Form 1

NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION

Award No. 36280
Docket No. MW-35493
02-3-99-3-401

The Third Division consisted of the regular members and in addition Referee Richard Mittenthal when award was rendered.

(Brotherhood of Maintenance of Way Employes

PARTIES TO DISPUTE:

(Burlington Northern Santa Fe Railway
( (former St. Louis-San Francisco Railway Company)

STATEMENT OF CLAIM:

"Claim of the System Committee of the Brotherhood that:



D. J. Brewer
W. L. Fish
R. L. Chance
E. Hoffman
M. A. Hosiner
G. A. Owens
D. L. Eden
J. R. Philpot

W. E. Bentch
D. L. Dail
T. P. Lowder
D. L. Crisp
L. A. Reynolds
D. J. Smith
R. C. Graves
J. D. Neece
Form 1 Award No. 36280
Page 2 Docket No. MW-35493
02-3-99-3-401
J. H. Holland R. E. Haile
J. M. Simpson J. S. Wiliams"

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The Carrier advised the General Chairman on August 3,199'1, that it wished to contract out "the new construction of the extension of a siding between MP 385.82 and MP 387.62 at Hogan, Arkansas." It contemplated that the following work would be done by contractors: grading (85,000 cubic yards, compacted); seeding (3 acres); topsoil (7,000 cubic yards); subballast (10,900 cubic yards, compacted); fence installation (1,000 feet of ROW fence; bridge construction (a 100-foot long concrete "T" girder bridge); and various culvert extensions and crossings. It anticipated that the contractors would begin the job on August 20, 1997. Equally important, its notice called for BMWE-represented employees to install 9,600 feet of new track including ties, ballast, surface, and two turnouts.


Discussions of the proposed contracting out were held between the parties. The Organization believed that much, perhaps all, of the "dirt work" should be done by Carrier employees rather than a contractor. It was referring apparently to the grading, subballast and other work in creating a foundation for the new siding extension. These discussions did not produce an agreement. The contractors, principally Gilbert Central, began work on this job in late August. The Organization grieved, alleging that the "dirt work" involved "fundamental and basic . . . track construction work" which had been "customarily assigned to and performed by Carrier employees." It stressed that its Special Equipment Operators and Truck Drivers were capable of manning all

Form 1 Award No. 36280
Page 3 Docket No. MW-35493
02-3-99-3-401

the equipment involved in the "dirt work" and that they, along with the Carrier's Foremen, Laborers and Mechanics, could do much larger portions of the project than they had been assigned to do. None of these arguments persuaded Management to alter its original plan.


The record in this case fails to establish that the type of work in question has been done exclusively by BMWE-represented employees in the past. Such work no doubt has been assigned to employees on occasion, but it has been assigned as well to contractors. Given these circumstances, the Organization's claim is without merit.






- ORDER

This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the CIaimant(s) not be made.