Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36604
Docket No. MW-33909
03-3-97-3-412
The Third Division consisted of the regular members and in addition Referee
Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Burlington Northern Santa Fe Railway Company
( (former St. Louis - San Francisco Railway Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
1. The Agreement was violated when the Carrier assigned outside forces
(Dunn Construction Company) to perform the work of setting forms,
tying steel, placing and finishing concrete and removing forms at the
Dixie Hub Center, Birmingham, Alabama on November 15, 1994 and
continuing (System File B-820-1/MWC 95-01-12AA SLF).
2. As a consequence of the aforesaid violation, Messrs. R. A. Smith, B. E.
Colburn, H. W. Vaughn, B. G. Tribble and T. M. Bennett shall each
be compensated at their respective rates of pay for an equal
proportionate share of the total number of man-hours expended by
the outside forces in the performance of the above-described work."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are
respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
herein.
Form 1 Award No. 36604
Page 2 Docket No. MW-33909
03-3-97-3-412
Parties to said dispute were given due notice of hearing thereon.
By notice dated June 23, 1994, the Carrier advised the Organization of its intent to
contract out work involving the expansion of the Intermodal Hubs located at Memphis
and Birmingham. According to the Carrier's notice, the initial intention was to contract
out (1) grading including clearing, demolition and grubbing; (2) placement of engineered
fill material; (3) storm water drainage systems; (4) asphalt paving and associated traffic
control; (5) construction of concrete craneways; (6) construction of concrete light tower
foundations; (7) construction of concrete dolly pads; (8) track construction, removal and
relocations; (9) crossing construction; and (10) fencing. According to the Carrier's notice
"[tjhe Carrier does not possess the sufficient equipment nor the expertise to properly
perform this work."
As shown by the Carrier's letter dated August 18, 1994, conferences between the
parties on July 29 and August 17, 1994, yielded agreement that the Carrier's forces would
construct concrete light tower foundations, concrete dolly pads, trackage including
removal and relocation, and track road crossings, but that a contractor would perform
grading including clearing, demolition and grubbing, placement of engineered fill
material, storm sewer and drainage construction, installation of asphalt paving along
with associated traffic control and fencing. However, as indicated in that letter, "[t]he
construction of concrete craneways is an open issue and will be decided prior to the start
of construction."
By letter dated September 15, 1994, the Carrier advised the Organization that ". . .
we have decided to contract the construction of the concrete craneways for the
Intermodal Hub expansion at Birmingham, Alabama." The Organization objected to the
contracting out of that work. The Carrier gave the work to Dunn Construction
Company. This claim followed for the work at Birmingham.
The Carrier's argument on the property that the Organization's claim must fail
because of a lack of demonstration of exclusive performance of the work is not persuasive.
"Exclusive performance of the work by covered employees is not required in contracting
out disputes." See Third Division Award 36603 and Awards cited therein. Under Rule
99, the work in dispute - construction of the concrete craneways for the Intermodal Hub
expansion at Birmingham - is clearly ". . . work within the scope of the applicable
schedule agreement. . ." for these employees.
Form 1 Award No. 36604
Page 3 Docket No. MW-33909
03-3-97-3-412
Turning to the work, according to the claim the Organization's specific protest is
the contracting ". . . to perform the work of setting forms, tying steel, placing and
finishing concrete and removing forms at the Dixie Hub Center, Birmingham. . . :'
According to the Carrier's September 22, 1994 letter:
"3. Design of the craneway is very complex and construction
must be handled in such a manner to handle extremely
high wheel load. The concrete structure as well as the
base material and subgrade must all be constructed to
very high standards and the contractor must be
responsible for all aspects in order to guarantee the
outcome of the job. No part of this construction can be
piecemealed out as it would be impossible to ensure
responsibility of structural integrity of final product. We
have no obligation to piecemeal a project of this type.
Also, this is not the normal concrete slab construction
that the B&B Department constructs for driveways,
walkway, etc.
4. The company possesses neither the specialized equipment
nor the special skills required, nor is the company
adequately equipped to handle the work and to complete
the new construction within the allotted time."
According to a July 18,1995 letter from the Carrier:
"The work involved was to form and pour concrete craneways for
equipment to load intermodal platforms. Approximately 3,912
cubic yards of concrete for 9,726 linear feet o f 8 ' w ide
platforms... "
Form 1 Award No. 36604
Page 4 Docket No. MW-33909
03-3-97-3-412
The employees did not view the work claimed by the Organization as complex as
the Carrier viewed the work. According to an October 8, 1995 letter from several
employees:
" 3. As for . . . [the] reference t o driveways, that is exactly
what the craneways are - a little thicker, a little more
reinforced, but a driveway nonetheless. This job would
have been very little challenge to us, considering some of
the projects we have successfully completed. This
craneway is far less complex than the scale pits, diesel
shop inspection pits, and pollutant retaining walls
meeting exacting EPA standards that B&B has poured in
the past. It also does not have to handle nearly as high a
wheel load as B&B's many bridge piers over which diesel
engines and loaded grain cars weighing far more than a
crane must pass on a daily basis ....
4. The craneway job required no tools that were not already
owned by BN or that could not have been rented or
purchased locally. There were no skills required that this
gang does not possess, and inspection of some of our
other work will prove this to be the case. . . :'
In a letter dated April 22, 1997, the Carrier further addressed the complexity of
the disputed work:
".
