The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
The West Switching Yard in Eola, Illinois, was flooded in the summer of 1996. The Carrier determined there was an immediate need for flood repair and improved drainage. It regarded the situation as an "emergency" and engaged a contractor for this project. Ditching and dirt-leveling through the use of such equipment as a backhoe, bulldozer, bobcat loader and dump truck was involved. The contractor used a specially modified backhoe which the Carrier claims it did not possess and could not lease. Form 1 Award No. 36285
The record is far from clear on many of the details in this case. But sometime in October 1996, perhaps earlier, the contractor left the project and was replaced by Carrier employees who continued with the ditching and dirt-leveling through the use of Carrier equipment. Then, on November 12, 1996, the contractor returned and the Carrier employees were removed and assigned to other work. The Carrier alleges it gave telephone notice of the original contracting out to the Organization in the summer months, but was unable to produce any tangible evidence of such notice. It admittedly gave no notice to the General Chairman at the time the contractor returned to the project on November 12.
The Organization alleges that the work in question belonged exclusively to Carrier employees and that, in any event, the Carrier failed to provide the General Chairman with the necessary contracting out notice. The Carrier contends the Organization failed to show such work had been done in the past exclusively by BMWE-represented employees and insists it had no notice obligation in these circumstances. It asserts moreover that an "emergency" condition and the contractor's specialized equipment justified its choice of a contractor and that the Organization's claim was not presented within the pertinent 60-day time limit.
The parties agree that the "date of the occurrence" was November 12, 1996, apparently the day the employees were removed from the project and the contractor returned. The parties agree also that the 60-day period began as of November 13, the day following the "occurrence." They agree further that the 60-day period ended on January 11. 1997. The Organization placed the claim in question in the mail on January 11. 1997. The Carrier received the claim the morning of January 13. 1997. According to the Organization, the claim was "presented in writing..." to the Carrier on January 11 when it placed the claim in the hands of the U. S. Postal Service. It a rges therefore that the claim was timely filed. According to the Carrier, the claim was not "presented in writing..." to the Company until it was received by a Carrier Officer on January 13. It urges therefore that the claim was untimely. Form I Award No. 36285
A number of Awards have interpreted and applied Rule 42. Some support the Organization's position; others support the Carrier's position. A claim is formalized through several steps. It must be reduced to writing; it must be sent; it must be received. Placement of a written claim in a mail box is simply not tantamount to the claim being ` resented . . . to the officer of the Company authorized to receive same." Note Award 18 of Public Law Board No. 3460 between these same parties. Had the parties intended a mailing alone to be sufficient, they surely would have said so. The Agreement then would have stated that the claim must be "sent" or "mailed" within 60 days of the occurrence. But Rule 42 nowhere mentions sending or mailing. It speaks only of the claim being "presented" to a Carrier officer authorized to "receive" it. These words strongly suggest that the parties meant the date of receipt, the date "presented," to be the critical date in applying the 60-day time limit. Of course, an exception may well be appropriate when postal negligence causes undue delay in delivery. But no such undue delay was present here. The Organization's claim was not "timely filed" and must therefore be dismissed.