Form 1 NATIONAL: RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 37333
Docket No. SG-37415
05-3-02-3-461

The Third Division consisted of the regular members and in addition Referee Nancy F. Eischen when award was rendered.


PARTIES TO DISPUTE:
(CSX Transportation, Inc. (former Baltimore &
( Ohio Railroad Company)

STATEMENT OF CLAIM:



FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
Form 1 Award No. 37333
Page 2 Docket No. SG-37415
05-3-02-3-461

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The Claimants in this dispute are CSX Signal employees, all of whom work in the Greater Cincinnati, Ohio, Terminal area. In a letter dated May 15, 2001, the Organization submitted a claim in which it alleged that the Carrier violated the B&O Signalmen's Agreement, particularly Rule 31, and Section 4 of the March 1984 Cincinnati Terminal Agreement, ". . . when the Carrier used system signal construction gangs to perform maintenance work on existing switches within the Cincinnati Terminal area. . . :' Specifically, the Organization contended that the Carrier failed to maintain an adequate work force in Cincinnati Terminal area in order to "meet the requirements of service." As a result, the Organization demanded that the Carrier compensate the Claimants at the straight time rate for "all work performed in the Cincinnati Terminal area," and restore five Signal Maintainer's positions and two Lead Signal Maintainer's positions.


In its July 6, 2001 reply, the Carrier confirmed that the construction team was brought to the property to "install electric locks on existing switches," but maintained that the construction crew did not perform any "scheduled maintenance." The Carrier went on to note that none of the signal employees in the affected area suffered a loss of wages. Finally, the Carrier maintained that the Organization failed to provide sufficient documentation to support its claim.


The Organization appealed the Carrier's denial contending that the work at issue accrued to the Claimants and was "not system signal gang work." In that connection, the Organization asserted that the Carrier's "failure" to properly maintain the existing work force and signal equipment did not "entitle Carrier to violate the Agreement" In its final denial to the claim, the Carrier reaffirmed that (1) the work in dispute entailed a "major revision" to the signal system (2) the

Form 1 Award No. 37333
Page 3 Docket No. SG-37415
05-3-02-3-461

Claimants were working at the time of the dispute; and (3) the Organization's claim was premised upon "insufficient evidence."


Except for the specific task involved (installing electric locks to comply with FRA regulations vs. replacing bond strand and rail connectors (a.k.a."STN" or "chicken head") the contract interpretation/application issues presented in this case are virtually indistinguishable from those decided by the Board in Third Division Award 33152. In that decision, the Board held:




Form 1 Award No. 37333
Page 4 Docket No. SG-37415
05-3-02-3-461




The judicial doctrines of stare decisis and res iudicata do not apply strictly in labor-management arbitration. As a practical matter, however, where a prior decision covers the same parties, issues, facts and contract language, a subsequent arbitrator often will consider the interpretation laid down in the earlier Award as a binding part of the Agreement, unless and until the parties change the language. Even those who refuse to hold prior Awards binding would give them serious and weighty consideration when called upon to interpret the same language. It is not necessary that the subsequent arbitrator endorse all of the reasoning expressed in the earlier opinion. What is important is that the earlier Award contains a holding that is not palpably erroneous. In such circumstances, arbitrators generally conclude that it would be a disservice to the parties to subject them to the unsettling effects of conflicting and inconsistent interpretations of the same contract language in the same set of circumstances.


Based on all of the foregoing, we conclude that Third Division Award 33152 is authoritative precedent that supports the denial of the present claim.

Form 1 Award No. 37333
Page 5 Docket No. SG-37415
05-3-02-3-461







This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 19th day of January 2005.