Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 37169
Docket No. MW-36264
04-3-00-3-495
The Third Division consisted of the regular members and in addition Referee
Dana Edward Eischen when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that
(1) The Agreement was violated when the Carrier assigned
outside forces (B&B Excavating Company) to perform
Maintenance of Way work (build roadway, dig drainage
ditches, install plastic pipe and concrete catch basins) between
Mile Posts 7 and 9 on the Cleveland Short Line in Cleveland,
Ohio beginning on May 11 and continuing through June 5,
1998 [Carrier's Files 12(99-543) and 12(99-644)].
(2) The Agreement was further violated when the Carrier failed to
furnish the General Chairman with advance written notice of
its intent to contract out the work described in Part (1) and (2)
above as required by the Scope Rule.
(3) As a consequence of the violations referred to in Parts (1)
and/or (2) above, Claimants K. G. Champa, F. R. Hoyt, R. H.
Zinni, K. Watts, J. D'Orazio and S. J. LaCavera shall now each
be compensated for eight (8) hours' pay at their appropriate
straight time rates of pay for each date of May 11, 12, 13, 14,
15, 18, 19, 20, 21, 22, 26, 27, 28, 29, June 1, 2, 3, 4 and 5, 1998,
and credit toward vacation and all other benefits."
Form 1 Award No. 37169
Page 2 Docket No. MW-36264
04-3-00-3-495
FINDINGS
:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
Under date of March 19, 1998, Senior Director-Labor Relations J. H. Burton
notified the BMWE General Chairmen in Pennsylvania and Ohio as follows:
"File: 013.27.04-1690 Installations of Ballast Pads, Cleveland &
Berea, Ohio
Gentlemen:
Solely as information, we intend to contract for the necessary
grading, drainage and ballast pad construction to support the track
construction at Berea, Ohio and on various locations along the Short
Line in Cleveland, Ohio. The contractor will distribute, grade and
compact the ballast on Conrail property. This work is for the
construction of a second track for the Short Line and for the
construction of a second track at Berea. Conrail forces will perform
all track construction.
We do not possess the necessary equipment and qualified operators
to do the grading work required to meet the project schedule. In
any event, the Carrier anticipates that it will recall furloughed
BMWE employees before the time we award the contract."
Pertinent to this case, General Chairman P. K. Geller, Sr. responded by letter
dated March 31, 1988, as follows:
Form 1 Award No. 37169
Page 3 Docket No. MW-36264
04-3-00-3-495
"Reference your letter dated March 19, 1998 addressed to both Mr.
Jed Dodd, General Chairman and myself, received in my office
March 23, 1998 relative to the above subject.
I believe you are aware I am opposed to your request contending
this work is not covered by the Scope and the AM hasn't
performed this work. The Scope is clear that work previously
performed on the former territory will not be removed from them.
Moreover, I must point out that the work to be performed in this
instance is clearly covered by the Scope. One cannot argue that
maintenance and repair of tracks and right-of-ways, roads, parking
facilities, drainage repairs and crossings are not railroad
Maintenance of Way work. Also the installation of ballast pads.
Also, you contend that the BMWE does not possess the necessary
equipment and qualified operators to perform the grading work. It
is my position that the carrier has not provided any evidence to
support to support these statements. The equipment required for
this work is available on the property and if there is equipment
which you contend you do not have, please advise so that we can
contact a vendor to rent or lease equipment required to perform this
BMWE work. The carrier has failed to provide any evidence that
our forces are not skilled for this assignment."
There is disagreement between the parties concerning the Carrier's
compliance with the notice and "notice deliberation" conference requirements of the
Scope Rule. However, the notice is not fatally deficient and our review of the
evidence reveals an exchange of correspondence in April 1998 confirming such
notice and conference. Thus, we are persuaded that Part 2 of the claim must be
denied and we turn our attention to the positions of the parties on the merits issue of
the claim, as presented on the property.
The accuracy of the following description of the specific work at issue in this
case, set forth in the claim letter, was never disputed or contradicted in handling on
the property:
"On the above dates six employees from B&B Excavating Co.
performed the duties of a Foreman, Mechanics, and Machine
Form 1 Award No. 37169
Page 4 Docket No. MW-36264
04-3-00-3-495
Operators. They performed this work with a bulldozer, front end
loader and a backhoe. This work consisted of installing 12" plastic
pipe and concrete catch basins in the tunnels and along the main line
track for the new track that is to be installed."
