Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 32365
Docket No. MW-31105
97-3-93-3-132

The Third Division consisted of the regular members and in addition Referee Dana E. Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.
Form 1 Award No. 32365
Page 2 Docket No. MW-31105
97-3-93-3-132

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




This dispute involves two Rules, each of which is unique to this property. Rule 58 states, in pertinent part:












Beginning in the early 1980's, Carrier began downsizing and reorganizing a portion of its property, facilities, and forces. As part of the reorganization program, Carrier instituted a multi-year project of replacing all windows in the Joliet and Gary office buildings. Commencing in 1989, Carrier engaged and utilized an outside contractor, Illinois Sash Erectors, Inc. to perform the window replacement. The last three listed items in the following schedule of work constitute the gravamen of the present dispute:

Form 1 Award No. 32365
Page 3 Docket No. MW-31105
97-3-93-3-132
Year Number of Windows Buildines









No Scope Rule claims were filed by the Organization relative to the 1989 and 1990 Joliet phase of the window project. A Scope Rule claim was filed for the 50 windows at Gary Office Building 160 in 990, but was progressed no further after denial on the property by Carrier's highest designated Labor Relations officer.


On May 1, 1991, Carrier notified the Organization that it was proceeding to contract out the third yearly segment of the window replacement program. At the Organization's request, a meeting was held to discuss the above scheduled repairs. Subsequently, Carrier contracted with Illinois Sash Erectors, Inc. to fabricate and install windows in the three Gary buildings. The purchase order covered "the purchase of and installation of Traco replacement windows" (consisting of aluminum window and screen sashes fabricated at the subcontractor's plant) and custom fit window frames, which were field constructed at the job site.


On September 16, 1991, the Organization submitted a claim for the man-hours "consumed by the contractor." The claim stated, in pertinent part:



Form 1 Award No. 32365
Page 4 Docket No. MW-31105
97-3-93-3-132
employees then took out the old windows and replace them
with new windows. This type work has been done in the Kirk
Yard Camp Building, M of E Department Office Building,
Main Offce Building just to name a few buildings.
This work, however, is the work of the Maintenance of Way
Department, Bridge & Building Carpenters on the Elgin,
Joliet & Eastern Railway Company and has been there (sic)
work for years and years.
Also, this type work is listed in the controlling agreement as
work belonging to the B&B Department Carpenters. Rules
2, 5; 16, 17, 32 and 41 of the controlling agreement in this
case has all been overlooked and or violated by the Carrier.
Therefore, the Organization is requesting that and (sic) equal
proportional share of man-hour spent by these outside
contractors be paid to the Gary Division Bridge & Building
Carpenters for the Agreement violations of the Carrier."

Carrier denied the claim, maintaining that the Organization's claim was untimely presented, in view of "acquiescing" on the following:













Form 1 Award No. 32365
Page 5 Docket No. MW-31105
97-3-93-3-132

Carrier went on to assert that "in view of the above" this claim was barred in accordance with paragraph (c), Rule 59 "Time Limit on Claims and Grievances Rule."


This claim represents a portion of one of the latter phases of a multi-year project.
Even if, areuendo, the Organization's acquiescence in the earlier phase of this window
replacement project and abandonment of the earlier identical claim did not undermine
its belated claim to the 1990 work, precedent Awards of this Division regarding window
replacement work do defeat the claim. See Third Division Awards 31103 and 11104; See
also Third Division Awards 29224 and 29225.







This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 30th day of December 1997.