Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 37169
Docket No. MW-36264
04-3-00-3-495

The Third Division consisted of the regular members and in addition Referee Dana Edward Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





Form 1 Award No. 37169
Page 2 Docket No. MW-36264
04-3-00-3-495

FINDINGS :

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



Under date of March 19, 1998, Senior Director-Labor Relations J. H. Burton notified the BMWE General Chairmen in Pennsylvania and Ohio as follows:







Pertinent to this case, General Chairman P. K. Geller, Sr. responded by letter dated March 31, 1988, as follows:
Form 1 Award No. 37169
Page 3 Docket No. MW-36264
04-3-00-3-495




There is disagreement between the parties concerning the Carrier's compliance with the notice and "notice deliberation" conference requirements of the Scope Rule. However, the notice is not fatally deficient and our review of the evidence reveals an exchange of correspondence in April 1998 confirming such notice and conference. Thus, we are persuaded that Part 2 of the claim must be denied and we turn our attention to the positions of the parties on the merits issue of the claim, as presented on the property.


The accuracy of the following description of the specific work at issue in this case, set forth in the claim letter, was never disputed or contradicted in handling on the property:


Form 1 Award No. 37169
Page 4 Docket No. MW-36264
04-3-00-3-495


The question presented for determination is whether performance of that work on the claim dates by employees of B&B Excavating Company, under subcontract with the Carrier, violated the contractual rights of the Claimants under the Scope Rule of the controlling ConrailBMWE Agreement. From the probative evidence and authoritative precedents in the case record before us in this matter, we are persuaded that question must be answered in the affirmative.


The respective positions and arguments presented by the parties in this case are not matters of first impression. Indeed, the drain pipe and catch basin work in dispute in this case is virtually indistinguishable from that considered and discussed by the Board in a sustaining decision in Third Division Award 37046 (cited by the Organization) whereas the denial decision in Third Division Award 30845 (cited by Carrier) concerned "so-called sub-ballast work." In Third Division Award 37046 the Board found that the Carrier failed altogether to give notice or hold a conference and had this to say about Scope Rule coverage of the specific work at issue:



Form 1 Award No. 37169
Page 5 Docket No. MW-36264
04-3-00-3-495





Nothing in the decision of the Board in Third Division Award 37046, in which the specific work at issue, the parties and the contract language are identical with the issue, parties and language in the present case, persuades us that it was wrongly decided or that its findings should not be considered dispositive of the present claim. We have often pointed out with only marginal success that the penchant of these parties for forum shopping and seemingly endless re-litigation of matters which should be settled by a soundly reasoned "final and binding" arbitration decision has served no useful purpose and generated much mischief.


Specifically, this claim is sustained because the water drainage line and catch basin work subcontracted by the Carrier over the objection of the Organization was "within the Scope of the Agreement" and the Carrier failed to provide any evidence to support its bare assertions of affirmative defenses i.e., that the project involved in

Form 1 Award No. 37169
Page 6 Docket No. MW-36264
04-3-00-3-495

this matter was of such character that BMWE-represented employees could not perform the tasks and/or that any specialized or unavailable equipment was required or used.


As for the appropriate remedy, we find Third Division Award 37046 to be on point, persuasive and dispositive:




Based on all of the foregoing, the Carrier is directed to compensate each Claimant an equal and proportionate share of all straight time and overtime hours expended by the outside forces in performance of said work at his/her respective, rate of pay.








This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 28th day of September 2004.