Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36827
Docket No. MW-35312
04-3-99-3-160
The Third Division consisted of the regular members and in addition Referee
Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(CSX Transportation, Inc. [former Louisville and
( Nashville Railroad Company (former Monon Railroad)]
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to perform Maintenance of Way work (minor steel
repairs and installation of steel bridge spans and a new timber
deck) at Bridge Q124.2 on the Monon Seniority District,
Chicago Service Lane in the vicinity of Lafayette, Indiana
beginning November 29, 1997 through February 3, 1998
(System File 98231.MB/12 (98-870) MNN].
(2) The Agreement was further violated when the Carrier failed to
make a good faith effort to reduce the incidence of contracting
out scope covered work and increase the use of its Maintenance
of Way forces as required by Rule 60 and the December 11,
1981 Letter of Understanding.
(3) As a consequence of the violations referred to in Parts (1)
and/or (2) above, Bridge Subdepartment Foreman R. E. White,
Truck Driver/Carpenter L. L. Phillips, Carpenters J. Miller
and W. J. Tyson shall each be compensated for three hundred
forty (340) hours at their respective rates of pay and one
hundred forty-three and one-half (143.5) hours at their
respective time and one-half rates of pay."
Form 1 Award No. 36827
Page 2 Docket No. MW-35312
04-3-99-3-160
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
By notice dated October 30, 1997, the Carrier advised the Organization that
it intended to contract out the replacement of two steel spans, plus minor steel
repairs to the third span and the installation of a new timber deck on Bridge 124.2
at Lafayette, Indiana, on the Monon Subdivision. Further, according to the notice,
the "Carrier has no alternative to contracting this work due to the fact that we do
not have adequate equipment laid up (i.e., large crane, boom truck, backhoe) . . .
with which the work may be done."
Conference was held, without resolution. The Carrier then contracted out
the work.
The Organization asserted on the property that "[t]here is a 50 ton
locomotive crane that is parked at Mitchell, Indiana . . . [which] is more than big
enough to do the job." The Organization further pointed out that a boom truck and
backhoe were also available for the job.
The Carrier responded:
".
. . Carrier does not have available the necessary equipment
provided by the contractor. Yes, Carrier owns a 50-ton crane that is
currently idle. However, the contractor provides an 80-ton crane
that is necessary for the safe and efficient accomplishment of the
Form 1 Award No. 36827
Page 3 Docket No. MW-35312
04-3-99-3-160
project. The contractor also provides a rail-mounted graddall, a
rail-mounted rotary dump truck, and a bob cat - none of which are
possessed or available to the Carrier."
This record is in conflict over what equipment was actually necessary to
perform the work; wheither the Carrier had the equipment and whether the
equipment was available to the Carrier from outside sources. The Organization
contends that the Carrier had sufficient equipment to perform the work. The
Carrier states that it did not (i.e., it needed a larger crane than it possessed and it
did not have certain other equipment at all); the necessary equipment was not
available to it; and the contractor had the equipment to perform the work. Without
more from the Organization showing that the necessary equipment was available to
the Carrier (either in its adequacy to perform the work; in its possession; or
whether it could be obtained from outside rental sources) we are unable to resolve
the conflict concerning the equipment in the Organization's favor. The claim shall
therefore be denied.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, ithis 28th day of January 2004.