Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36744
Docket No. MW-36237
03-3-00-3-445

The Third Division consisted of the regular members and in addition Referee Nancy F. Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:



STATEMENT OF CLAIM:





Form 1 Award No. 36744
Page 2 Docket No. MW-36237
03-3-00-3-445

FINDINGS :

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




On November 24, 1997 the Carrier informed the General Chairman as follows:





Form 1 Award No. 36744
Page 3 Docket No. MW-36237
03-3-00-3-445
It is anticipated the project will begin on December 11,
1997, and will take approximately 45 days.
The type and/or magnitude of work in the above project is
such that it is and has been customarily performed by
outside contract forces. The Company possesses neither
the specialized equipment nor special skills required, nor
is the Company adequately equipped to handle the work
and to complete this project within the allotted time
period.
If you or your designated representative wish to discuss
any of the work described in greater detail, please contact
me . . . . so that arrangements can be made for a meeting."

On December 4, 1997, the General Chairman replied to the Carrier's November 24 notice in which he asserted that:



On or about March 17, 1998 Patrick Construction commenced on the project which the Carrier set forth in the November 24 Notice, and, on April 28, 1999, the Organization submitted a claim in connection with same in which it asserted that the Carrier bad violated Rules 1, 2, 5, 6, 7, 24, 25, 29, 55, and the Note to Rule 55 and Appendix Y.
Form 1 Award No. 36744
Page 4 Docket No. MW-36237
03-3-00-3-445

Specifically, the General Chairman noted that "most" of the Claimants are heavy equipment Operators who had been assigned to operate machines "similar or identical" to those operated by Patrick Construction employees, and bad done "the very same" type of projects now in dispute. In that connection, the Organization asserts that Patrick Construction used machines on the disputed project which were either "owned by Carrier or available to rent." Finally, the General Chairman maintained that: "Carrier's refusal to exert an effort to reduce outside contracting is reason sufficient to justify sustaining this claim."















Form 1 Award No. 36744

Page 5 Docket No. MW-36237
03-3-00-3-445
Scope covered work. In fact, all of the buttressing work was off of
the Carrier's right of way.
The project at issue had to be completed in an expeditious manner.
The track was almost completely out of service, having a ten mile
per hour slow order placed on it, and the work was going to take
place below what the normal water line of the Milk River usually
would be. Once Spring arrived the water level would rise and the
track would be taken out of service."

This dispute involves a claimed violation of numerous Agreement Rules, including the Scope Rule, when following due notice the Carrier contracted out the work of bank stabilization at MP 300.4 in the area of Vandalia, Montana. Careful review of this voluminous record, persuades us that the Organization failed to make out a prima facie showing that the cited Agreement Rules were violated by the Carrier's subcontracting of the Vandalia bank stabilization project. Despite the Organization's contention that the disputed work is "specifically reserved" to MotW employees, there is no specific contract language, history, or record evidence, which substantiates such a contention. In fact, the record supports the Carrier's assertion that there has been a "mixed practice" on this property, and while MofW employees may have participated in similar projects, there is no reservation of the disputed work to MofW employees.




      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 22nd day of October 2003.