Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36514
Docket No. MW-35886
03-3-99-3-894
The Third Division consisted of the regular members and in addition Referee
Ann S. Kenis when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company [former Southern Pacific
( Transportation Company (Western Lines)]
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (Herzog Construction Company) to distribute new and
secondhand plates and other track material on the Suisun District
beginning August 4, 1997 and continuing (Carrier's File 1162223
SPW).
(2) The Agreement was further violated when the Carrier failed to
provide the General Chairman with a proper advance written
notice of its intent to contract out said work in accordance with
Article IV of the May 17, 1968 National Agreement.
(3) As a consequence of the violations referred to in Parts (1) and/or (2)
above, System Work Equipment Operator D. P. Knotts shall be `.
. . paid an equal amount of the total man hours worked by the
Herzog Construction Company Car Top Material operator, which
will be no less than the two hundred sixteen (216) straight time
hours, and one hundred sixty-eight (168) overtime hours, already
identified herein, at the Car Top Material Machine Operators,
Class 05A, rate of pay. Compensation for this violation is
continuous until the contractor is no longer employed to perform
this work and will be in addition to any compensation Claimant may
have already received."
Form 1 Award No. 36514
Page 2 Docket No. MW-35886
03-3-99-3-894
FINDINGS:
The Third Division
of
the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning
of
the Railway Labor Act, as
approved June 21, 1934.
This Division
of
the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute were given due notice
of
hearing thereon.
This claim alleges that the Carrier, without prior notice, contracted with an
outside concern for the handling and distribution
of
tie plates and other track material
on the Suisun District beginning on August 4, 1997 and continuing, in conjunction with
what was referred to as the "Cal P Project." The Organization asserted in its claim that
BMWE-represented employees had performed this work utilizing Carrier equipment
until they were sent off the project and outside forces were brought in.
The factual predicate in this case and the arguments advanced by the parties are
substantially similar to Third Division Award 36516. Both cases involve the same
parties and the same kind
of
work. The Board held in that case that the work was
arguably scope covered and that, at minimum, notice should have been provided to the
Organization before contracting out. Exclusivity was rejected as a defense for purposes
of
notice. After careful review, we find that there is no reason why the instant case
should be treated any differently. Accordingly, this claim will be sustained.
AWARD
Claim sustained.
Form 1 Award No. 36514
Page 3 Docket No. MW-35886
03-3-99-3-894
ORDER
This Board, after consideration
of
the dispute identified above, hereby orders that
an award favorable to the Claimant(s) be made. The Carrier is ordered to make the
Award effective on or before 30 days following the postmark date the Award is
transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order
of
Third Division
Dated at Chicago, Illinois, this 23rd day
of
April 2003.