Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36795
Docket No. MW-36263
03-3-00-3-491
The Third Division consisted of the regular members and in addition Referee
Nancy F. Eischen when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (Great Lakes Construction Company) to perform
Maintenance of Way work (demolish and remove a bridge and
fill gap cause by removal with ballast and tamp with
compactor) at the bridge at Mile Post 0.45 on the Cleveland
Short Line in Cleveland, Ohio beginning on April 22 and
continuing through May 8, 1998 [Carrier's File 12(99-642)].
(2) The Agreement was violated when the Carrier assigned outside
forces (Great Lakes Construction Company) to perform
Maintenance of Way work (burning out anchor bolts and
removing steel structures and concrete support bases) at the
Catenary Structures between Mile Posts 0.0 and 5.0 on the
Cleveland Short Line in Cleveland Ohio on May 11 and
continuing through May 15, 1998 [Carriers File 12(99-643)].
(3) The Agreement was further violated when the Carrier failed to
furnish the General Chairman with proper advance written
notice of its intent to contract out said work or discuss the
matter in good faith as required by the Scope Rule.
Form 1 Award No. 36795
Page 2 Docket No. MW-36263
03-3-00-3-491
(4) As a consequence of the violation referred to in Parts (1) and/or
(3) above, Claimants K. G. Champa, F. R. Hoyt, J. D'Orazio, S.
J. La Cavera and R. H. Zinni shall now each be compensated
for eight (8) hours' pay at their appropriate straight time rates
of pay for each date of April 22, 23, 24, 27, 28, 29, May 4, 5, 6,
7, and 8, 1998.
(5) As a consequence of the violations referred to in Parts (2)
and/or (3) above, Claimants K. G. Champa, F. R. Hoyt, R. H.
Zinni and K. Watts shall now each be compensated for eight (8)
hours' pay at their appropriate straight time rates of pay for
each date of May 11, 12, 13, 14 and 15, 1998."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
The Organization combined two claims in this docket. Between April 22 and
May 8, 1998, the Carrier employed Great Lakes Construction, to "demolish an old
roadway bridge" at MP 0.45 on the Cleveland Short Line. The contractor then
filled the gap with stone. During the period of May 11 - 15, 1998 Great Lakes
Construction removed "old steel Catenary Structures" between MP 0.0 and 5.0 on
the Cleveland Short Line.
In each claim the Organization asserts that its employees have "historically"
done this work. Specifically, the Assistant General Chairman contended that:
Form 1 Award No. 36795
Page 3 Docket No. MW-36263
03-3-00-3-491
"This claim is for eight hours each day at the Claimants appropriate
straight time rates of pay when the Carrier violated the Scope, Rule
1, Rule 3 of our 1996 Agreement and Article XV of the 1996
National Agreement when it called and used an outside contractor
on April 22, 23, 24, 27, 28, 29, May 4, 5, 6, 7 &8, 1998 at Mile Post
0.45 on the Cleveland Short Line in Cleveland, Ohio.
On the claim dates, it was determined by the Carrier Supervision to
use this outside concern to perform duties that are consistent with
the functions of M of W employees prescribed in our Agreement.
Rather than calling the Claimants who were ready, willing, qualified
and able to perform these duties, the Carrier Supervision used this
outside contractor.
The Carrier violated the Scope Rule of our Agreement when it failed
to give the General Chairman advanced written notice that this
work was to be performed by an outside concern, which alone makes
this a valid claim."
In its denial of the claims, the Carrier contended that the work undertaken by
Great Lakes Construction was demolition of catenaries, "which is not typically
undertaken by B&B forces." The Carrier went on to note that the Organization
was provided notice that the work would be contracted, per the Agreement between
the parties.
At the outset, we note that the Division Engineer erroneously stated that
notice had been served regarding the contracting in both claims noted supra. In the
circumstances however, we concur with the Carrier's contention that notice was not
required for the demolition work because there is not even a colorable showing that
it was covered by the Scope Rule or by custom, practice or tradition thereunder,
thereby rendering that portion of the claim invalid.
Turning to the merits issue, in order to prevail in this dispute it was
incumbent upon the Organization to: (1) cite specific language within the applicable
Scope Rule that reserves demolition work to the Claimants; or, (2) demonstrate that
Form 1 Award No. 36795
Page 4 Docket No. MW-36263
03-3-00-3-491
BMWE-represented employees had by customary and historical practice
performed the disputed work. The Organization was unable to shoulder that
burden on the record before the Board. Rather, the record evidence supports the
Carrier's contention that the work which Great Lakes Construction performed on
the dates at issue "was of the type not typically undertaken by B&B forces," and
that same has "historically been contracted out on Conrail."
Premised upon the foregoing, this claim must be denied.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 29th day of December 2003.