. . The Carrier did not have adequate forces and equipment to
perform the massive project and be able to complete quickly
enough to handle the increased intermodal traffic.
Form 1 Award No. 36604
Page 5 Docket No. MW-33909
03-3-97-3-412
The Claimants have also argued that the work is similar to pouring
a driveway, only the craneway is a little thicker and more
reinforced However, to a Civil Engineer, Construction Engineer
or a Structural Engineer that are responsible for the structural side
and construction of the craneway there is a great deal of
difference .... [T]he design of the craneway is very complex and
construction must be handled in such a manner to handle
extremely high wheel load. The concrete structure as well as the
base material and subgrade must all be constructed to very high
standards and the contractor must be responsible for an aspects in
order to guarantee the outcome of the job. No part of this
construction can be piecemealed out as it would be impossible to
ensure responsibility of structural integrity of the final product ....
[C]raneway construction is not the normal concrete slab
construction that the Bridge and Building Department constructs
for driveways and walkways .
. . . In this case, the placing of the concrete was just one portion of
an extensive project which included the placement of engineered fill
material, the installation of storm water drainage systems, asphalt
paving and traffic control, construction of light tower foundations,
construction of dolly pad, track construction and relocation,
crossing construction and the installation of fence around the
facility. It is well established that the Carrier is not required to
piecemeal a project of this size in order to provide employees
represented by the Organization work. However, in this case some
of the work was performed by Carrier forces. However, since the
Carrier's forces did not have the expertise to construct the
craaeway to the rigid specifications required, the work was
contracted."
For the sake of discussion, we will assume (and we believe the record supports) the
fact that contrary to the Carrier's assertions, the Claimants were capable of performing
the disputed work identified in the claim. Again, as set forth in the claim, that work was
°°. . . setting forms, tying steel, placing and finishing concrete and removing forms at the
Dixie Hub Center, Birmingham. . . :' The employees adequately described that claimed
work - "[a]s for . . . [the] reference to driveways, that is exactly what the craneways are -
a little thicker, a little more reinforced, but a driveway nonetheless." B&B forces have
Form 1 Award No. 36604
Page 6 Docket No. MW-33909
03-3-97-3-412
constructed driveways and more complex structures, and the work claimed ". . . setting
forms, tying steel, placing and finishing concrete and removing forms at the Dixie Hub
Center, Birmingham. . . :' - precisely describes that kind of work which the employees
have previously performed. Thus, at first blush, it appears that this work could have
been performed by Maintenance of Way forces.
But there is more to this case. On the property and as set forth in the above
quoted letters, the Carrier consistently maintained that it was not obligated to piecemeal
the work on the craneways by assigning some work to an outside contractor and some
work to covered employees. Precedent exists for the principle that a Carrier is not
obligated to piecemeal a contracted project. See e.g, Third Division Awards 34123 (". . .
it is an established principle that a Carrier is not required to piecemeal a large project in
order to provide some portion of the work to the Organization-represented employees");
31526 (". . . the Carrier need not piecemeal . . ."); 29187 (". . . insufficient support for the
contention that the Carrier was required to `piecemeal' a portion of the work to
Maintenance of Way employees").
The expansion of the Intermodal Hub at Birmingham was a large project. It
appears at first that the Carrier desired to contract out the vast majority (if not all) of the
work. See the Carrier's initial notice (where the Carrier notified the Organization that it
was going to contract out grading including clearing, demolition and grubbing;
placement of engineered fill material; storm water drainage systems; asphalt paving and
associated traffic control; construction of concrete craneways; construction of concrete
light tower foundations; construction of concrete dolly pads; track construction, removal
and relocations; crossing construction; and fencing). After conferences between the
parties, agreement was reached that the Carrier's forces would construct concrete light
tower foundations, concrete dolly pads, trackage including removal and relocation, and
track road crossings, but that a contractor would perform grading including clearing,
demolition and grubbing, placement of engineered fill material, storm sewer and drainage
construction, installation of asphalt paving along with associated traffic control and
fencing. What is significant here is that the craneway work claimed by the Organization
Le,
°1.
. . the work of setting forms, tying steel, placing and finishing concrete and
removing forms . . ." - is part and parcel of the overall craneway construction work,
which, according to the Carrier's description of the work, also includes placement of the
base material and subgrade for the craneways. But, as stated in the Carrier's August 18,
1994 letter, after conferences the Organization agreed that".. . a contractor would
perform grading [and] . . . placement of engineered fill material . . . ." [emphasis
added]. The only disputed work as set forth in the claim concerns ". . . the work of setting
Form 1 Award No. 36604
Page 7 Docket No. MW-33909
03-3-97-3-412
forms, tying steel, placing and finishing concrete and removing forms. . . :' Thus, with
respect to the craneway, the Organization sought to piecemeal the construction of that
portion of the craneways identified in the claim from the work of placement of the base
material and subgrade for the craneways which the Organization previously agreed could
be performed by a contractor. Under established precedent, the Carrier is not obligated
to piecemeal the work in that fashion. We must therefore deny the claim.
In light of the above, the Carrier's other arguments are moot.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders that
an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 29th day of July 2003.