Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 32294
Docket No. MW-31104
97-3-93-3-134

The Third Division consisted of the regular members and in addition Referee Dana E. Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.
Form 1 Award No. 32294
Page 2 Docket No. MW-31104
97-3-93-3-134

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



This dispute involves two pertinent rules, each of which is unique to this property. Rule 58, states:



Rule 6, "CONTRACTING OUT OF WORK", first adopted in April, 1992, provides in pertinent part:







Claimants are employed by Carrier as Bridge & Building carpenters. At the time of this incident, they were regularly assigned as such on the Gary Division.


There is no dispute that beginning in the early 1980's, Carrier "downsizing" required considerable reorganization, repair and modification to the facilities which it retained. As part of the reorganization program, Carrier instituted a multi-year project of repairing and/or spray foam coating all roofs of the retained buildings. At issue in this case, the Kirk Yard Roundhouse-Truck Garage complex was one of the facilities designated for spray foam coating.

Form 1 Award No. 32294
Page 3 Docket No. MW-31104
97-3-93-3-134

The roof repair to this complex was engineered to be installed in five (5) annual phases, 1988-92, by an outside contractor. Commencing in 1988, the first phase over roundhouse stalls 31-40 was completed. The second phase scheduled roof repairs for the other end of the complex, which were completed in 1989. Phase three, (3), which was completed in 1990, returned the scheduled repairs to the second segment of the roundhouse roof. Phases four and five (4&5) were scheduled to be completed it 1991 and 1992.


On May 31, 1991, Carrier notified the Organization of its intent to contract out the Phase 4 roofing repairs at the Kirk Yard Roundhouse, and on July 15, 1991, Carrier signed a contract for labor and material to apply the urethane roofing system to the remaining areas designated to be completed in Phases 4 & 5. On July 9, 1991, Spray Foam Systems, Inc. commenced applying the roof coating, ultimately working a total of 142 hours, utilizing 3-5 men per day. The work was completed on August 2, 1991.


On September 16, the Organization submitted a claim regarding the Phase 4 work, maintaining that:





Form 1 Award No. 32294
Page 4 Docket No. MW-31104
97-3-93-3-134
the carpenters on the Elgin, Joliet and Eastern Railway
Company."

Carrier denied the claim, asserting that it was "untimely presented" in that it protested only one of the last phases of an ongoing project. Carrier further asserted that the claim "failed to identify what person or persons you are making the claim for," and asserting that "all carpenters were compensated for time worked on claim date at their respective rates of pay." Finally, Carrier stated that:




Finally, Carrier asserted that: "Third Division awards on this property have affirmed the Carrier's right to contract out repair work."


Carrier commenced the five (5) phase project in 1988 and three (3) of the five (5) phases were completed before the Organization requested that a conference be held regarding jurisdiction of said work. During the conference, the Organization maintained that B&B carpenters had "customarily" performed the duties, and that no expertise or special equipment was necessary to apply the spray foam coating. However, Carrier was able to successfully demonstrate that in accordance with its "unique" contractual right, e.g., Rule 6 of the controlling Agreement, it had historically contracted out the repair and maintenance work at issue in this dispute. Further, we

Form 1 Award No. 32294

Page 5 Docket No. MW-31104
97-3-93-3-134

deem it significant that this claim was not raised until the final two (2) annual phases of a five (5) year annually phased project. The Organization explained its delay in claiming the work on a theory of forbearance to allow its members to learn by observation the specialized spray-foam technology utilized by the subcontractor. That argument appears to be an admission against interest that the work in dispute has historically and traditionally been contracted out by Carrier. Moreover, the claim is defeated by the clear and concise language set forth in Rule 6 of the Agreement.








This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 13th day of November 1997.