Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 35762
Docket No. MW-33734
01-3-97-3-192
The Third Division consisted
of
the regular members and in addition Referee
Barry E. Simon when award was rendered.
(Brotherhood
of
Maintenance
of
Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM:
"Claim
of
the System Committee
of
the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces to perform Maintenance
of
Way work (forming and pouring
concrete pads) along the Engine Pit Track at Frankford Junction,
Philadelphia, Pennsylvania on August 28, 1995 and continuing
(System Docket MW-4153).
(2) The Agreement was violated when the Carrier assigned outside
forces to perform Maintenance
of
Way work (installing ties,
changing bolts and joint bars and cutting weeds) on the Engine Pit
Track at Frankford Junction, Philadelphia, Pennsylvania on August
28, 1995 and continuing (System Docket MW-4154).
(3) The Agreement was further violated when the Carrier failed to give
the General Chairman advance written notice
of
its intent to
contract out the work referred to in Parts (1) and (2) above.
(4) As a consequence
of
the violations referred to in Parts (1) and/or (3)
above, Messrs. W. W. Trexler, G. A. Golden, J. L. Royer, M. D.
Tallarida and E. W. Volbrig shall each be allowed eight (8) hours'
pay at their respective rates
of
pay for each day the outside forces
performed the work described in Part (1) above beginning August
28, 1995 and continuing until the violation ceased.
Form 1 Award No. 35762
Page 2 Docket No. MW-33734
01-3-97-3-192
(5) As a consequence
of
the violations referred to in Parts (2) and/or (3)
above, Messrs. K. A. Wunderlich, D. A. Sabo, M. J. McCarthy, W.
A. Cropper, G. F. Warren and C. E. Miller shall each be allowed
eight (8) hours' pay at their respective rates
of
pay for each day the
outside forces performed the work described in Part (2) above
beginning August 28, 1995 and continuing until the violation
ceased."
FINDINGS:
The Third Division
of
the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21, 1934.
This Division
of
the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute were given due notice
of
hearing thereon.
The record in this case indicates the Carrier had leased .74 acres and 390 feet
of
track at Frankfort Junction to Tanner Industries. The lessee apparently performed or
contracted with a third party to have it perform certain work that the Organization
argues was reserved to employees under the scope
of
the Agreement. There is no
indication that any of this work was performed on property not subject to the leasehold,
or was performed for the benefit of the Carrier.
The Organization objects to the Carrier's citation of the lease, arguing it was not
furnished with a copy of the lease. The record shows, however, that the Organization
was permitted to examine the lease in the Carrier's office. We do not agree that the
Carrier was obligated to give the Organization a copy of the lease, as long as it had the
opportunity to inspect it to determine the limits of the leasehold and other items that
might be relevant to the Organization's objective of enforcement of the Agreement. In
Third Division Award 29515, involving these parties, the Board held:
Form 1 Award No. 35762
Page 3 Docket No. MW-33734
01-3-97-3-192
"This is a contracting out case which turns on the issue of whether or not
the tracks on which the work was performed by the contractor was under
the control of Carrier or leased to another enterprise at the time that the
disputed work was performed. Carrier, from the outset, maintained that
the track was leased, and while it refused to furnish the Organization with
a copy of the lease because of confidentiality considerations it did make a
copy available for inspection by the Organization. The Organization did
not avail itself of the inspection opportunity.
The failure of the Organization to take advantage of the opportunity to
inspect the lease flaws its argument that the trackage on which the
contractor worked was under the control of Carrier. Accordingly, in these
circumstances the Board must accept Carrier's position as correct."
Based upon the facts of record, the Board does not find that the Agreement was
violated.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders that
an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 24th day of October, 2001.