Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 35570
Docket No. MW-33417
01-3-96-3-942

The Third Division consisted of the regular members and in addition Referee Dana E. Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
Form 1 Award No. 35570
Page 2 Docket No. MW-33417
01-3-96-3-942

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The Claimants are regularly assigned monthly-rated Machine Operators on the T1 Tie Gang, which was scheduled in September 1995 to work "compressed work weeks" of four, ten hour days, Monday - Thursday. After working three and one-half hours performing tie installation work on Wednesday, September 6,1995, the Claimants were relieved from duty and sent home by Supervisor Hoban for the balance of that work day, due to "inclement weather." 1t is not disputed that despite the inclement weather other members of the T1 Tie Gang were kept on duty performing ballast unloading work for the,balance of that day.


The Organization presented the instant claim on behalf of these Machine Operators, asserting a violation of their rights under Rule 26 Forty Hour Week, Rule 32 Reporting and Not Used and Appendix M Compressed Work Week. The Carrier denied the claims on the basis of the "inclement weather" provisions found in Rule 25 Basic Day-Basic Week, specifically 25(b) and 25(d), infra. The Organization responded with three counter-arguments: 1) that Rule 25 has no application to monthly-rated employees like the Claimants, 2) that even if, arEuendo, tie installation could not be safely performed under the prevailing weather conditions, the Carrier was obligated to allow the Claimants to perform other work on their machines to fill out the ten-hour work day, eg, "regular and/or preventive maintenance service," and 3) that the Carrier was arbitrary and discriminatory in sending the Claimants home while allowing the other employees to work in the inclement weather.


Each of these Parties cites countervailing authorities from other properties but the authoritative precedent in this case is found in Third Division Award 33266 involving the same issues, contract language and Parties. Each of the points and arguments presented in the instant case was definitively answered by the decision in Award 33266, as follows:

Form 1 Award No. 35570
Page 3 Docket No. MW-33417
01-3-96-3-942




Form 1 Award No. 35570
Page 4 Docket No. MW-33417
01-3-96-3-942




We find no factual or contractual bases for distinguishing the instant case from that which was decided in Award 33266 and for the reasons set forth therein we will likewise deny the present claim.







This Board, after consideration ofthe dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 24th day of July, 2001.