The question presented for determination is whether performance of that
work on the claim dates by employees of B&B Excavating Company, under
subcontract with the Carrier, violated the contractual rights of the Claimants under
the Scope Rule of the controlling ConrailBMWE Agreement. From the probative
evidence and authoritative precedents in the case record before us in this matter, we
are persuaded that question must be answered in the affirmative.
The respective positions and arguments presented by the parties in this case
are not matters of first impression. Indeed, the drain pipe and catch basin work in
dispute in this case is virtually indistinguishable from that considered and discussed
by the Board in a sustaining decision in Third Division Award 37046 (cited by the
Organization) whereas the denial decision in Third Division Award 30845 (cited by
Carrier) concerned "so-called sub-ballast work." In Third Division Award 37046
the Board found that the Carrier failed altogether to give notice or hold a
conference and had this to say about Scope Rule coverage of the specific work at
issue:
"The specific work performed by the contractor as described by the
Organization was the installation of water drainage lines between and
parallel to the tracks in the receiving yard and road railer tracks and
installation of distribution boxes to connect the various lines in
Rochester Yard. The work required the contractor to use two dump
trucks, two Machine Operators (backhoe and front-end loader), a
Foreman and two Laborers.
The Scope Rule covers `. . . work generally recognized as Maintenance
of Way work, such as . . . construction, repair, and maintenance of
water facilities .... Rule 1 of the Agreement lists the operation of
front-end loaders and backhoes as work, covered by the Agreement.
Further, Rule 1 encompasses the operation of vehicles, which we find
includes dump trucks .... Therefore, the kind of work involved in this
dispute - installation of water drainage lines and distribution boxes to
Form 1 Award No. 37169
Page 5 Docket No. MW-36264
04-3-00-3-495
connect the various lines through the use of front-end loaders,
backhoes, and dump trucks - is work `within the scope of this
Agreement.'
The Carrier's argument that the Organization must show that
Maintenance of Way employees exclusively performed the work in
contracting out disputes is not persuasive and has long been rejected.
The Carrier's argument that the Organization has not shown that it
has performed the precise work at issue also does not change the result .
. . . The type of work in dispute is work `within the scope of this
Agreement.' That is as far as our inquiry can go.
There is no evidence that the project involved in this matter was of
such character that BMWE-represented employees could not
perform the tasks or that such specialized equipment was involved.
In this case, the contractor used dump trucks, a backhoe, and a
front-end loader. That is the kind of equipment that the covered
employees routinely use."
Nothing in the decision of the Board in Third Division Award 37046, in which
the specific work at issue, the parties and the contract language are identical with
the issue, parties and language in the present case, persuades us that it was wrongly
decided or that its findings should not be considered dispositive of the present claim.
We have often pointed out with only marginal success that the penchant of these
parties for forum shopping and seemingly endless re-litigation of matters which
should be settled by a soundly reasoned "final and binding" arbitration decision has
served no useful purpose and generated much mischief.
Specifically, this claim is sustained because the water drainage line and catch
basin work subcontracted by the Carrier over the objection of the Organization was
"within the Scope of the Agreement" and the Carrier failed to provide any evidence
to support its bare assertions of affirmative defenses i.e., that the project involved in
Form 1 Award No. 37169
Page 6 Docket No. MW-36264
04-3-00-3-495
this matter was of such character that BMWE-represented employees could not
perform the tasks and/or that any specialized or unavailable equipment was
required or used.
As for the appropriate remedy, we find Third Division Award 37046 to be on
point, persuasive and dispositive:
"[Ijn these kinds of disputes, make whole remedies are granted to
employees for lost work opportunities even though those employees
may have been working. See Third Division Awards 32335, 31594
and 30944."
Based on all of the foregoing, the Carrier is directed to compensate each
Claimant an equal and proportionate share of all straight time and overtime hours
expended by the outside forces in performance of said work at his/her respective,
rate of pay.
AWARD
Claim sustained in accordance with the Findings.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an award favorable to the Claimant(s) be made. The Carrier is ordered to make
the Award effective on or before 30 days following the postmark date the Award is
transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 28th day of September 2004.