Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36093
Docket No. MW-34973
02-3-98-3-731
The Third Division consisted of the regular members and in addition Referee
Dana Edward Eischen when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(CSX Transportation, Inc.
( (former Clinchfield Railroad)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (Progress Rail) to perform Track Subdepartment work
(picking up rail, tie plates, rail bars, spikes, bolts and scrap)
between Mile Post 173 (Kona, North Carolina) and Mile Post 93
(Kingsport, Tennessee) on June 23 through August 15,1997 and at
Mile Post 01 (Elkhorn City, Kentucky) beginning on August 18,
1997 and continuing [Carrier's File 12(97-2579) CLR].
(2) The Agreement was violated when the Carrier assigned outside
forces (Progress Rail) to perform Track Subdepartment work
(cutting up continuous welded rail) at Mile Post 148.5 to Mile Post
93, Kingsport, Tennessee on June 30 through August 8, 1997
[Carrier's File 12(97-2580)].
(3) The Agreement was further violated when the Carrier failed to
furnish the General Chairman with a proper advance written notice
of its intent to contract out the work described in Parts (1) and (2)
above and to make a `good-faith' effort to reduce the incidence of
contracting out scope covered work and increase the use of its
Maintenance of Way forces as required by Rule 48 and the
December 11, 1981 Letter of Understanding.
Form 1 Award No. 36093
Page 2 Docket No. MW-34973
02-3-98-3-731
(4) As a consequence
of
the violations referred to in Parts (1) and/or (3)
above, Messrs. M. L. Thomas, C. Edwards, W. L. Lasley and R. L.
Stephens shall each be compensated at their respective and
applicable rates
of
pay for an equal proportionate share
of
the total
man-hours expended by the outside forces in the performance
of
the
work in question beginning June 23, 1997 and continuing until the
violation ceased.
(5) As a consequence
of
the violations referred to in Parts (2) and/or (3)
above, Messrs. B. R. Peterson and R. E. White shall each be allowed
two hundred eighty (280) hours' pay at their respective pro rata
rates."
FINDINGS:
The Third Division
of
the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning
of
the Railway Labor Act, as
approved June 21, 1934.
This Division
of
the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute were given due notice
of
hearing thereon.
It is not unprecedented for this Division and other Board tribunals to permit the
combination of separate but factually linked claims into a single contract interpretation
dispute, in the interests of administrative efficiency and economy. See, First Division
Awards 24530 and 25212, as well as Third Division Award 31546. In these two claims,
which were consolidated on appeal to the Board, the Organization asserts Scope Rule
violations during Summer 1997 when employees of Progress Rail performed track and
related right-of-way maintenance work on the Appalachian Service Lane:
i.e.,
from
June 23 through August 15, 1997, four Progress Rail employees picked up rail, tie
plates, rail bars, spikes, bolts and scrap between Mile Post 173 (Kona, North Carolina)
and Mile Post 93 (Kingsport, Tennessee); commencing on Aug st 18, 1997 and
Form 1 Award No. 36093
Page 3 Docket No. MW-34973
02-3-98-3-731
continuing four Progress Rail employees picked up rail, tie plates, rail bars, spikes,
bolts and scrap at Mile Post 01 (Elkhorn City, Kentucky); from June 30 through August
8, 1997, the two Progress Rail employees cut up continuous welded rail at Mile Post
148.5 to Mile Post 93, Kingsport, Tennessee.
When challenged by the Organization with these factually related claims, the
Carrier responded that the work in question was no longer subject to the Scope Rule
of
the Agreement because Progress Rail had made an "as is, where is" purchase
of
the
track materials as scrap and was merely picking up its own purchased property. It is
well recognized in the precedent decisions
of
the Board that when a bona fide and
properly proven "as is, where is" purchase occurs, the purchased materials pass out
from under the Carrier's dominion and control and the Carrier is thus relieved
of
its
Scope Rule obligations relative to such materials, including the notice and conference
requirements of Rule 48 and the December 11,1981 Letter Agreement. See, e.g., Third
Division Award 34986. However, this line of cases also establishes that a plea of an "as
is, where is sale" is an affirmative defense, which the Carrier has the burden of
persuasively proving on the property if it is to prevail before the Board. See Third
Division Awards 19623, 20230, 20895, 25402, 28229, 28430, 28759, 29059, 30661, 31521,
31619, 31754, 32278, 32320, 32335 and 32858. Thus, this case narrows to the question
whether, in the facts and circumstances of this record, the Carrier produced during onproperty handling sufficient probative evidence to persuasively establish its affirmative
defense of an "as is, where is" sale of those track and related materials which Progress
Rail employees dismantled and/or picked up on the dates encompassed by these claims.
