Form 1  NATIONAL RAILROAD ADJUSTMENT THIRD DIVISION
 
Award o.3723
Docket No: 37670
  
04-3-0-3-1
The Third Division consisted of the regular members and in addition Referee
Nancy F: Eischen when award was 
rendered. , ,
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
 
(CSX Transportation, Inc. 
(former 
Seaboard Coast Line
 
( Railroad Company)
STATEMENT F CL
"Claim on behalf of the General 
Committee 
of the Brotherhood of
Railroad Signalmen on the CSX Transportation, Inc. (CST):
Claim on behalf of R. L: Cooper, for one hour at the time 
and 
one-half
rate of pay, account Carrier violated the current Signalmen s
Agreement particularly the Scope Rule, when it allowed an outsie
contractor to remove a signal and a signal foundation on October 7,
2001; and deprived the Claimant of the opportunity t® perform this
work, Carrier's File o. 02-0039. General Chairman's File No: SCL0-1-02.A® BRS File Case No. 1417-SCL."
F GS:
The Third Division of the Adjustment Board, upon the whole record an all 
the
evidence, 
finds that:
The carrier or carriers and the employee or employees involved in this dispute are
respectively carrier and employee within the meaning of the Railway Laor Act, as
approve June 21,1934.
This Division of the Adjustment Board has jurisdiction over the dispute involve
herein.
Parties to said dispute ere given unticf hearing thereon.
For 1  sward No. 3723
Page 2 Docket o. S-37670
  
04-3--3-1
On October 7, 2001 the Carrier directed the Claimant's signal construction team
to 
remove a dead signal from its location. Following a failed second attempt by the
signal force crew to remove same, the Carrier authorized a Track Hoe Operator, who
was working in the vicinity, to remove the dismantled signal mast from its foundation.
In his initial claim, submitted on December 7, 2001 the Claimant asserted the
following:
"Crew of men outside contractor removed old signal and foundation
from right away. 
Due 
to lack of Signalmen to perform task as quickly
as requested by project engineer of maintenance."
The Carrier denied the Organization's February 20, 2002 appeal, premised, i
pertinent part, upon the following:
"Our review of the facts in this case reveals that on October 7, 2001 the
Carrier directed the Claimant's signal construction team to remove a
dead signal from 
its location. However, the 
location was not accessible
to team's boom truck because of tight clearances and the probability o
damaging or immobilizing the boom truck. Therefore, the Carrier
authorized a track hoe operator, who was working in the vicinity, to
remove the dismantled signal mast from its foundation. This task 
took
less than 1intes for the operator to complete. Moreover, the
operator performed no work on the signal itself. He merely lifted the
mast from the signal foundation and set it on the ground.
Given, these circumstances, the Carrier fails to see where it would have
violated the agreement. Indeed, the Claimant himself was present t
the site during the brief period of time in which the track hoe operator
removed the mast and then place it on the round. Tasks of this
nature must a considere de mini us work t best. Furthermore, the
Organization's request for punitive damages for work performed
during normal business ours is clearly misplaced. In light of the
safety issues in this case and the fact that the work was f an extremely
sort duration, the Carrier's decision to allo t track hoe operator t
remove si nl fro its foundation id not violate the Agreement."
Form 
1 Award No. 3723
Page 3 Docket No. -37670
 
0-3-0-3-15
 
,Tune 7, 2002 conference ryas held, however, no additional information 
or
arguments were presented by the Organization that induced the Carrier 
to 
reconsider
its earlier 
denials.
review of the record demonstrates that the 
Claimant's 
signal construction
crew was 
given 
two opportunities to remove a nonfunctional signal mast but was 
unable
to accomplish same. Specifically, the crew truck became stuck in the soft ground
several feet from 
the 
desired location: The contractor, who was already working at the
location with a track hoe, laid the signal out of 
the 
way 
until the Claimant's 
crew 
could
et its boom truck into position. Thereafter, the foundation was bulldozed over,
because it was no longer needed, and Signalmen assisted in the mast removal by
disconnecting the signal cable and removing the bolts that held the mast to the stand,,
In light of the Carrier crew's inability to lay the signal out of the way, the
Carrier had no alternative but to use the contractor to accomplish the necessary task.
There is no dispute that the contractor vas already working at the 
site and 
that the task
in 
dispute took less 
than 
15 minutes to complete. Furthermore, o S-represented
employees were adversely affected as a result of the contractor's de mini mus
contribution to the project. Therefore, the claim must be denied:
AWARD
Claim denied.
ORDER
This r, after consideration of the dispute identified above, here orders that
awar favorable to the li ant(s) not made.
NATIONAL T
 
y Order 
of Third Division
ate t Chicago, Illinois; this 7th day of October 4®