Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 32334
Docket No. MW-32027
97-3-94-3-394

The Third Division consisted of the regular members and in addition Referee Margo R. Newman when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:







FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and ail the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.


Form 1 Award No. 32334
Page 2 Docket No. MW-32027
97-3-94-3-394

The underlying dispute concerns Carrier's contracting of handrail replacement on two bridges in New Jersey in November, 1992, after service of notice and conference occurred. Two separate claims were filed by the Organization on January 11, 1993 on behalf of specifically identified Claimants alleging that such bridge work violated the Scope Rule of the Agreement.


The instant claim seeks payment of the original claim amounts under the following provision of Rule 26(a):





During the handling of this matter on the property, and again before the Board, the Organization contends that it never received any response to its January 11, 1993 claims, which resulted in it sending a letter dated July 8, 1993 seeking payment under Rule 26(a). In its letters confirming the appeal meeting on the claims dated July 23 and August 5, 1993 respectively, Carrier states its position that a timely denial letter was issued by the Division Engineer on March 2, 1993. During the processing of this claim on the property, Carrier never indicated the manner in which the letter was sent to the Organization nor forwarded a copy of the denial letter to the Organization. Rather, it stated that "A copy of that letter was received in this office on March 10, 1993 and therefore further validates that the first level response was within the time limits prescribed by Rule 26(a)."


The only issue before this Board is the procedural issue of the alleged time limit violation. The Organization contends that it never received any denial letter and Carrier asserts that one must have been sent since it had a copy in its Human Resources file time-stamped March 10, 1993. Carrier included a letter dated March 2, 1993 with a

Form 1 Award No. 32334
Page 3 Docket No. MW-32027
97-3-94-3-394

stamp that the original was signed by Division Engineer Tierney in its record on the property.


A review of the record, and consideration of the awards cited by both parties, leads the Board to conclude that the following rationale adopted by it in Third Division Award 25309 between these parties is equally applicable herein:




This rationale is particularly appropriate where Carrier failed to produce any evidence on the property that the March 2, 1993 letter was actually sent or mailed in the normal course, or what the accepted practice was between the parties for delivery of declination letters. There is no dispute that the claims were hand-delivered. The only position Carrier takes in its correspondence on the property is that the apparent receipt of a copy of the letter by Human Resources which was retained in its files establishes timely denial. In fact, there is no proof that Carrier ever included copies of the March 2, 1993 declination letters with any of its correspondence to the Organization during discussion on the property. Such circumstances clearly distinguish this case from those relied upon by Carrier, which either predate Third Division Award 25309 (see Third Division Awards 22036, 24232, 22903), are between different parties and rely upon an established practice for delivery between the parties, see Special Board of Adjustment

Form 1 Award No. 32334
Page 4 Docket No. MW-32027
97-3-94-3-394

1011, Awards 7 & 8; Public Law Board No. 2945, Award 70; Public Law Board No. 3775, Award 55.









This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 13th day of November 1997.