Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36202
Docket No. SG-36279
02-3-00-3-504

The Third Division consisted of the regular members and in addition Referee Nancy F. Eischen when award was rendered.

(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE:



STATEMENT OF CLAIM:



FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.


Form 1 Award No. 36202
Page 2 Docket No. SG-36279
02-3-00-3-504

This dispute concerns the Carrier's use of System Signal Construction Gangs ("System Gangs") to work with a Maintenance of Way System Production Tie and Surfacing Gang ("Tie Gang") from August 14 to September 27,1999.


Specifically, 23 employees from three System Gangs were assigned to work in conjunction with the Tie Gang installing new ties and surfacing track on District 9 of the former L&N Railroad. The work performed by the System Gang signals and signal apparatus, and cleaning up and hauling scrap material.


Of note, the Organization asserts that General Chairman Wilson filed a claim with regard to the above work on December 13,1999. However, the Carrier maintains that there is no record of the December 13, 1999 correspondence. Thereafter, the General Chairman filed an appeal alleging that Rules 31, 32 and 51 were violated when the System Gangs were used to work in conjunction with the Tie Gang from August 14 to September 27,1999.


Specifically, the General Chairman maintained that the System Gangs were "precluded" from performing the "routine maintenance work" and further maintained that the amount paid to System Gang personnel($47,252) should be evenly divided and paid to the 23 employees working District Signal positions on Seniority District 9. Finally, the General Chairman contended that the claim was a "continuous claim" to include "all dates following those listed that these System Gangs are used in violation of the Agreement rules." Finally, the General Chairman maintained that the Organization's position was supported by past practice, citing letter Agreements from 1968 and 1984.


The Carrier denied the claim contending that pursuant to Rule 51, it has the right to use system construction forces to perform any construction work which is defined as work that involves the installation of new equipment and systems and the major revision of existing systems, not the normal routine maintenance required to have existing systems operating at maximum efficiency. Furthermore, the replacement of existing systems may also be considered construction work. It further noted that the work at issue involved a major revision to the existing track structure and signal system, as evidenced by the Organization's contention that as many as 23 employees suffered a loss of work opportunity, which clearly demonstrated the work at issue could not be considered "normal maintenance."


This dispute is one of three claims submitted by the Organization, each of which involves the same issues, Claimants and work project, and differ only with respect to the claim dates. For the reasons set forth more fully in companion Third Division Award 36206, this claim is denied.

Form 1 Award No. 36202
Page 3 Docket No. SG-36279
02-3-00-3-504



      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimants) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 24th day of September 2002.