Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36502
Docket No. MW-35818
03-3-99-3-818

The Third Division consisted of the regular members and in addition Referee Elliott H. Goldstein when award was rendered.


(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:



STATEMENT OF CLAIM :











Form 1 Award No. 36502
Page 2 Docket No. MW-35818
03-3-99-3-818

FINDINGS :

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The Claimants established and held seniority as Group 2 Machine Operators on Seniority District 15. On the claim dates, they were regularly assigned as Group 2 Machine Operators on the Sidney Subdivision of the Powder River Division.


By letter dated December 18,1996, the Carrier issued a 15-day notice informing the four BMWE General Chairmen of the Carrier's intention to contract out certain work described as the "loading and unloading of various products throughout the Burlington Northern Santa Fe System" including "the handling of switch ties, crossing timbers, cross ties, tie plates, rail, and various other materials primarily, but not necessarily always, shipped in coal cars or gondolas."


The Carrier's 15-day notice further explained that the contractor's equipment was "patented, special equipment . . . able to operate from the top of the cars, and, as necessary, lower into the cars themselves in order to maintain clearances," and that the contractor's equipment would "supplement Carrier magnetic cranes and Jimbo Cartoppers to handle the estimated 700 track miles of relay material to be shipped over the system in 1997." The letter also stated that, "The machines utilized by Herzog, Inc., . . . are patented, specially designed, not available to the Carrier and the Contractor is unwilling to allow for the operation of equipment by other than its own employees."


In a letter dated January 10,1997 to the Carrier, the General Chairmen objected to the contracting notice "for a number of reasons," namely, that the notice was not timely and failed to identify the specific locations and dates of the intended contracting. The

Form 1 Award No. 36502
Page 3 Docket No. MW-35818
03-3-99-3-818

letter also characterized the contracting notice as an unacceptable blanket notice that did not comply with the Note to Rule 55 or the December 11, 1981, Letter of Understanding (Appendix Y). The letter further stated that the work in dispute had customarily been performed by BMW E-represented employees with equipment owned by the Carrier. The General Chairmen concluded their letter with a request that the Carrier conference the matter with the General Chairmen at a mutually convenient time and place.


On January 15, 1997, the Carrier and Organization met for the purpose of discussing the Carrier's systemwide plan to contract out the loading and unloading work scheduled for the 1997 capital program. The parties, however, were unable to reach an understanding concerning the contracting out issue. The Organization alleged that on September 8,1997, the Carrier assigned Herzog Contracting Corporation to perform the work of "operating material handling machines to clear the right of way of scrap ties, rail, angle bars, spikes, plates and other track material discarded by steel relay gangs at various locations on the Sidney Subdivision of the Powder River Division."


The Organization avers that the contractor used car top material handling machines to accomplish the above-quoted work. The Organization maintains that the contractor's machines were similar to machines listed in Rule 5 and commonly operated by the Carrier's own M of W forces. According to the Organization, such machines include "truck cranes, backhoes with magnet attachments, front end loaders, car top material handlers, speed swings, etc."


The Organization maintains that the Carrier improperly assigned track and roadbed maintenance work to Herzog Contracting instead of allowing the Claimants to perform the work reserved to them under Rules 1, 2, 5, 55 and the Note to Rule 55. As a result of the Carrier's alleged violation of the above Rules, the Organization requests that the Claimants receive payment as detailed in paragraph (3) of the instant claim.


The Carrier contends that since the early 1980s, it has contracted with Herzog Contracting Corporation to have track material loaded and unloaded using Herzog's patented "cartopper" material handler and that the instant claim is not the result of any new practice on the Burlington Northern Santa Fe Railway (BNSF). It argues that the "cartopper" is special equipment not owned by the Carrier and operated solely by Herzog's own employees to pick up scrap as Herzog employees have done for many years. The Carrier also asserts that previous arbitration Awards have upheld BNSF's practice of contracting with Herzog Contracting Corporation.

Form 1 Award No. 36502
Page 4 Docket No. MW-35818


The Carrier maintains that the 15-day contracting notice it served complied in all respects with the Note to Rule 55 and with Appendix Y. The Carrier argues that the "cartopper" falls within the definition of "special equipment not owned by the Company." Furthermore, the Carrier stresses that it conducted a conference with the General Chairmen to discuss the "contracting transaction," and when an understanding could not be reached, it properly proceeded with the contracting work described in the notice. In addition, the Carrier states that while M of W employees on the BNSF have picked up scrap, they never have used the Herzog "cartopper." The Carrier urges that, at best, the work of picking up scrap on the BNSF is a "mixed practice."


Finally, the Carrier states that at the time of the alleged violation, the Claimants were working in the craft. The Carrier emphasizes that there is no basis for awarding any additional compensation inasmuch as both employees did not suffer any loss of pay.


After reviewing the extensive record and the comprehensive arguments expressed by the parties, the Board finds that the work of loading ties and scrap material from the Carrier's right-of-way has been performed by both M of W Department employees and by outside contractors using their own specialized equipment. The Board also finds that a "mixed practice" regarding the performance of this work exists on BNSF and holds that the Carrier properly served the Organization with a 15-day contracting notice, as prescribed by the Note to Rule 55 and the December 11, 1981 Letter of Understanding (Appendix Y).


Regarding the correctness of the 15-day notice, the Board disagrees with the Organization's characterization of the notice as "vague, blanket, ex post facto, and bad faith." The Carrier demonstrated that its December 18,1996 contracting notice involving its use of the "cartopper" was virtually identical to the "cartopper" notices it had issued to the Organization in prior years, and that the letter itself contained sufficient information so as to comply with the Note to Rule 55 and Appendix Y. There is nothing in the voluminous record to indicate that the Organization was prevented from meeting with the Carrier and discussing the Carrier's contracting plans. The Board finds, therefore, that the Organization had an opportunity to ascertain the details regarding the contracting plans and to present its position to the Carrier during the meeting of January 27, 1997, pursuant to the requirements specified in the Note to Rule 55 and in Appendix Y.

Form 1 Award No. 36502
Page 5 Docket No. MW-35818
03-3-99-3-818

As stated above, the Board rinds that the Carrier was within its right to contract out the disputed work on the basis that it needed the specialized "cartopper" equipment owned and operated by Herzog Contracting Corporation in order to accomplish the material pick up work on a systemwide basis during the 1997 capital project year. The record contains several statements from the Carrier's M of "'Department supervisors, along with literature from Herzog Contracting Corporation showing that the "cartopper" is capable of performing various special functions that the Carrier's equipment (e.g., Jimbo cranes) cannot accomplish. Regarding the Organization's assertions that many of the "cartopper's" capabilities were not required or utilized in the instant case (e.g., there were no "clearance limitations"), the Board finds that such assertion lacks evidentiary support. As the moving party in this claim, the Organization had the affirmative burden of showing that the specialized equipment was not needed. In other words, the Organization must offer proof beyond a mere assertion; here it did not.


In sum, the Board finds that the Carrier properly served notice and contracted for the use of the Herzog "cartopper," and that the Carrier's use of the "cartopper" constituted an established practice. No violation of Rules 1, 2, 5, 55, the Note to Rule 55 or Appendix Y occurred. In further support of the Board's position, see Public Law Board No. 3460, Award 63, Public Law Board No. 4402, Award 20, Public Law Board No. 4768, Awards 28 and 47, and Third Division Awards 31615, 32153, 35386, 36157, and 36209. Accordingly, the claim is denied in its entirety.


                        AWARD


      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 23rd day of April 2003.