PARTIES TO DISPUTE:
STATEMENT OF CLAIM:
Form 1
NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 34986
Docket No. MW-32361
00-3-95-3-204
The Third Division consisted of the regular members and in addition Referee
Robert M. O'Brien when award was rendered.
(Brotherhood of Maintenance of Way Employes
(Consolidated Rail Corporation
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (Steel Processing Services, Inc.) to perform Maintenance of
Way work [remove and/or stockpile jointed rail, plates and other
track materials (OTM)] on the Cherry Tree Secondary Track from
Mile Posts 0.0 to 14.0 and Mile Posts 20.0 to 22.0 beginning May
17 through June 28, 1993 (System Docket MW-3213).
(2) The Agreement was violated when the Carrier assigned outside
forces (Steel Processing Services. Inc.) to perform Maintenance of
Way work [remove and/or stockpile jointed rail, plates and other
track materials (OTM)] on the Cherry Tree Secondary Track from
Mile Posts 0.0 to 14.0 and Mile Posts 20.0 to 22.0 beginning July 26
through August 9, 1993 (System Docket MW-3214).
(3) The Agreement was violated when the Carrier assigned outside
forces (Steel Processing Services, Inc.) to perform Maintenance of
Way work [remove and/or stockpile jointed rail, plates and other
track materials (OTM)] on the Cherry Tree Secondary Track from
Mile Posts 0.0 to 14.0 and Mile Posts 20.0 to 22.0 on August 10
through 16, 1993 (System Docket MW-3215).
(4) The Agreement was violated when the carrier assigned outside
forces (Steel Processing Services, Inc.) to perform Maintenance of
Way work [to sort, classify and/or stockpile the other track
Form 1
Page 2
Award No. 34986
Docket No. MW-32361
00-3-95-3-204
materials (OTM) previously removed from the Cherry Tree
Secondary Track from Mile Posts 0.0 to 14.0 and Mile Posts 20.0
to 22.0] at Mile Post 6.2 on August 9, 10, 11, 12 and 13, 1993
(System Docket MW-3216).
(5) The Agreement was further violated when the Carrier failed to
give the General Chairman prior written notice of its plan to
contract out the work referenced in Parts (1), (2), (3) and (4) above
to outside forces as required by the Scope Rule.
(6) The claim as presented by Vice Chairman D. J. Tredent on July
15, 1993 to Division Engineer R. J. Rumsey (System Docket MW3213) shall be allowed as presented beca
disallowed by Division Engineer R. J. Rumsey in accordance with
Rule 26 (a).
(7) As a consequence of the violations referred to in Parts (1), (5)
and/or (6) above, Messrs. T. J. Peters and D. W. Huffman shall
each be allowed ten (10) hours' pay per day at their respective
straight time rates, with credits for vacation and other benefits for
each of the days worked beginning May 17 through June 28,1993.
(8) As a consequence of the violations referred to in Parts (2) and/or
(5) above, Messrs. T. J. Peters, J. P. Daugherty, D. W. Huffman
and M. E. Slocum shall each be allowed ten (10) hours' pay per
day at their respective straight time rates and all overtime
expended by the outside forces in the performance of said work,
with credits for vacation and other benefits for each of the days
worked beginning July 26 through August 9, 1993.
(9) As a consequence of the violations referred to in Parts (3) and/or
(5) above, Messrs. D. W. Huffman and J.P. Daugherty shall each
be allowed ten (10) hours' pay per day at their respective straight
time rates and all overtime expended by the outside forces in the
performance of said work, with credits for vacation and other
benefits for each of the days worked beginning August 10 through
16, 1993.
Form 1
Page 3
FINDINGS:
Award No. 34986
Docket No. MW-32361
00-3-95-3-204
(10) As a consequence of the violations referred to in Parts (4) and/or
(5) above, Messrs, D. W. Huffman, J. P. Daugherty, M. P. Perry,
J. E. Armagost and R. D. Battaglia shall each be allowed ten (10)
hours' pay per day at their respective straight time rates and all
overtime expended by the outside forces in the performance of said
work, with credits for vacation and other benefits for each of the
days worked beginning August 9 through 13, 1993."
