Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36795
Docket No. MW-36263
03-3-00-3-491

The Third Division consisted of the regular members and in addition Referee Nancy F. Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





Form 1 Award No. 36795
Page 2 Docket No. MW-36263
03-3-00-3-491
(4) As a consequence of the violation referred to in Parts (1) and/or
(3) above, Claimants K. G. Champa, F. R. Hoyt, J. D'Orazio, S.
J. La Cavera and R. H. Zinni shall now each be compensated
for eight (8) hours' pay at their appropriate straight time rates
of pay for each date of April 22, 23, 24, 27, 28, 29, May 4, 5, 6,
7, and 8, 1998.
(5) As a consequence of the violations referred to in Parts (2)
and/or (3) above, Claimants K. G. Champa, F. R. Hoyt, R. H.
Zinni and K. Watts shall now each be compensated for eight (8)
hours' pay at their appropriate straight time rates of pay for
each date of May 11, 12, 13, 14 and 15, 1998."

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The Organization combined two claims in this docket. Between April 22 and May 8, 1998, the Carrier employed Great Lakes Construction, to "demolish an old roadway bridge" at MP 0.45 on the Cleveland Short Line. The contractor then filled the gap with stone. During the period of May 11 - 15, 1998 Great Lakes Construction removed "old steel Catenary Structures" between MP 0.0 and 5.0 on the Cleveland Short Line.


In each claim the Organization asserts that its employees have "historically" done this work. Specifically, the Assistant General Chairman contended that:

Form 1 Award No. 36795
Page 3 Docket No. MW-36263
03-3-00-3-491




In its denial of the claims, the Carrier contended that the work undertaken by Great Lakes Construction was demolition of catenaries, "which is not typically undertaken by B&B forces." The Carrier went on to note that the Organization was provided notice that the work would be contracted, per the Agreement between the parties.


At the outset, we note that the Division Engineer erroneously stated that notice had been served regarding the contracting in both claims noted supra. In the circumstances however, we concur with the Carrier's contention that notice was not required for the demolition work because there is not even a colorable showing that it was covered by the Scope Rule or by custom, practice or tradition thereunder, thereby rendering that portion of the claim invalid.


Turning to the merits issue, in order to prevail in this dispute it was incumbent upon the Organization to: (1) cite specific language within the applicable Scope Rule that reserves demolition work to the Claimants; or, (2) demonstrate that

Form 1 Award No. 36795
Page 4 Docket No. MW-36263
03-3-00-3-491

BMWE-represented employees had by customary and historical practice performed the disputed work. The Organization was unable to shoulder that burden on the record before the Board. Rather, the record evidence supports the Carrier's contention that the work which Great Lakes Construction performed on the dates at issue "was of the type not typically undertaken by B&B forces," and that same has "historically been contracted out on Conrail."










This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 29th day of December 2003.