PARTIES TO DISPUTE
:
STATEMENT OF CLAIM
:
Form 1
NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 34995
Docket No. MW-31053
00-3-93-3-34
The Third Division consisted of the regular members and in addition Referee
Martin F. Scheinman when award was rendered.
(Brotherhood of Maintenance of Way Employes
(Burlington Northern Railroad Company (former St. Louis -
( San Francisco Railway Company)
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned four (4) shop
craft employes represented by the Firemen and Oilers to perform
Track Subdepartment work comprised of unloading rail from a train,
removing the angle bars and other track materials, separating them
and reloading them onto another train on September 13 and 14,1990
(System File B-846-1/MWC 90-12-30A SLF).
(2) The Agreement was also violated when the Carrier assigned two (2)
shop craft employes represented by the Firemen and Oilers to
perform Track Subdepartment work comprised of loading the rack
at the welding plant in Springfield, Missouri, on April 9,1991 (System
File B-846-6/MWC 91-06-17).
(3) The Agreement was also violated when the Carrier assigned two (2)
shop craft employes represented by the Firemen and Oilers to
perform Track Subdepartment work comprised of loading the rack
at the welding plant in Springfield, Missouri, on July 16 and 17,1991
(System File B-846-7/MWC 91-10-OS).
(4) The Agreement was also violated when the Carrier assigned three (3)
shop craft employes represented by the Firemen and Oilers to
perform Track Subdepartment work comprised of loading and
unloading rail from trains on October 29 through December 5, 1991
(System File B-846-8/8MWC 92-02-18).
Form 1
Page 2
Award No. 34995
Docket No. MW-31053
00-3-93-3-34
(5) The Agreement was also violated when the Carrier assigned two (2)
shop craft employes represented by the Firemen and Oilers to
perform Track Subdepartment work comprised of loading the rack
at the welding plant in Springfield, Missouri, on January 3 and
January 17, 1992 (System File B-846-9/8MWC 92-05-19).
(6) The Carrier further violated the Agreement when it failed to timely
respond to the initial letter of claim, presented to division General
Manager W. V. Eisenman on February 4,1992, in connection with the
violation referenced in Part (5) above.
(7) The Agreement was also violated when the Carrier assigned two (2)
shop craft employes represented by the Firemen and Oilers to
perform Track Subdepartment work comprised of unloading, loading
and stacking rail at the welding plan in Springfield, Missouri, on
January 22, 23, February 27, 28, March 1, 2, 4, 5, 6 and 7, 1991
(System File B-2451/8MWC 91-05-15).
(8) As a consequence of the violation referred to in Part (1) above,
Foreman T. D. Johannsen, Special Equipment Operator W. T.
Hudgens, Trackmen E. Fisher and H. D. Barger shall each be allowed
pay for twelve (12) man-hours at their respective pro rata straight
time rates of pay.
(9) As a consequence of the violation referred to in Part (2) above,
Foreman T. D. Johannsen and Special Equipment Operator W. T.
Hudgens shall each be allowed pay for three and one-half (3.5) man
hours at their respective pro rata straight time rates of pay.
(10) As a consequence of the violation referred to in Part (3) above,
Foreman T. D. Johannsen and Special Equipment Operator W. T.
Hudgens shall each be allowed pay at their respective pro rata
straight time rates for eight (8) man-hours for each of the two (2)
claim dates and for as long as the violation continues.
(11) As a consequence of the violation referred to in Part (4) above,
Foreman T. D. Johannsen, Special Equipment Operator W. T.
Hudgens and Trackman E. Fisher shall each be allowed pay for 240.7
Form I
Page 3
FINDINGS
:
Award No. 34995
Docket No. MW-31053
00-3-93-3-34
man-hours at their respective pro rata straight time rates of pay and
their applicable overtime rates for all overtime hours worked.
(12) As a consequence of the violation referred to in Parts (5) and/or (6)
above, Foreman T. D. Johannsen and Special Equipment Operator
W. T. Hudgens shall each be allowed pay for ninety (90) man-hours
at their respective pro rata straight time rates.
