Form 1 NATIONAL RAILROAD JUT NT BOARD
The Third Division consisted of the regular members and in addition Referee
Nancy F.
Eischen
when award was rendered.
(Brotherhood 4f Railroad Signalmen
(CSX Transortation; Inc. (former Seaboard Coast Line
"Claim on behalf of the General Committee of the Brotherhood of
ailroad Signalmen on the CSX Transportation, Inc. (CSXT):
Claim on behalf of . H. Phillips, for one hour at the time and onehlf rate of pay, account Carrier violated the current Signalmen
S
Agreement particularly the Scope Rule, when it allowed an outside
contractor to remove signal foundation that was to a re-used at
iami Plantation on October 7, 2001, and deprived the Claimant of
the opportunity to perform this work. Carrier's File o. 02-0044.
General Chairman's File No: SCL-03-04-02A. B RS File Case o.
12422-SCL."
FINDINGS:
The Third Division of the Adjustment oar, upon the whole recor and all t
. . . evidence, finds that:
The carrier or carriers an the employee or employees involved in this
dispute
are respectively carrier and employee in the ein of the Railway Labor
AC4
approved June 21,1934.
This Division of the Adjustment Board
has
jurisdiction over the dispute
involved herein.
Form 1 Award o. 37239
Paga Docket o. 37700
04-3-03-3-3
Parties to said dispute were given due notice of hearing thereon.
The Claimant in this case is R. H. Phillips, Who, at the time this dispute arose,
was assigned to the position of Signalmen. A review of the record demonstrates that
on October 7, 2001, the Claimant's signal force was ice assigned the task of
removing a nonfunctional signal mast,
but
twice failed to accomplish same:
p
ecifcally, due to soft ground, the Claimant's crew was unable to move
its
boo
truck next to the signal mast to remove it from its foundation. Therefore, the
Carrier asked a contractor, who was already working at the location with
a
track
hoe,
to lay
the signal out of the way until CST personnel could get their boom
truck into the location. Thereafter, the foundation was bulldozed over because it
was no longer needed, and Signalmen assisted in the mast removal by disconnecting
the signal cable and removing the
bolts
that held the mast to the stand.
In his November 21, 2001 claim the Local Chairman asserted that the Carrier
violated the Scope Rule on Sunday, October 7, 2001 when a contractor removed
signal and its foundation at Miami Plantation on the F BU.
The Carrier denied the Organization's arch 4, 2002 appeal, premised, i
pertinent art, upon the following:
" ur review of the facts
in
this case reveals that on October 7, 2001
the Carrier directed the Claimant's signal construction team t
remove a dead signal from its location. However, the location as
not accessible to tea's boom truck because f tight clearances and
t probabili of damaging r immobilizing boom truck.
Therefore, the Carrier authorize track hoe operator,
who
s
orking in the vicinity, to remove the dismantled signal mast from
its foundation. This task took less than 15 minutes for the operator
to complete., Moreover, the operator performed n t
signal itself. He merely lifted the mast fro the signal foundation
and set it on the ground.
Given, these circumstances, Carrier fails to see ere it would v
violate the agreement. Indeed, the Claimant himself as resent at
e site during the brief period f
time
in Which te track hoe
Form 1 Award o. 37239
Paga Docket : SG-37700
04-3-0 -3-
operator removed the mast
and
then placed. it on the ground. Tasks
of this nature must be considered de inius work at best.
Furthermore, the Organization's request
for punitive damages for
work performed during normal business hours is
clearly
misplaced.
In light of the safety issues in'this case and the fact that the
work
was
of ad extremely short duration; the Carrier's decision to allow
the
track
hoe
operator to remove the signal from its foundation did
not violate the Agreement."
This claim is indistinguishable in any material aspect from the companion
claim in Third Division Award 37238, also before the Board, with the only
difference being the named Claimant. For reasons set forth more fully in Award
37238, this claim likewise is denied:
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Awrfavorable to te Claimants) not be e.
TI IONAL RAILROAD ADJUSTMENT BOARD
Order Tiivisi n
ate at i, Illinois, this 7th ft