Form 1 NATIONAL. RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36304
Docket No. MW-36414
02-3-00-3-656

The Third Division consisted of the regular members and in addition Referee Nancy F. Eischen when award was rendered.


(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:



STATEMENT OF CLAIM:










FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved Jute 21,1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The Claimant has established and holds seniority in various classes within the Track and Roadway Machine Operator Subdepartments, including Laborer and Group 3 Machine Operator. Although the Claimant was experienced as Group 3 Machine Operator, he had not previously been qualified as a Ballast Regulator Operator.

Form 1 Award No. 36304
Page 2 Docket No. MW-36414
02-3-00-3-656

Prior to February 2,1998 the Claimant submitted a bid for one of the Group 3 Ballast Regulator positions available on System Gang SC30, a track surfacing gang. Subsequently the Claimant was notified of his assignment to one of the Ballast Regulator Operator positions.


On February 2,1998, Gang SC30 began a week long series of safety and start-up meetings, which ended on February 6, 1998, with no ballast regulation work being performed that week. The following week, the gang moved equipment from Wenatchee, Washington, to their starting work location at Kelso, Washington. Thereafter, the Claimant observed vacation during the week of February 9 through 13, 1998, but returned to duty on February 17,1998. On February 17,18 and 19,1998, the Claimant began work on the ballast regulator, under the tutelage of Assistant Foreman C. Pitcher, who was assigned to assist the Claimant during his training.





By letter dated February 23,1998, the Claimant requested an Unjust Treatment Hearing, per Rule 62 of the Agreement. The Hearing was held on March 13,1998, after which the Carrier upheld its decision to disqualify the Claimant as a Ballast Regulator Operator.


In the meantime, however, the Organization filed a "continuing" claim on behalf of the Claimant, alleging that the Carrier had violated Rules 1, 2, 4,8,23, and 40 of the Agreement when it did not allow a "reasonable" amount of time for the Claimant to qualify for the Ballast Regulator Operator position. The Vice General Chairman further alleged that the Carrier was not living up to the "spirit or intent" of Rule 23 when "no specific reasod' was given for the Claimant's disqualification. In that connection, the Organization noted that for the three days the Assistant Foreman was assigned to work with the Claimant, he observed that: ". . . I felt he was a little slow but he was . . . improving daily."


As remedy for the Carrier's alleged Rule violations, the Vice General Chairman requested thaw


Form 1 Award No. 36304
Page 3 Docket No. MW-36414
02-3-00-3-656

The Carrier denied the claim, contending that the Claimant was disqualified for "several reasons." Specifically, the Carrier premised its decision upon the following:









The Organization alleges that the Carrier violated Section A of Rule 23 when it disqualified the Claimant from his position as a Group 3 Machine Operator after operating his machine for only three working days. In Rule 23-FAILURE TO QUALIFY states:


Form 1 Award No. 36304
Page 4 Docket No. MW-36414
02-3-00-3-656
B. An employee failing to qualify for a position secured by bulletin, or
in exercise of seniority will be given notice in writing of reason for
such disqualification.
C. An employee who considers himself unfairly disqualified may
request, and shall thereupon be given, an investigation as to such
qualifications pursuant to the provisions of Rule 62."

The Claimant was assigned to the position in question commencing February 2, 1998. Slightly over two weeks on the job, the Carrier disqualified the Claimant, contending that the Claimant did not possess the fitness and ability to operate the machine to meet the requirements of the position.


In these circumstances, the Organization does not argue with the Carrier's assessment of the Claimant's fitness and ability for the position in dispute, but rather asserts that the Claimant was "improving" and should have been given "more time" to attempt to become qualified. Specifically, the Organization asserts that the Carrier violated Rule 23 noted sup by not providing the Claimant with 30 days to attempt to qualify for the Group 3 Ballast Regulator Operator position. However, Rule 23 does not require that the Carrier allow successful bidders to work any specified period of time before disqualifying them. The Rule only requires that the Carrier give the employee a "reasonable opportunity" to qualify. In these circumstances, the record demonstrates that the Carrier adhered to that requirement.


In that connection, the Organization asserts that the Claimant was only "on the position" for three days. However, the record demonstrates that the Claimant was actually "on the position" for 18 days. Of those 18 days, the Claimant was physically operating the machine at least five days: two days of non-production, training operation of the machine in the week of February 2,1998, and three days of production work in the week of February 17,1998.


On February 4, 1998, during the first two weeks of operating the Ballast Regulator, the Claimant ran his machine into another machine. Regarding that incident, Roadmaster Searer stated that tht Claimant didn't seem to be "very familiarized" with the equipment.


During that same period of time, the record demonstrates that the Claimant fell asleep during training class in his first week of training. The instructor, who observed the Claimant nodding off and then sleeping, directed the Claimant to wake up and pay attention.


Finally, with respect to the Claimant's overall progress, the Assistant Foreman assigned to train the Claimant reported that:

Form 1 Award No. 36304
Page 5 Docket No. MW-36414
02-3-00-3-656



The Carrier's right to determine whether their employees are qualified to perform desired jobs is supported by numerous Awards. (See for example the onproperty Award Appendix K Board, Award 24, Third Division Awards 35408 and 35917.) The record demonstrates that the Carrier afforded the Claimant ample opportunity to qualify for the Group 3 (GP-3) Machine Operator position, and in these circumstances, the Carrier's decision to disqualify the Claimant from same cannot be considered arbitrary or capricious.




      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division


                      Dated at Chicago, Illinois, this 13th day of November 2002.