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
herein.
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
Parties to said dispute were given due notice of hearing thereon.
On or about May 16, 1993 the Carrier entered into a contract with Steel
Processing Services, Inc. to remove track from the right-of-way on the Cherry Tree
Secondary Track between Mile Post (MP) 0.00 and 14.0 and MP 20.0 and 22.0. The
contract was entered into on an "as is, where is" basis with the contractor keeping the
scrap rail and other material that it removed from the right-of-way. The contractor
began removing the scrap rail on May 17,1993 and completed the contract on August
13, 1993.
On July 15,1993, the Organization submitted time claims on behalf of Welder
Helper J. Peters and Vehicle Operator D. W. Huffman. It was the Organization's
position that Conrail violated the Scope Rule and Rule 1 of the prevailing Agreement
beginning on May 17, 1993, when it permitted Steel Processing Services, Inc. to
perform work that belonged to Maintenance of Way Employes. The Organization also
argued that Conrail failed to give the General Chairman the requisite notice of this
contracting out of Scope covered work. The Organization requested that the two
Form 1
Page 4
Award No. 34986
Docket No. MW-32361
00-3-95-3-204
Claimants be allowed ten hours of compensation at their applicable rates of pay for
each day that the contractor was performing Maintenance of Way work encompassed
by the Scope Rule.
On September 7, 1993, Division Engineer R. J. Rumsey denied the claim
contending that there was no violation of the BMWE Agreement because the contract
with Steel Processing Services, Inc. was entered into on an "as is, where is" basis.
On September 23,1993, the Organization submitted three additional claims on
behalf of Welder Helpers, Vehicle Operators and Trackmen. Conrail denied those
claims and they were subsequently progressed to the Board for resolution.
It is now well established on the Board that the removal of scrap rail and other
track materials from the shoulder of the track which has been purchased by an outside
contractor/vendor does not come within the Scope Rule of the BMWE Agreement.
Accordingly, the notice that the Carrier must give the appropriate BMWE General
Chairman when it plans to contract out work within the Scope of the Agreement is
inapplicable to these transactions.
For the foregoing reason, the scrap rail and other track material removed and
retained by Steel Processing Services, Inc. on the Cherry Tree Secondary Track from
May 17 to August 13, 1993 was not encompassed by the Organization's Scope Rule.
However, any of that track or material retained by Conrail for its future use was
encompassed by the Organization's Scope Rule and removal of this track and other
track material should have been assigned to Maintenance of Way Employes unless this
work was de minimus. The claims will be remanded to the parties to determine how
much scrap rail and other track material, if any, was retained by Conrail from this rail
removal project.
The Organization further contends that the Division Engineer did not deny the
claim it submitted on July 15, 1993 until September 27, 1993 beyond the 60-day time
limit set forth in Rule 26. Therefore, the claim must be allowed, according to the
Organization.
The evidence reveals that on September 7,1993 Division Engineer R. J. Rumsey
denied the July 15,1993 claim. For some reason, the Organization did not receive this
denial until September 27 when a copy of the September 7, 1993 denial was faxed to
Form 1
Page 5
Award No. 34986
Docket No. MW-32361
00-3-95-3-204
it. However, the Board has no reason to conclude that the September 7 denial of the
July 15, 1993 claim was not sent to the Organization. That decision was rendered
within 60 days from the date the claim was filed. Consequently, there was no violation
of Rule 26 notwithstanding the Organization's contention to the contrary.
AWARD
Claim sustained in accordance with the Findings.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an award favorable to the Claimant(s) be made. The Carrier is ordered to make
the Award effective on or before 30 days following the postmark date the Award is
transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 20th day of September, 2000.