Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 36960
Docket No. MW-36069
04-3-00-3-227

The Third Division consisted of the regular members and in addition Referee Edwin H. Benn when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.
Form 1 Award No. 36960
Page 2 Docket No. MW-36069
04-3-00-3-227

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.






Conference between the parties did not resolve the Organization's objection to the Carrier's use of an outside contractor to perform the work. The contractor performed the work. This claim followed.

On the property, the Carrier explained its reasons for using an outside contractor on this project:

Form 1 Award No. 36960
Page 3 Docket No. MW-36069
04-3-00-3-227
crane to facilitate the handling of the cast ballast pans, and thereby
creating an additional expense.
The height of the project, 63 feet above ground level, is a concern
along with an appropriate amount of experience working with fall
protection. Wearing safety harnesses and following proper fall
protection procedures are only a component of this project, the
workers needed to be able to apply fall protection procedures while
maintaining high levels of production output. A person is not
capable of working at a production rate just because a safety
harness has been worn previously. Experience with fall protection is
developed over a continuous period of time, not a few days here and
a few days there. These two factors, production output and fall
protection experience, needed to be combined on this project to
ensure that the completion date was met in a safe and efficient
manner.
All lifts, while on the bridge, whether placing or removing material,
needed to be made such that the loads were in close proximity to
workers in fall protection equipment at great heights. Workers had
to be in these positions to make the connection and guide the
material being lifted or lowered. This is not a position to have a
worker gain on the job training, and it is again the combination of
situations that present a hazard, working around suspended loads
and wearing fall protection.
The project had time constraints placed on it, the track was removed
from service for a total of 20 days. This allowed only a short period
of time, 14 calendar days, for the removal and installation of the
concrete ballast pans. These deadlines were necessary to ensure that
the interruption of train traffic was minimized.
The DM&IR does not have the amount of working supervision that
is required for a project of this magnitude, and complexity. The
Contract supervision would have to ensure that the procedures of
the project drawings and specifications are being met on a daily
Form 1 Award No. 36960
Page 4 Docket No. MW-36069
04-3-00-3-227



The Organization attempted to counter the Carrier's assertions, maintaining that the Carrier owned a 50 ton Pettibone crane which was available and would have worked well in lifting the tubs; the tubs could have been poured in the car shop area, lifted onto flat cars by the crane and transported to the bridge; the job was performed when the weather could not have been considered inclement; spring and summer months would have been ideal for the pouring of the tubs by B&B employees; and the B&B employees worked at similar heights on a daily basis at the ore docks and used safety harnesses.


The Carrier responded that although it had a 60 ton Pettibone crane, that equipment was stationed for use at the Two Harbors Dock and was not available for the Holman Bridge project; given the projects underway at the time and the size of the Holman Bridge project, the entire B&B group would have had to work on the Holman Bridge project for about a three month period and no other work could have been accomplished; the time factor was important because the BNSF operates loaded taconite trains over the Holman Bridge on a daily basis and those trains had to be rerouted during the decking replacement and the contractor was under stringent time constraints to complete the work within a 14 day window.


Supplement No. 3, Paragraph (a) mandates that the Carrier ". . . will make every reasonable effort to perform all maintenance work in the Maintenance of Way and Structures Department with its own forces." Supplement No. 3, Paragraph (b) further states that "Consistent with the skills available in the Bridge and Building Department and the equipment owned by the Company, the Railway Company will make every reasonable effort to hold to a minimum the amount of new construction work contracted."

Form 1 Award No. 36960
Page 5 Docket No. MW-36069
04-3-00-3-227

In Third Division Award 30897, the Board addressed a similar dispute arising under Supplement No. 3 between the parties:



This case also arises under Supplement No. 3. Given the complexity and magnitude of the Holman Bridge project; the needed equipment and facilities that were not available to the Carrier; the short time constraints involved; and the consequences of having to shift such a substantial amount of the Carrier's manpower to perform that job to the detriment of other ongoing work, the reasoning in Third Division .Award 30897 applies to his case.


Form 1 Award No. 36960
Page 6 Docket No. MW-36069
04-3-00-3-227







This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 21st day of April 2004.