Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 32334
Docket No. MW-32027
97-3-94-3-394
The Third Division consisted of the regular members and in addition Referee
Margo R. Newman when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The two (2) claims* as presented by Vice Chairman H. Wise on
January 11, 1993 to Division Engineer T. C. Tierney shall be
allowed as presented because the claims were not disallowed by
Division Engineer T. C. Tierney in accordance with Rule 26(a)
(System Dockets MW-2979 and MW-2980).
*The initial letters of claim will be reproduced within our
initial submission."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and ail the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute were given due notice of hearing thereon.
Form 1 Award No. 32334
Page 2 Docket No. MW-32027
97-3-94-3-394
The underlying dispute concerns Carrier's contracting of handrail replacement
on two bridges in New Jersey in November, 1992, after service of notice and conference
occurred. Two separate claims were filed by the Organization on January 11, 1993 on
behalf of specifically identified Claimants alleging that such bridge work violated the
Scope Rule of the Agreement.
The instant claim seeks payment of the original claim amounts under the
following provision of Rule 26(a):
"RULE 26 - CLAIMS AND GRIEVANCES
(a) A claim or grievance must be presented, in writing, by
an employee or on his behalf by his union representative to
the Division Engineer or other designated official within sixty
(60) days from the date of the occurrence on which the claim
is based. The Division Engineer or other designated official
shall render a decision within sixty (60) days from the date
same is filed, in writing, to whoever filed the claim or
grievance (the employee or his union representative). When
not so notified, the claim will be allowed."
During the handling of this matter on the property, and again before the Board,
the Organization contends that it never received any response to its January 11, 1993
claims, which resulted in it sending a letter dated July 8, 1993 seeking payment under
Rule 26(a). In its letters confirming the appeal meeting on the claims dated July 23 and
August 5, 1993 respectively, Carrier states its position that a timely denial letter was
issued by the Division Engineer on March 2, 1993. During the processing of this claim
on the property, Carrier never indicated the manner in which the letter was sent to the
Organization nor forwarded a copy of the denial letter to the Organization. Rather, it
stated that "A copy of that letter was received in this office on March 10, 1993 and
therefore further validates that the first level response was within the time limits
prescribed by Rule 26(a)."
The only issue before this Board is the procedural issue of the alleged time limit
violation. The Organization contends that it never received any denial letter and Carrier
asserts that one must have been sent since it had a copy in its Human Resources file
time-stamped March 10, 1993. Carrier included a letter dated March 2, 1993 with a
Form 1 Award No. 32334
Page 3 Docket No. MW-32027
97-3-94-3-394
stamp that the original was signed by Division Engineer Tierney in its record on the
property.
A review of the record, and consideration of the awards cited by both parties,
leads the Board to conclude that the following rationale adopted by it in Third Division
Award 25309 between these parties is equally applicable herein:
"In ruling on this procedural issue, this Board must
consider both precedent and substantial evidence of record.
There is considerable past precedent that it is the
responsibility of Carrier to unequivocally assure that letters
of declination are properly delivered to the appropriate
Organization official within the stated time limits (Third
Division Awards 10173; 11505; 14354; 16163; 25100). With
respect to substantial evidence, this Board has long held that
assertions alone that letters have been mailed will not suffice .
.... Carrier assertions alone that letters were mailed, even
when copies of such letters are produced, do not provide the
necessary evidence required in cases of dispute which come
before this Board (see Third Division Awards 17291, 10173,
10742) .........
Therefore, the claim must be sustained on procedural
grounds ...."
This rationale is particularly appropriate where Carrier failed to produce any
evidence on the property that the March 2, 1993 letter was actually sent or mailed in the
normal course, or what the accepted practice was between the parties for delivery of
declination letters. There is no dispute that the claims were hand-delivered. The only
position Carrier takes in its correspondence on the property is that the apparent receipt
of a copy of the letter by Human Resources which was retained in its files establishes
timely denial. In fact, there is no proof that Carrier ever included copies of the March
2, 1993 declination letters with any of its correspondence to the Organization during
discussion on the property. Such circumstances clearly distinguish this case from those
relied upon by Carrier, which either predate Third Division Award 25309 (see Third
Division Awards 22036, 24232, 22903), are between different parties and rely upon an
established practice for delivery between the parties, see Special Board of Adjustment
Form 1 Award No. 32334
Page 4 Docket No. MW-32027
97-3-94-3-394
1011, Awards 7 & 8; Public Law Board No. 2945, Award 70; Public Law Board No.
3775, Award 55.
Under such circumstances, the claim is sustained on procedural grounds.
AWARD
Claim sustained.
ORDER
This Board, after consideration of the dispute identified above, hereby orders that
an award favorable to the Claimant(s) be made. The Carrier is ordered to make the
Award effective on or before 30 days following the postmark date the Award is
transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 13th day of November 1997.