Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 32162
Docket No. MW-31439
97-3-93-3-421

The Third Division consisted of the regular members and in addition Referee Herbert L. Marx, Jr. when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:



STATEMENT OF CLAIM:










Form 1 Award No. 32162
Page 2 Docket No. MW-31439
97-3-93-3-421
*The initial letters of claim will be reproduced within our
initial submission."

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act. as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




Without prior notice to the General Chairman, the Carrier states it employed a contractor to "perform backhoe and hauling work in the general vicinity of Cisco, Texas" during the period from February 7, 1992 through February 21, 1992. As will be seen below, the dates involved are of particular significance. The claim cited violation of the Scope Rule and of Article IV of the May 17, 1968 National Agreement.




Form 1 Award No. 32162
Page 3 Docket No. MW-31439
97-3-93-3-421



On April 7, 1992, the Organization initiated a claim, contending that the work could have and should have been performed by Carrier forces. This claim was received by the Carrier on April 9, 1992.


.according to the Carrier, a reply to this claim was issued on June 2, 1992. This denial response stated, among other considerations, that "the 60-day time limit for this claim has expired and the claim, therefore, must fail."


In a further appeal dated August 24, 1992, the Organization contended that it never received the June 2 response, thus requiring the claim to be allowed for failure of the Carrier to respond within 60 days.


The Carrier then sent the Organization a copy of the initial June 2 response, alleging that it had indeed responded in timely fashion and adding that the August 24 appeal was also untimely.


Finally, in its Submission, the Carrier argues the claim should be rejected not only for lack of timeliness, but because the claim as presented to the Board protests lack of notice to the General Chairman concerning the contracting and "(during the handling on the property, the Organization never raised the issue of the Carrier failing to serve notice."


The Board finds all these allegations without determinative significance, as follows:



Form 1 Award No. 32162
Page 4 Docket No. MW-31439
97-3-93-3-421





As to the merits, the Carrier asserted that it had regularly contracted this type of work for many years, without protest from the Organization. Attached to its Submission was an extensive list of such occasions, although the Organization points out that this was not produced on the property during the claim handling procedure and must be ignored as "new" argument Nevertheless, the Board is satisfied that there was knowledge of such previous contracting. Thus, the Organization's protest in this instance is properly treated as stated in Third Division Award 28849 (and in numerous subsequent Awards):



It must be noted, however, there is no Rule support for the Carrier's assertion that the Organization must show it has performed the work "exclusively." This, too, has been determined in many previous Awards.
Form 1 Award No. 32162
Page 5 Docket No. MW-31439
97-3-93-3-421

In this instance, the Carrier did fail to give notice, as required by Article IV and thus was in violation of the Agreement. However, this occurred, as specified above, in February 1992. Previous Awards, such as Third Division Awards 28849, 29474 and others, required this Carrier to provide notice even in instances where contracting has been previously undertaken without protest. These Awards, however, were issued after February 1992, when the instance here under review occurred. Thus, monetary remedy is not appropriate.




      Claim sustained in accordance with the Findings.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 13th day of August 1997.