When the Organization asked for evidence in support of the asserted "as is, where
is" defense, the Carrier initially provided a copy of an undated and uneaecuted
"purchase order," which it subsequently withdrew and replaced with a different undated
uneaecuted purchase order much later in the claims appeal process. Throughout
handling on the property, however, the Carrier adamantly refused to produce or even
allow the Organization (and thus the Board) to inspect the underlying contract which
it had allegedly entered into with Progress Rail Services, Corp. in April 1997, for the
purchase and removal of the material in dispute. In that connection, the following
statement in a letter dated October 5, 1998 from Director Employee Relations J. H.
Wilson to BMWE General Chairman T. R. McCoy, Jr. is illustrative of the Carrier's
position:
Form 1 Award No. 36093
Page 4 Docket No. MW-34973
02-3-98-3-731
"The request for a copy of the sales contract with Progress Rail is
respectfully declined. We have never provided such a contract; we have
only provided sales orders, yet no previous claim involving 'where is, as is'
sales of scrap material to Progress Rail by CSXT has been progressed past
conference denial by your Organization. Nevertheless, you now contend
that failure to provide a copy of that contract is an admission that the
materials were not sold as alleged, that they remained carrier property,
and that the Agreement was violated.
We disagree entirely. We are under no obligation to provide copies of
proprietary documents to you, and our refusal to turn over the document
you request is not an admission of anything. In fact, other than to prove
that the terms of the sale are `as is, where is,' the contract could not prove
that the scrap involved in this claim was sold to Progress Rail. In that
respect, the attached sales order is the best evidence and is certainly
sufficient to prove our affirmative defense that the materials were sold `as
is, where is' to Progress Rail. As previously noted, you have accepted the
sales orders as probative evidence in every previous case; obviously, you
believed they were suffcient before, and your request for the contract is
obviously a fishing expedition at the direction of the BMWE national office
in Chicago."
That the Carrier itself relied for its affirmative defense on this underlying
contract with Progress Rail, rather than unsigned, undated and non-specific "sales
orders" which may or may not apply to the materials, work and locations at issue in
these claims, is borne out by the following opening sentences of the Statement of Facts
in the Carrier's Submission to the Board:
"Effective April 23, 1997, the Carrier entered into a contract with
Progress Rail Services, Inc. in which Progress Rail purchased retired rail
and other related track materials. On the dates in question, Progress
entered Carrier's right-of-way and began removal of its property."
In Third Division Award 30971, involving these same Parties, the Board sustained
a virtually indistinguishable claim when another component road of the Carrier (former
Seaboard Coastline Railroad Company) asserted "confidentiality" or "proprietary
interest" for refusing to produce an alleged "as is, where is" contract of purchase upon
Form I Award No. 36093
Page 5 Docket No. MW-34973
02-3-98-3-731
which it based its affirmative defense. The following rationale from Award 30971
applies equally in this case:
"Belated assertions
of
'confidentiality' are
of
no comfort to Carrier in this
situation. Carrier cannot have it both ways,
if
it asserts an `as is where is'
defense, it must provide the Organization and this Board with sufficient
information to support that assertion."
In the face
of
that on-property dating from July 26, 1995, the Carrier took and
lost a calculated risk when it refused to provide for the record a copy of the Progress
Rail Services purchase contract which was the basis of its affirmative defense in the
instant case. Based upon the failure of proof on the "as is, where is" affirmative defense,
Parts 1, 2, 4 and 5 of the claim must be sustained.
AWARD
Claim sustained in accordance with the Findings.
ORDER
This Board, after consideration ofthe dispute identified above, hereby orders that
an award favorable to the Claimant(s) be made. The Carrier is ordered to make the
Award effective on or before 30 days following the postmark date the Award is
transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 22nd day of July 2002.