled to the west switch at Collado, Texas, where he was to meet the tamper being operated by Machine Operator Lopez. As Claimant approached the west switch, he applied his brakes: however, the ballast regulator slid, some 574 feet, colliding with the tamper. The collision resulted in damage to the front attachments (buggies) of the tamper.


Claimant maintained that the collision occurred a result of "an excess amount of grease on the rail", caused by a rail oiler located at MP. 705.30. However, Carrier asserted that the accident occurred as a result of Claimant traveling at "an excessive speed."


On the following day, September 16, 1992, the "incident" was reenacted. According to Roadmaster Zunker, on the date of the accident, Claimant slid approximately 574 feet, and on the day of the reenactment, he traveled only 450 feet prior to the point of impact. However, Work Equipment supervisor Quesada stated that Mr. Martinez actually slid 585 feet on the day the incident was reenacted, some 11 feet further than on the date Carrier charged him with the improper the rule violation.


Regardless of the inconclusive reenactment "results", on September 30, 1992, Carrier assessed Claimant with a 30 day suspension for his "involvement in" the collision of his machine and the buggies of the tamper. Carrier premised the discipline on Claimant's alleged violation of Rule 2.11.8, which states:
Form 1 Award No. 32013
Page 3 Docket No. MW-31704
97-3-93-3-735
"Operators must have track cars under control at all times and be
able to stop short of one-half of the sight distance or before striking
an obstruction on, or foul of, the track."

In accordance with Article 14 of the Agreement - DISCIPLINE AND INVESTIGATION, Claimant requested an Investigation, which was originally scheduled for October 20, 1992, but was postponed, and held on October 29, 1992. In Carrier's Notice regarding said postponement, it stated that Claimant had instead, allegedly violated Rule 2.13.32, which provides:



At the outset of the Hearing, Carrier qualified the alleged dual Rule violation by stating that:


The Organization did not ask for additional time to prepare, but, Mr. Sanchez did request that the Investigation be terminated because: "Mr. Martinez was operating a track machine, not a track car. It is our position that a roadway machine is a machine that can be operated on the highway and on the track, and Mr. Martinez is and was not
Form 1 4ward No. 32013
Page 4 Docket No. iVIW-31704
97-3-93-3-735

operating a roadway machine or motor car on this date as charged." Carrier denied the Organization's motion to terminate the Investigation, reiterating that Claimant "could have been charged with either Rule 2.11.8 or 2.13.32." Subsequent to the Investigation, Carrier upheld the discipline of a 30 day suspension.











The Organization's threshold argument, regarding the change in the Agreement Rules cited, and the appropriateness, or lack thereof, is not persuasive. Carrier's assertion that either, or both Rule 2.11.8 or 2.13.32, could apply, in these particular circumstances, is well grounded. There is no showing of actual prejudice, unfairness or lack of understanding of the charges, by Claimant or the Organization. Moreover, the Organization waived the right to have additional time to prepare. Therefore, the Organization's contention, that that procedural "flaw" Is fatal to Carrier's case is without merit.


Turning to the merits of this dispute, a close review of the transcript fails to support Carrier's contention that the accident would not have occurred, but for Claimant traveling at "an excessive rate of speed." In that connection, we need look no

Form 1 Award No. 32013
Page 5 Docket No. MW-31704
97-3-93-3-735

further than the testimony of Carrier witnesses' Zunker and Quesada. Under questioning by Organization Representative Sanchez, Roadmaster Zunker testified:
















Regarding the Organization's assertion that excessive grease on the rail, rather than excessive speed, was, in fact, the primary cause of the accident, we have Mr. Sanchez' interrogation of Roadmaster Zunker and Work Equipment Supervisor Quesada:


Form I Award No. 32013
Page 6 Docket No. MW-31704
97-3-93-3-735













Aside from speculation, there is no persuasive proof, in this record, that Claimant was traveling at a speed which could be considered "excessive" for the conditions. On
Form I Award No. 32013
Page 7 Docket No. MW-31704
97-3-93-3-735

the other hand, the undisputed record establishes that there was an extraordinary amount of grease on the rail. a condition which Claimant could not have observed or anticipated. Based on the evidence presented, we conclude that Carrier erred in holding Claimant responsible for the collision. Therefore, the imposition of any discipline in this case was arbitrary and unreasonable. The claim is sustained.








This Board; after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.



                      By Order of Third Division


Dated at Chicago, Illinois, this 6th day of May 1997.