Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36282
Docket No. MW-35495
02-3-99-3-400

The Third Division consisted of the regular members and in addition Referee Richard Mittenthal when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:



STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Form 1 Award No. 36282
Page 2 Docket No. MW-35495
02-3-99-3-400



The Carrier notified the General Chairman on July 27, 1997, that it intended to contract out "the new construction of the extension of the switching lead at Harvard Yard in Harvard, Arkansas." It contemplated that the following work would be done by contractors: embankment (15,932 cubic yards, compacted); install row fencing (3,900 feet); excavation (67,575 cubic yards); clearing and grubbing (1.8 acres); subballast (4,468 cubic yards, compacted); and drainage (install 60-inch CMP). It anticipated that the contractors would begin this job no later than August 13,1997. Equally important, its notice called for BMWE-represented employees to install 3,750 feet of new track including ties, ballast, surface, and one turnout along with relocation of three existing turnouts with new switch tie packages and installation of a concrete grade crossing.


Discussions of the proposed contracting out were held. But the Organization was unable to persuade the Carrier to assign the other portions of the project, particularly the "dirt work," to the Carrier's employees. A grievance followed.


This case is closely related to the dispute in Third Division Award 36280. It presents much the same evidence with respect to essentially the same issue. The Board finds, as it did in Third Division Award 36280, that the record fails to establish that the type of work in question has been done exclusively by Carrier employees in the past. Such work has no doubt been assigned to such employees on occasion, but it has also been assigned to contractors. Given these circumstances, the Organization's claim is without merit.




      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 28th day of October 2002.