PARTIES TO DISPUTE:

STATEMENT OF CLAIM:

Form 1

NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION

Award No. 33467
Docket No. MW-32500
99-3-95-3-317

The Third Division consisted of the regular members and in addition Referee Dana E. Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes

(Union Pacific Railroad Company

"Claim of the System Committee of the Brotherhood that:

(1) The Agreement was violated when the Carrier assigned outside






(2) The Agreement was further violated when the Carrier failed to







'***As compensation for loss of work opportunity each Claimant should be paid fifty four and four-fifths (54 4/5) hours at his respective straight time rate of pay and thirty seven and two-fifths (37 2/5) hour and (sic) the

Form 1 Page 2

FINDINGS:

Award No. 33467
Docket No. MW-32500
99-3-95-3-317

time and one-half rate of pay for time worked by outside forces when the Carrier failed to assign Bridge and Building Subdepartment forces the concrete work and construction of a steel building to cover the waste oil treatment plant and related work at La Grande Oregon Yard starting on November 8, 1993. This claim is considered continuous as the building is not finished."'


The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved

herein.



By letter of July 27, 1993, Carrier's Manager Contract Services notified the BMWE General Chairman of Carrier's intent to solicit bids to contract certain work at La Grande, Oregon, specified as ". . . furnishing labor, equipment and materials to perform demolition and associated construction for the waste water treatment plant." General Chairman Wehrli and Carrier Representative Hallberg met in conference on August 3, 1993, to discuss the proposed contracting, following which by letter of August 3, 1993 the General Chairman filed a written protest that "the notice was procedurally defective and the Organization could not reach an Agreement with the carrier to allow it to contract out this work customarily performed by Maintenance of Way employees . . . ." Carrier proceeded to contract with Coleman Industrial &Adams Construction and the demolition and reconstruction work at issue commenced at La Grande on November 8, 1993. Thereafter, the General Chairman filed the instant claim on January 3, 1994, which echoed and expanded upon the allegations contained in his August 3, 1993 letter of protest, including a detailed description of the concrete footing and wall work and steel building fabrication which is claimed under the Scope Rule.

Form 1 Page 3

Award No. 33467
Docket No. MW-32500
99-3-95-3-317

Careful analysis of the record evidence leaves us unpersuaded that the July 27, 1993 letter of notice was procedurally defective or substantively inadequate under Rule 52 (a) or the December 11, 1981 Letter of Agreement. See Third Division Awards 30185, 30063 and 29981. Similarly, the Organization has not carried its burden of persuasion on this evidentiary record with regard to the alleged violation of Rule 1Scope. In that connection, this Board held in Third Division Award 32333 as follows:



See also Third Division Award 32433 . Nothing in the present record provides any basis for deviating from the cited line of authoritative precedent involving these same Parties, the same issues, essentially identical facts and the same contract language.

AWARD

Claim denied.

ORDER

This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimants) not be made.

NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division

Dated at Chicago, Illinois, this 22nd day of September 1999.
.r