Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36716
Docket No. MW-36154
03-3-00-3-344

The Third Division consisted of the regular members and in addition Referee Nancy F. Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





Form 1 Award No. 36716
Page 2 Docket No. MW-36154
03-3-00-3-344
29, 30, November 2, 3, 4, 5, 6, 9, 10, 11, 12, 13, 23, 24, 25, 30,
December 1, 2, 3, 7, 8, 9, 10, 14, 15, 16 and 17, 1998, January 4,
5, 6, 7, 11, 12, 13 and 14, 1999, and each Claimant shall be
compensated for ten (10) hours' pay at their appropriate time
and one-half rates of pay for each date of August 22, 23, 29, 30,
September 5, 6, 12, 13, 19, 20, 26, 27, October 3, 4, 10, 11, 17, 18,
24, 25, 31, November 1, 7, 8, 14, 15, 21, 22, 27, 28, 29, December
4, 5, 6, 11, 12, 13, 18, 19 and 20, 1998, January 7, 8, 14 and 15,
1999, and Claimants K. C. Champa, F. R. Hoyt, R. H. Zinni, K.
Watts and P. J. Kolean shall each be compensated for ten (10)
hours' pay at their appropriate rates of pay for each date of
March 16, 17, 18, 22, 23, 24 and 25, 1999 and compensated for
ten (10) hours' pay at their appropriate time and one-half rates
of pay for each date of March 19 and 26, 1999."

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




In this case, the Organization asserts a violation of the controlling Scope Rule when the Carrier subcontracted the work of repair/replacement of the 1,921 foot long 175 foot high bridge over the Cuyahoga River, at MP 11.09, in Cuyahoga County, Ohio. This truss span type bridge, built in 1907 by an outside contractor, consists of 25 deck girder spans of 40, 67 and 80 foot lengths, and five deck truss spans, four of which are 100 feet long. The construction is of built-up members with riveted connections, plus a main span of 180 feet, comprised of two pin-connected

Form 1 Award No. 36716
Page 3 Docket No. MW-36154
03-3-00-3-344

trusses of built-up riveted and eye-bar members. The spans are supported by steel towers resting on concrete pedestals and two concrete abutments, also built originally by the contractor in 1907.


After ascertaining that virtual replacement of this 90-year old bridge over the Cuyahoga River was structurally necessary, the Carrier determined that the magnitude of reconstructing this particular bridge was beyond the capacity of Conrail's B&B workforce and required specialized equipment Conran did not possess and could not rent without an operator. It is not disputed on this record that Conrail B&B forces represented by the Organization have performed the majority of bridge repairs and have replaced some other steel bridges in the past. Thus, we conclude that the work in question was subject to the following notice, meeting and good faith discussion requirements of the second and third paragraphs of the Scope Rule:




The Carrier served notice of intent to subcontract the above-described Cuyahoga River Bridge reconstruction project, by letter to the General Chairman, dated February 19, 1998, reading in pertinent part as follows:

Form 1 Award No. 36716
Page 4 Docket No. MW-36154
03-3-00-3-344

































Form 1 Award No. 36716
Page 5 Docket No. MW-36154
03-3-00-3-344









Following written objection by the Organization and timely conference in which discussion did not result in any mutually agreeable alternative, the Carrier went forward with contracting out of the project and commenced the reconstruction on or about August 17, 1998. The Organization filed a number of virtually identical claims in which only the dates were different, asserting procedural and substantive violations of the Scope Rule by the Carrier.
Form 1 Award No. 36716
Page 6 Docket No. MW-36154


The Agreement language does not specify what would serve to justify subcontracting of Agreement-covered work when a decision to contract out such work covered under the Scope Rule is grieved by the Organization. However, as a matter of practice, these Parties recognize that certain criteria generally must be demonstrated by Conrail, i.e., lack of available equipment, insufficient manpower or specialized equipment not reasonably available to or obtainable by the Carrier. Part 2 of the instant claim is denied because the record persuasively demonstrates that the Carrier did comply with the notice and good-faith conferencing requirements, supra. Moreover, careful review of the record and prior decisions regarding specialized skills, specialized equipment and carving up or piece-mealing work of such magnitude under similar circumstances involving the same issue, Parties and Agreement language, persuades us that the Organization failed to make a showing that the Scope Rule was violated by the Carrier's subcontracting of the Cuyahoga River Bridge reconstruction in this particular case. See Third Division Awards 31287, 29558, 29024, 28891 and 26850.




      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 17th day of September 2003.