Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36156
Docket No. MW-34931
02-3-98-3-668

The Third Division consisted of the regular members and in addition Referee Dana Edward Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE: (Burlington Northern Santa Fe (former Burlington ( Northern Railroad Company)

STATEMENT OF CLAIM:
















FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.


Form 1 Award No. 36156
Page 2 Docket No. MW-34931

02-3-98-3-668 Under date of June 14,1994, the Carrier presented the General Chairman with a notice of its intention to utilize outside forces to perform the work of constructing a Roadway Work Equipment Building at Alliance, Nebraska. That notice described the work which the Carrier proposed to subcontract, as follows:












In the July 18, 1994 conference held in accordance with the Note to Rule 55, the General Chairman and the Carrier's representatives discussed the Carrier's reasons for wishing to contract out that described work. However, because the notice made no reference whatsoever to water or sewer line work, there was no discussion of that subject. When no Agreement was reached concerning the construction Work Equipment Building, the Carrier went forward with the contracting out. After the Claimants reported to the General Chairman that the outside forces were in fact performing such water and sewer line work, the Organization filed the instant claim which remained unresolved on the property.


In all such cases, it is critically important to focus as specifically as the evidentiary record permits on the work that is the subject of the contract violation. In this particular case, the generically described work of installation of water and sewer line in Alliance, Nebraska Yards beginning September 6,1994 and continu ing was described with particularity and never refuted by the Carrier, in a letter from Claimant Sherlock to General Chairman Joynt, dated December 21,19%, as quoted in the General Chairman's letter of January 8,1998, to Director -Labor Relations D. J. Merrell:






Form 1 Award No. 36156
Page 3 Docket No. MW-34931






























As the handling on the property plainly shows, the crux of this case is that the Carrier's June 14, 1994 notice makes no reference at all to its intent to subcontract the installation of water and sewer line water work in connection with the construction of the Roadway Work Equipment Building at Alliance, Nebraska. Nor was the subcontracting of water and sewer line installation ever mentioned or discussed during the ensuing conferences requested by the
Form 1 Award No. 36156
Page 4 Docket No. MW-34931


General Chairman. In that connection, the following facts and arguments set forth in the General Chairman's January 8, 1998 appeal of the claim denials are not effectively refuted by the Carrier:








- Construct an Asphalt Parking Lot.
















For its part, the Carrier urged that the General Chairman should have "assumed" that water and sewer line installation was encompassed in the above-quoted June 14,1994 notice and/or that during the ensuing conference the Organization representatives were obliged to ask whether the Carrier intended to subcontract such water and sewer line installation work. We do not find the Carrier's position tenable because the plain intent of the Note to Rule 55
Form 1 Award No. 36156
Page 5 Docket No. MW-34931



and Appendix Y is to place on the Carrier the duty of disclosure in such a case, so that the Organization can make an informed judgment about exercising its conference rights and the Parties can make a good-faith effort to reach a meeting of the minds.


It would be contrary to the manifest mutual intent of the contracting Parties for the Board to accept the Carrier's theory that it can transform its contractual duty of full disclosure and good faith discussion into an obligation on the Organization to interrogate the Carrier about subject matters not reasonably included in the notice served by the Carrier. In that regard, the record amply demonstrates that in other such new construction cases the Carrier has served and discussed advance disclosure notices, inclusive of water and sewer work, prior to subcontracting. In this case, the Carrier's failure to do so effectively precluded any possibility of discussion of the Carrier's reasons for subcontracting the water and sewer service work now in dispute and thus prevented good faith effort to reach an understanding concerning the contracting out of that work. For that reason, we shall sustain this claim.


                        AWARD


      Claim sustained.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 20th day of August 2002.