Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 35570
Docket No. MW-33417
01-3-96-3-942
The Third Division consisted
of
the regular members and in addition Referee
Dana E. Eischen when award was rendered.
(Brotherhood
of
Maintenance
of
Way Employes
PARTIES TO DISPUTE:
(Soo Line Railroad Company
STATEMENT OF CLAIM:
"Claim
of
the System Committee
of
the Brotherhood that:
(1) The Agreement was violated when the Carrier refused to permit
Machine Operators K. Drabus, M. St. Cyr, J.Northagen, P.
Stenson, D. Melhouse, S. Hunt, F. Scheppler, E. Stenerson, R.
Fiebiger, R. Hendricks, P. Thorp, A. Sundem and E. Samson,
assigned to the tie gang working on the Noyes and Detroit Lakes
Subdivisions, to perform their assigned duties on September 6,1995
and thereafter failed and refused to compensate them for their lost
wages (System File RI.050/8-00243).
(2) As a consequence
of
the aforesaid violation, Messrs.K. Drabus, M.
St. Cyr, J. Northagen, P. Stenson, D. Melhouse, S. Hunt, F.
Scheppler, E. Stenerson, R. Fiebiger, R. Hendricks, P. Thorp, A.
Sundem and E. Samson shall each be ` . . . reimbursed for the
equivalent
of
one-fifteenth
of
his respective monthly rate, less the
amount paid for September 6,1995, and have all overtime, vacation,
fringe benefits, and other rights restored which were lost to them as
a result
of
the above violation."
FINDINGS:
The Third Division
of
the Adjustment Board, upon the whole record and all the
evidence, finds that:
Form 1 Award No. 35570
Page 2 Docket No. MW-33417
01-3-96-3-942
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute were given due notice of hearing thereon.
The Claimants are regularly assigned monthly-rated Machine Operators on the
T1 Tie Gang, which was scheduled in September 1995 to work "compressed work
weeks" of four, ten hour days, Monday - Thursday. After working three and one-half
hours performing tie installation work on Wednesday, September 6,1995, the Claimants
were relieved from duty and sent home by Supervisor Hoban for the balance of that
work day, due to "inclement weather." 1t is not disputed that despite the inclement
weather other members of the T1 Tie Gang were kept on duty performing ballast
unloading work for the,balance of that day.
The Organization presented the instant claim on behalf of these Machine
Operators, asserting a violation of their rights under Rule 26 Forty Hour Week, Rule
32 Reporting and Not Used and Appendix M Compressed Work Week. The Carrier
denied the claims on the basis of the "inclement weather" provisions found in Rule 25
Basic Day-Basic Week, specifically 25(b) and 25(d), infra. The Organization responded
with three counter-arguments: 1) that Rule 25 has no application to monthly-rated
employees like the Claimants, 2) that even if, arEuendo, tie installation could not be
safely performed under the prevailing weather conditions, the Carrier was obligated to
allow the Claimants to perform other work on their machines to fill out the ten-hour
work day, eg, "regular and/or preventive maintenance service," and 3) that the Carrier
was arbitrary and discriminatory in sending the Claimants home while allowing the
other employees to work in the inclement weather.
Each of these Parties cites countervailing authorities from other properties but
the authoritative precedent in this case is found in Third Division Award 33266
involving the same issues, contract language and Parties. Each of the points and
arguments presented in the instant case was definitively answered by the decision in
Award 33266, as follows:
Form 1 Award No. 35570
Page 3 Docket No. MW-33417
01-3-96-3-942
"The Board believes the crucial question in this case is whether Rule 25(d)
supports the Carrier's action.
The Organization maintains that Rule 25(d) is inapplicable to the facts
of
this case because the Rule applies to hourly rated and not monthly rated
employees. However, nothing in the language
of
Rule 25 specifically
confines its application to hourly rated employees. In fact there is no
mention made in the Rule
of
such employees. By contrast Rule 32
of
the
applicable schedule agreement specifically pertains to hourly rated
employees. It was a Rule worded much like that
of
Rule 32 which was
before the Third Division in Award 25183 relied upon by the Organization.
Accordingly, we do not find that Award persuasive with respect to the
question before us. In the final analysis we believe that Rule 25(d) does
apply to monthly rated employees and thus to Claimants in this case.
The Organization also attacks the Carrier's reliance upon Rule 25(d) on
the ground that the Carrier has not proven that the inclement weather on
the claim date created an unsafe situation with respect to Claimants'
performance of their work. We cannot agree. It must be borne in mind
that Claimants' principle duty on the claim date was to lay rail. The fact
that rain was falling supports the inference that for Claimants to perform
such work would have constituted an unsafe condition.
The Organization further attacks the Carrier's reliance upon Rule 25(d)
on the ground that there was additional work Claimants could have
performed on the claim date. However, the Carrier counters with the
allegation that such work had been completed by others by the time the
Carrier decided to send Claimants home. As pertaining to the claim in this
case reveals that the Carrier's argument in its Submission and its oral
argument before the Board is nothing more than an extrapolation of issues
and arguments addressed on the property. Accordingly, the
Organization's argument has no merit. further evidence, the Carrier
emphasizes that there was no overtime on the claim date to any employee
for the performance of such work. The record contains no evidence
refuting these contentions by the Carrier.
Form 1 Award No. 35570
Page 4 Docket No. MW-33417
01-3-96-3-942
Finally, with respect to Rule 25(d) the Organization points out that other
employees, including members
of
Claimants crew, were retained in service
for their entire scheduled tour
of
duty while Claimants were sent home
after three hours. However, there is no evidence or allegation that such
employees laid rail after Claimants were sent home. Moreover, as noted
above, all duties other than laying rail which Claimants could have
performed were completed by the time they were sent home. At least there
is no evidence to the contrary.
Nevertheless, the Organization argues that the Carrier was obligated to
find work for Claimants in order that they could complete their ten-hour
tour of duty on the claim date. We do not believe this argument has any
merit in view of the clear terms of Rule 25(d).
In the final analysis we must conclude that the claim in this case is without
agreement support."
We find no factual or contractual bases for distinguishing the instant case from
that which was decided in Award 33266 and for the reasons set forth therein we will
likewise deny the present claim.
AWARD
Claim denied.
ORDER
This Board, after consideration ofthe dispute identified above, hereby orders that
an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 24th day of July, 2001.