Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 35735
Docket No. MW-33422
01-3-96-3-785

The Third Division consisted of the regular members and in addition Referee Dana E. Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE: (Union Pacific Railroad Company (former Chicago & ( North Western Transportation Company)

STATEMENT OF CLAIM:






FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
Form 1 Award No. 35735
Page 2 Docket No. MW-33422


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The Scope Rule of the governing Agreement and the applicable provisions of the so-called Berge- Hopkins Letter Agreement of December 11,1981 read in pertinent part as follows:






Form 1 Award No. 35735
Page 3 Docket No. MW-33422






Form 1 Award No. 35735
Page 4 Docket No. MW-33422


The facts giving rise to the instant claim are not in material conflict in the record before us. Thus, it is undisputed that by letter dated April 5, 1995, Carrier's Assistant Vice-President Labor Relations-Non-Operating sent the BMWE General Chairman written Notice of Intent to subcontract out certain work in connection with crossing renewals, as follows:

    "Please accept this as the Carrier's notice required under Rule 1(b) of the BMWE Agreement of our intention to sub-contract certain work in the connection with crossing renewal projects. Specifically, the Carrier intends to use contractors to perform asphalt paving in connection with crossing rehabilitation projects. Crossing renewals are being performed in conjunction with state highway departments, along with projects of various cities and counties. The work to be performed by a contractor involves the laying and paving of asphalt at crossing locations that intersect with various streets, highways, etc. We will also require, at some locations, to have the contractor use concrete saws, concrete breakers and vibratory rollers in order to handle the work that the Transportation Company is not experienced in and for which it does not have the equipment. Chicago and North Western forces will perform all work related to track rehabilitations, such as surfacing and placing of flange rails. In most cases, the work will be performed at the direction and, in some cases, at the cost of outside agencies."


Nor is it disputed that the BMWE General Chairman promptly responded by letter of April 11, 1995, reading in pertinent part as follows:

    "Please refer to your April 5, 1995 letter received by this office on April 11,1995 wherein you advise of the Carrier's intention to subcontract work in the connection with crossing renewal projects.


    The Brotherhood requests an immediate conference of this notice in an effort to reach an understanding in accordance with Rule 1 scope, Section (b), Paragraph 3. It is imperative the Brotherhood be able to present its position BEFORE the Carrier commits itself to using outside contractors.


    Rule 1(b), Paragraph 2 provides in pertinent part: `*** However, such work may only be contracted provided that special skills not possessed by

Form 1 Award No. 35735
Page 5 Docket No. MW-33422
                                              01-3-96-3-785


      the Company's employes, special equipment not owned by the Company, or special material available only when applied or installed through supplier, are required; or unless work is such that the Company is not adequately equipped to handle the work; or, time requirements must be met which are beyond the capabilities of Company forces to meet.' The April 5, 1995 Notice has failed to clearly identify any circumstances or positions which legitimately falls within these five enumerated exceptions."


Notwithstanding the Carrier's manifest and acknowledged notice/confer responsibility under the above-cited Agreement provisions and despite meeting its notice obligation, the Carrier inexplicably ignored the General Chairman's request for a conference and simply subcontracted the asphalt paving preparation work at issue in this claim. It is undisputed that, without even acknowledging let alone acceding to the General Chairman's plainly worded invocation of the Organization's right to a precontracting confere to perform paving removal, paving and related clean-up work at the Main Street Crossing, Glen Ellyn, Illinois, during the period April 17 through 23,1995. The Carrier did not dispute that four employees of the outside contractor utilized ordinary Maintenance of Way equipment such as a backhoe and dump trucks to perform the grade crossing repair work. Such work consisted of breaking and removing old asphalt, concrete and roadbed using a backhoe tractor equipped with a breaker attachment on April 17 through 23,1995 and utilizing contractor owned dump trucks to haul away the spoil from the crossing. Nor was the question that a pre-contracting good faith conference is required in such a situation ever persuasively contested on this record.


The Carrier's procedural objection to an alleged improper change in the nature of the claim is not only de novo but misplaced, because the claim perfected on the property and appealed to the Board plainly grieves the refusal/failure of the Carrier to grant the General Chairman's timely and unambiguous request for a pre-contracting conference. In denying the claim, the Carrier also pointed out that some prior arbitration tribunals have found adequate justification for contracting out such work due to time constraints, lack of equipment or inadequate manpower. But none of those precedents involved a complete and unmitigated failure or refusal to grant a timely, contractually mandated request for a pre-contracting conference which, by mutual intent of the contracting Parties, is supposed to be a forum for good faith discussion of

Form 1 Award No. 35735
Page 6 Docket No. MW-33422
                                              01-3-96-3-785


precisely these kinds of issues that could have and should have been discussed at the requested conference in this case. Finally, notwithstanding the Carrier's defense that the Claimant's were "fully employed" on claim dates, their loss of work opportunity coupled with the blatant, unexplained and unmitigated violation of the Carrier's acknowledged contractual obligation to meet and confer with the General Chairman before contracting out the work warrants a sustaining award by the Board. See Third Division Awards 31752, 31754, 31755, 31756, 31760, 31777.


                        AWARD


      Claim sustained.


                          ORDER


This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                        NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division


                        Dated at Chicago, Illinois, this 24th day of October, 2001.