The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
The Carrier engaged a contractor, Johnson Excavating, to clean a blocked culvert at Mile Post 173.8 near Oak Creek, Colorado. It contends that this was necessary to "keep the culvert from washing out the tracks." The contractor did the work with its own employee and equipment, a backhoe, for eight hours on April 20, 1998. No notice of this contracting out was given to the General Chairman. The Carrier insists that the lack of notice was justified by "the fact that the work was performed under an emergency situation and needed to be executed before a 15-day notice could be served."
Appendix D, Article IV (Contracting Out) of the May 1968 National Agreement dealt with this subject as follows:
This notice requirement was reaffirmed in a December 11,19811etter which also added the following commitment:
The Claimant, Matlock, is a Work Equipment Operator. He says he could have cleaned the culvert in question with leased equipment, or perhaps Carrier equipment.
The Organization argues first that operation of a backhoe to clean a culvert is "work . . . clearly reserved to Carrier forces" under Rules 1 through 4 and that contracting out such work is hence a violation of the Agreement. It argues further that the failure to provide the General Chairman with notice of the contracting out was a violation of Appendix D and denied the General Chairman of the opportunity to persuade the Carrier to have the work done by its employees.
There is no need to address the first argument because the second has merit. The Carrier concedes it failed to provide the required notice, but urges that its failure was justified by an "emergency" situation. However, it has provided no meaningful evidence with respect to the alleged "emergency:" True, it stated that the culvert was blocked and that the contractor cleared the blockage on April 20, 1998. But there is nothing else to show that a real "emergency" existed. We do not know when the culvert problem was discovered, how much time the Carrier had to correct the problem before the tracks would be endangered, when exactly the Carrier engaged the contractor, how long it took for the contractor to act, why some notice could not have been provided before the contractor was engaged, and so on. All that is before the Board is the bare assertion of an "emergency." The Carrier has the burden of establishing that there was indeed an "emergency." It failed to meet that burden. Its lack of notice to the General Chairman was a violation of Appendix D. Given the record made in this case, it cannot Form I Award No. 36292
be said that the General Chairman could not possibly have persuaded the Carrier to use a Carrier employee to perform the disputed work.
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.