Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36744
Docket No. MW-36237
03-3-00-3-445
The Third Division consisted of the regular members and in addition Referee
Nancy F. Eischen when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Burlington Northern Santa Fe Railway Company
( (former Burlington Northern Railroad Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
1. The Agreement was violated when the Carrier assigned outside
forces (Patrick Construction) to perform embankment
stabilization work (install drains and place rip-rap) at Mile
Post 300.4 on the Montana Division mainline in the vicinity of
Vandallia, Montana beginning March 17, 1998 and continuing
(System File B-M-602-F/MWB 98-08-13AA BNR).
2. The Agreement was further violated when the Carrier failed to
make a good-faith effort to reduce the incidence of
subcontracting and increase the use of its Maintenance of Way
forces as required by Rule 55 and Appendix Y.
3. As a consequence of the violations referred to in Parts (1)
and/or (2) above, Foreman G. W. Sinclair, Truck Drivers W. E.
Arnold, G. S. Blackman, Group 2 Machine Operators R. C.
Rodriguez, M. W. Sinclair, J. W. Peltier, G. L. Sinclair and K.
R. Johnson shall each `. . . receive an equal and proportionate
amount of pay for all hours straight time hours and overtime
hours worked by the contractor beginning March 17, 1998 and
continuing until work has been completed."
Form 1 Award No. 36744
Page 2 Docket No. MW-36237
03-3-00-3-445
FINDINGS
:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
On November 24, 1997 the Carrier informed the General Chairman as
follows:
"As information, the Carrier plans to perform the following project
near Vandalia, Montana. As has been customarily done in the past,
it is proposed that the work will be performed by contractors who
are properly equipped and possess the necessary expertise to
perform all aspects of the work. A description of the work is as
follows:
Rehabilitate approximately 600' of embankment on the
main line that is failing due to water infiltration. Plans
include the installation of French drains throughout the
fill at strategic locations and the construction of a buttress
at the toe of the embankment using rip rap. It is
anticipated that the following materials will be used
during the project:
7,000 tons of crushed rock for the French drains
150 rail cars of rip rap
Form 1 Award No. 36744
Page 3 Docket No. MW-36237
03-3-00-3-445
It is anticipated the project will begin on December 11,
1997, and will take approximately 45 days.
The type and/or magnitude of work in the above project is
such that it is and has been customarily performed by
outside contract forces. The Company possesses neither
the specialized equipment nor special skills required, nor
is the Company adequately equipped to handle the work
and to complete this project within the allotted time
period.
If you or your designated representative wish to discuss
any of the work described in greater detail, please contact
me . . . . so that arrangements can be made for a meeting."
On December 4, 1997, the General Chairman replied to the Carrier's
November 24 notice in which he asserted that:
"The description of the work in your letter clearly shows that this
project is not of such magnitude to support an argument for the use
of contractors. Further, while you have made an allegation, you
have failed to provide any evidence which support your position that
the work is specialized or that special skills are required. We hope
you can see why we cannot concur in your desire to assign this work
to others.
Pursuant to the Note to Rule 55 and Appendix Y of our Agreement,
we are herewith requesting a conference. Would you kindly contact
BMWE Vice General Chairman G. E. Frank to arrange for a
mutually convenient time and place for
this
conference."
On or about March 17, 1998 Patrick Construction commenced on the project
which the Carrier set forth in the November 24 Notice, and, on April 28, 1999, the
Organization submitted a claim in connection with same in which it asserted that
the Carrier bad violated Rules 1, 2, 5, 6, 7, 24, 25, 29, 55, and the Note to Rule 55
and Appendix Y.
Form 1 Award No. 36744
Page 4 Docket No. MW-36237
03-3-00-3-445
Specifically, the General Chairman noted that "most" of the Claimants are
heavy equipment Operators who had been assigned to operate machines "similar or
identical" to those operated by Patrick Construction employees, and bad done "the
very same" type of projects now in dispute. In that connection, the Organization
asserts that Patrick Construction used machines on the disputed project which were
either "owned by Carrier or available to rent." Finally, the General Chairman
maintained that: "Carrier's refusal to exert an effort to reduce outside contracting
is reason sufficient to justify sustaining this claim."
In its denial to the claim, the Carrier argued that:
"Embankment stabilization and French drain installation work is
often assigned to outside contractors because they have both the
equipment and the expertise to handle what is a dangerous project.
Just in recent years, outside forces have been assigned to perform
similar work at the following locations:
- MP 10.4-106 and MP 8 & MP 16 at Seattle and
Everett, Washington;
- MP 15.9-16.1, and MP 8 & MP 16 at Seattle and
Everett, Washington;
- MP 26.5 and MP 26.8 at Edmond and Mukilteo,
Washington;
- MP 1784.4-1784.6 at Everett, Washington;
- MP 1736.9-1737.0 at Skynomish and Baring,
Washington.
As the moving party in this dispute it is not enough for the
Organization to simply make an assertion and then sit back to see
what the Carrier does next. It is your burden to show that such
work has been exclusively performed in the past by the employees.
The Organization has failed to meet that burden. Moreover, the list
of locations where the Carrier has contracted out the work in
question refutes those statements. Another factor to consider is that
most of the work took place off the right of way and as such was not
Form 1 Award No. 36744
Page 5 Docket No. MW-36237
03-3-00-3-445
Scope covered work. In fact, all of the buttressing work was off of
the Carrier's right of way.
The project at issue had to be completed in an expeditious manner.
The track was almost completely out of service, having a ten mile
per hour slow order placed on it, and the work was going to take
place below what the normal water line of the Milk River usually
would be. Once Spring arrived the water level would rise and the
track would be taken out of service."
This dispute involves a claimed violation of numerous Agreement Rules,
including the Scope Rule, when following due notice the Carrier contracted out the
work of bank stabilization at MP 300.4 in the area of Vandalia, Montana. Careful
review of this voluminous record, persuades us that the Organization failed to make
out a prima facie showing that the cited Agreement Rules were violated by the
Carrier's subcontracting of the Vandalia bank stabilization project. Despite the
Organization's contention that the disputed work is "specifically reserved" to MotW
employees, there is no specific contract language, history, or record evidence, which
substantiates such a contention. In fact, the record supports the Carrier's assertion
that there has been a "mixed practice" on this property, and while MofW employees
may have participated in similar projects, there is no reservation of the disputed
work to MofW employees.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 22nd day of October 2003.