Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 32265
Docket No. MW-31412
97-3-92-3-882

The Third Division consisted of the regular members and in addition Referee Herbert L. Marx, Jr. when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





Form 1 Award No. 32265
Page 2 Docket No. MW-31412
97-3-92-3-882
(4) The Agreement was further violated when the Carrier failed to
properly notify and discuss with the General Chairman its intent to
contract out said work as required by Article IV of the 1968
National Agreement.
(5) As a consequence of the violations referred to in Parts (1) and/or (4)
above, [five] B&B employes shall each be allowed three (3) hours'
pay at their respective hourly rates for each date the outside forces
performed the B&B Subdepartment road crossing work.
(6) As a consequence of the violations referred to in Parts (2) and/or (4)
above, 1411 Claimants shall each be allowed pay at their respective
rates of pay for an equal proportionate share of the total number of
man-hours expended by the Norfolk and Southern tie gang forces in
the performance of the tie renewal work on the dates in question.
(7) As a consequence of the violations referred to in Parts (3) and/or (4)
above, [62[ Claimants shall each be allowed pay at their respective
rates of pay for an equal proportionate share of the total number of
man-hours expended by the Norfolk and Southern rail and
surfacing gang forces in the performance of the unloading and
laying of rail and the surfacing work on the dates in question."

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.


Form 1 Award No. 32265
Page 3 Docket No. MW-31412
97-3-92-3-882

This matter consists of three separate claims, combined for the Board's review, concerning work performed by an outside contractor in one instance and by employees of another Carrier in the other two instances.


The type of work and arguments set forth by the Organization are virtually identical to those advanced in the dispute resulting in Third Division Award 31348, involving the same parties. In that Award, the Board found no exception to the reasons set forth by the Carrier to justify the necessity of contracting the work instead of utilizing its own forces.


In this instance, there is no question that the proper advance notice was given by the Carrier, and a resulting conference was held as requested by the Organization.


The Board finds the reasoning in Award 31348 should be and is determinative here. There is no basis to distinguish the facts from those considered earlier.








This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 7th day of October 1997.