Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 37109
Docket No. SG-37128
04-3-02-3-94

The Third Division consisted of the regular members and in addition Referee Steven M. Bierig when award was rendered.

(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE:



STATEMENT OF CLAIM:



FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.
Form 1 Award No. 37109
Page 2 Docket No. SG-37128
04-3-02-3-94

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The facts of the instant matter do not appear to be in dispute. Between October 30 and November 17, 2000, the Carrier used a System Signal Construction Gang to perform work on the Indianapolis Subdivision. Specifically, System Signal Construction Gang No. 7XF6, consisting of four Signalmen, prepared for completion of a major construction project covering a significant amount of territory where a large BMWE System Production Gang was scheduled to perform tie and surfacing work. The disputed work included removing staples from track leads, removing fasteners for the termination tie shunts and marking the signal wires so that they would be visible for the track forces while doing their work.


By letter dated December 26, 2000, the Organization submitted its claim alleging that the Carrier violated CSXT Labor Agreement No. 15-18-94 because the work the System Signal Construction Gang performed, ". . . was preparation on the Indianapolis Sub-Division for a tie and surfacing unit . . . ."


Thus, the issue in the instant case is whether the Carrier erred when it assigned a System Signal Construction Gang to complete work on the Indianapolis Subdivision. It is clear that CSXT Labor Agreement No. 15-18-94 specifies that System Signal Construction Gangs were established for the purpose of performing construction work rather than maintenance work.


The Organization takes the position that the Carrier was required to assign employees of the Toledo Indianapolis Maintenance Gang covering the Indianapolis Subdivision to the work in question because the tasks involved maintenance and not construction work. The Organization requests pay for the Claimants in the amount of 320 hours at the Signalman's rate of pay and 110 hours at the Foreman's rate of pay to be divided equally among the Claimants for this loss of work opportunity.


Conversely, the Carrier takes the position that it acted properly. CSXT Labor Agreement No. 15-18-94 provides for the use of System Signal Construction

Form 1 Award No. 37109
Page 3 Docket No. SG-37128
04-3-02-3-94

Gangs when more than routine maintenance work is required or a major revision of an existing system is needed. In the instant situation, the system work included, among other tasks, removing hundreds of staples from track leads, removing hundreds of fasteners that hold the termination shunts to ties and marking signal wires as needed for a capital construction project. According to the Carrier, this was a major revision that allowed for the use of a System Signal Construction Gang.


The relevant language of CSXT Labor Agreement No. 15-18-94 provides as follows:



After a review of all evidence, the Board finds that it must agree with the Carrier. The burden of proof in this matter falls on the Organization to prove that the Carrier should have assigned a maintenance crew to the project. In a similar case, Third Division Award 33152, the Board ruled for the Carrier:


Form 1 Award No. 37109
Page 4 Docket No. SG-37128
04-3-02-3-94







Form 1 Award No. 37109
Page 5 Docket No. SG-37128
04-3-02-3-94

In the instant case, the Carrier utilized the System Signal Construction Gang in a manner consistent with the intent of CSXT Labor Agreement No. 15-18-94. The work involved in this case was construction work, and therefore, it was appropriate to use a System Signal Construction Gang to perform the work. We find that the Organization has been unable to meet its burden of proof. Thus, the claim must be denied.




      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 25th day of August 2004.