Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 37384
Docket No. SG-37024
05-3-01-3-666
The Third Division consisted of the regular members and in addition Referee
Robert Perkovich when award was rendered.
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(BNSF Railway Company
STATEMENT OF CLAIM:
"Claim on behalf of the General Committee of the Brotherhood of
Railroad Signalmen
'DR
the Burlington Northern Santa Fe Railroad
Co:
Claim on behalf of D. E. Malone, M. J. Spah and C. C. McQueen,
for 80 hours at the prevailing Signalmen's rate to be divided equally
among the Claimants, account Carrier violated the current
Signalmen's Agreement, particularly Rule 1, the Scope Rule, when
it allowed outside forces to remove signal lines and cable from the
signal pole line from August 7, 2000 through August 14, 2000, and
deprived the Claimants of the opportunity to perform this work.
Carrier's File No. 35 Ol 0006. General Chairman's File No. 01-005BNSF-103-C. BRS File Case No. 11872-BN."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21, 1934.
Form 1 Award No. 37384
Page 2 Docket No. SG-37024
05-3-01-3-666
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
At all relevant times herein the Claimants were employed as Signalmen on
Signal Gang 134 with headquarters in Galesburg, Illinois. On the dates in question
the Carrier utilized the services of an outside contractor to remove cable and copper
line that the contractor had purchased from the Carrier. The Organization alleges
that in doing so the Carrier violated the parties' Scope Rule, because the work in
question should have been performed by bargaining unit personnel.
In arguing the claim the parties make much argument whether the cable and
copper line in question were active. In our view however, that debate does not aid in
resolving the claim because the record reflects that the cable and copper line that
the contractor removed had been purchased by the contractor on an "as is, where
is" basis. Thus, the cable and copper line were no longer the property of the Carrier
and, as such, in accordance with other Third Division precedent (e.g., Awards 28488
and 28615) the claim must be denied.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 24th day of February 2005.