The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
A diesel spill occurred on the Carrier's property at Norden, California, Mile Post 192 of the Sacramento Subdivision on February 26,1997. Approximately 17,000 gallons of diesel fuel were spilled on the ground. Given this emergency situation, the Carrier employed an outside contractor (Erickson Environmental) to contain, control and clean up the diesel fuel spill. Beginning February 28, 1997 the Carrier assigned Maintenance of Way forces to join the contractor in the work. This continued through May 15,1997.
On May 16, 1997, however, the Carrier's forces were reassigned from this duty and returned to other assignments. The contractor's forces continued work at the site through August 31, 1997. The claim here under review concerns this period. The Organization notes the failure of the Carrier to provide advance notice of that portion of the contracting that commenced on May 16, 1997, and contends that the remaining work could and should have been assigned to Carrier forces.
It may be reasonably inferred that the Carrier could have given a 15-day advance notice of its intention to discontinue use of Carrier forces on May 15, 1997. This, however, would hardly have been a notice of planned (that is, future) contracting of work, because the contractor was already in place. The record fails to show whether the nature of the work performed by contractor forces beginning May 16, 1997 differed in any way from that which they performed for the two and one-half months preceding that date. Because there was no claim as to the earlier period, the Organization's argument as to improper assignment of scope-covered work is not persuasive.
Sustaining Third Division Award 31997, cited by the Organization, gives additional credence to this point. The circumstances in Award 31997 were that a Maintenance of Way Gang was assigned to commencework on structural repairs to two bridges. The Gang was then removed from this assignment; the Carrier gave notice of its intention to contract out this work; and the Carrier then assigned a contractor to the Form 1 Award No. 36162
work prior to the requisite 15-day period. As a result, the Organization had established that the Gang was capable of the work (because the Gang had been assigned to it) and that the Carrier had not met the 15-day advance notice requirement. Here, the contractor was assigned under emergency circumstances (in the face of an unanticipated diesel fuel spill) and the use of Carrier forces was supplementary.
This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.