Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 32865
Docket No. MW-31876
98-3-94-3-211

The Third Division consisted of the regular members and in addition Referee Edwin H. Benn when award was rendered.


(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





Form 1 Award No. 32865
Page 2 Docket No. MW-31876
98-3-94-3-211

FINDINGS :

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




By letter dated September 23, 1992, the Carrier notified the General Chairman as follows:




The Carrier asserts that conference was held on the subject matter of the notice on October 8, 1992. A letter dated October 29, 1992 from the Organization confirms that the parties held a conference.


On December 28,1992, the Carrier entered into an agreement with the contractor for the performance of the work, which commenced January 23, 1993. The project was substantial in nature and duration. The bid on the project was for approximately $1.5 million. According to the Organization, the work was performed ten to 12 hours per day, six days per week According to the Carrier, its forces were not used for the entire project because of the coordination and size of the project.

Form 1 Award No. 32865
Page 3 Docket No. MW-31876
98-3-94-3-211

Claimants Robb and Orsak worked on the project along with the contractor. The other Claimants were also fully employed during the time of the project.









Form 1 Award No. 32865
Page 4 Docket No. MW-31876
98-3-94-3-211



The Carrier's notice and conference obligations were met. The Carrier gave advance notice of its intent to contract the work and the parties met in conference substantially prior to the Carrier's contracting the work.


The Organization makes much of the lost work opportunities for employees on furlough. Initially, that appears to be compelling logic for the assertion that the Carrier should have done more consistent with its obligations under the Hopkins/Berge letter to come up with alternative ways to have furloughed employees perform the work as opposed to reliance upon outside forces. However, while the Organization has leeway in choosing who the Claimants shall be, this claim was not filed on behalf of furloughed employees. This claim was filed on behalf of employees who were working during the time of the claim. Indeed, two of the Claimants worked along with the contractor's forces. Had the Organization sought relief on behalf of furloughed employees, we would have to consider the merits of the arguments that the Carrier could have done more to avoid having to contract the work. But, the Organization did not do so.


This was a very substantial, lengthy and complex project. Claimants were fully employed and no relief was sought on behalf of furloughed employees. The Carrier met its notice and conference obligations. The Organization has not shown how these seven named Claimants who were fully employed (two having worked with the contractor's forces) were realistically denied work opportunities or could have possibly performed this complex and substantial project in addition to their full employment. Under the circumstances of this case, we shall deny the claim.





Form 1 Award No. 32865
Page 5 Docket No. MW-31876
98-3-94-3-211



This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) not be made.


                        NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division


                        Dated at Chicago, Illinois, this 21st day of October 1998.