(13) As a consequence of the violation referred to in Part (7) above,
Foreman T. D. Johannsen and Special Equipment Operator W. T.
Hudgens shall each be allowed pay for fifty-seven (57) man-hours at
their respective pro rata straight time rates and ten and one-half
(10.5) man-hours at their respective time and one-half overtime
rates."
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are
respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute were given due notice of hearing thereon.
As Third Party in Interest, the National Conference of Firemen & Oilers (Service
Employees International Union) was advised of the pendency of this dispute, but chose not
to file a Submission with the Board.
This case involves several claims by the Organization that the Carrier violated the
Agreement by using Shop Craft employees represented by the National Conference of
Firemen & Oilers to perform the work of loading and
unloading rails, and the work of
loading rail onto the feeding rack for the contractor's welding machine. According to the
Organization, the Agreement reserves such work for employees of the classes and groups
Form I
Page 4
Award No. 34995
Docket No. MW-31053
00-3-93-3-34
in which the Claimants hold seniority. It argues that the delegation of such work to
another class of employees, in this case Firemen & Oilers, violates the Agreement.
The Organization disputes the Carrier's contention that the disputed assignments
are consistent with a long-standing past practice. It maintains that the Carrier has not
presented evidence to support the existence of such a practice. Moreover, according to the
Organization, its past acquiescence to de minimus crossings of craft lines did not establish
a practice of assigning Shop Craft employees to perform work contractually reserved to
Maintenance of Way employees.
The Organization asserts that the Claimants lost work opportunities, and are
entitled to receive pay at the rate they would have been paid had the Carrier not violated
the Agreement. The Organization disputes the Carrier's allegation that the Claimants
were fully employed, but argues in any case that a remedy is required to protect the
integrity of the Agreement. With respect to the claim for January 3 and 17, 1992,
described in paragraph (5) above, the Organization asserts that the Carrier did not timely
respond and, in accordance with Rule 90, asserts that the claim must be allowed as
presented.
The Carrier, on the other hand, argues that there has been no violation of the
Agreement. According to the Carrier, the claims merely describe the common practice of
using the crane operated by Shop Craft employees when the crane operated by
Maintenance of Way employees breaks down. According to the Carrier, in such instances,
the Shop Craft crew remains with its crane for safety purposes, while the Maintenance of
Way Crane Operator and Helpers remain under pay. Thus, the Carrier asserts, no
employee has suffered any loss.
According to the Carrier, the practice has been in effect for many years and the
Organization's claims therefore are barred by the doctrine of laches. As to the merits of
the claims, the Carrier maintains that the Organization failed to shoulder its burden of
showing that the disputed work, by custom, practice and tradition, is reserved exclusively
on a system-wide basis to Maintenance of Way employees.
After carefully reviewing the record evidence, we have determined that the claim
must be denied in part and sustained in part.
The Carrier does not contest the fact that the disputed work belongs to Maintenance
of Way employees. Rather, it merely asserts that under extraordinary conditions where
the BMWE-operated crane breaks down, it should be free to utilize a crane operated by
Form 1
Page 5
Award No. 34995
Docket No. MW-31053
00-3-93-3-34
Shop Craft employees on a temporary basis, in order to ensure continued operations, and
as long as the Maintenance of Way employees suffer no loss of pay as a result of the
breakdown.
We agree with the Carrier. Because the utilization of cranes operated by Shop
Craft employees was temporary and occurred only during breakdowns of cranes operated
by Maintenance of Way employees, and because no BMWE-rep resented employee suffered
any loss of pay, we dismiss the claims, with one exception.
We agree with the Organization that the Carrier's response to the Organization's
claim dated February 4,1992 and amended on February 6,1992, File No. B-846-9, was not
timely. According to the record, the Carrier did not respond to the claim until April 12,
1992, more than 60 days after the claim was filed. Accordingly, said claim shall be allowed
as presented.
AWARD
Claim sustained in accordance with the Findings.
ORDER
This Board, after consideration of the dispute identified above, hereby orders that
an award favorable to the Claimant(s) be made. The Carrier is ordered to make the
Award effective on or before 30 days following the postmark date the Award is transmitted
to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 20th day of September, 2000.