Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 32277
Docket No. MW-31679
97-3-93-3-708

The Third Division consisted of the regular members and in addition Referee Peter R. Meyers when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:






FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
Form I Award No. 32277
Page 2 Docket No. MW-31679
97-3-93-3-708

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




This claim arose when the Organization took exception to the Carrier's use of an outside contractor to construct a 1' x 30' concrete pad at the Pocatello, Idaho Repair Shop on September 15, 16, 17 and 21, 1992. The Organization argued that this type of work has customarily, historically and traditionally been performed by the B&B subdepartment. The Organization contended also that the Claimant was fully capable and available to perform the work in question. Furthermore, the Organization argued that the Carrier violated the Agreement when it issued a notice to the Organization that "had absolutely no relevance to the instant case."


The Carrier denied the claim contending that it has a long established practice of contracting out masonry work of this nature. Further, the Carrier points out that the Claimant was fully employed and working on other projects for the Carrier on the dates in question.


The parties being unable to resolve the issues at hand, this matter came before this Board.


This Board has reviewed the record in this case and we find that the Carrier has met the notice requirements. The record reveals that a notice was served on the Organization on July 16, 1992. A conference was eventually held on August 19, 1992. The work did not begin until September 15, 1992.


With respect to the substantive issue, this Board finds that the work performed in this case was concrete work. The Carrier has relied upon 12 Awards that hold that it has the right to contract out concrete work. See Third Division Awards 28623, 30262, 30287, 31000, 31027, and 31028. We can see no reason to find differently in this case.



Form 1 Award No. 32277
Page 3 Docket No. MW-31679
97-3-93-3-708

the Agreement when it contracted out the concrete work, this Board must deny the claim.







This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 7th day of October 1997.