Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 37397
Docket No. MW-37173
05-3-02-3-151
The Third Division consisted of the regular members and in addition Referee
Gerald E. Wallin when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Duluth, Missabe and Iron Range Railway Company
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (Waldholm Excavating and Flint Masonry) to perform
Bridge and Buillding Subdepartment work (excavating, forming
and pouring concrete and related work) at Proctor, MN on
October 26, 27, 30 and 31, 2000, instead of R. Lambert, D.
Signoralli, J. Skifstad and R. Headrick (Claim No. 38-00).
(2) As a consequence of the violation referred to in Part (1) above,
Claimants R. Lambert, D. Signoralli, J. Skifstad and R.
Headrick shall now each be compensated at their respective
straight time rates of pay for an equal and proportionate share
of the total man-hours expended by the outside forces in the
performance of the aforesaid work."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21, 1934.
Form 1 Award No. 37397
Page 2 Docket No. MW-37173
05-3-02-3-151
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
Contracting of work on this property is governed by Supplement No. 3 to the
parties' Agreement. It reads as follows:
"SUPPLEMENT NO. 3
Contracting of Work
(a) The Railway Company will make every reasonable effort to
perform all maintenance work in the Maintenance of Way and
Structures Department with its own forces.
(b) Consistent with the skills available in the Bridge and Building
Department and the equipment owned by the Company, the
Railway Company will make every reasonable effort to hold to
a minimum the amount of new construction work contracted.
(c) Except in emergency cases where the need for prompt action
precludes following such procedure, whenever work is to be
contracted, the Carrier shall so notify the General Chairman in
writing, describe the work to be contracted, state the reason or
reasons therefor, and afford the General Chairman the
opportunity of discussing the matter in conference with Carrier
representatives. In emergency cases, the Carrier will attempt
to reach an understanding with the General Chairman in
conference, by telephone if necessary, and in each case confirm
such conference in writing.
(d) It is further understood and agreed that the Company can
continue in accordance with past practice the contracting of
right-of-way cutting, weed spraying, ditching and grading."
Form 1 Award No. 37397
Page 3 Docket No. NTW-37173
05-3-02-3-151
Paragraphs (a) and (b) of Supplement No. 3 recognize that even new
construction work that is reserved to BMWE-represented employees can still be
properly contracted out if the Carrier has made every reasonable effort to have it
performed with Carrier forces. While there was some early skirmishing over scope
coverage of the work in dispute, due to the general nature of the applicable Scope
Rule, the Organization asserted that BMWE-represented employees had historically
and traditionally performed the work in dispute as part of its March 22, 2001
appeal on the property. Thiis assertion was not refuted by the Carrier. Indeed, the
Carrier conceded that its forces would have been used on the project in question
had they not been fully employed elsewhere, and that time was of the essence. Thus,
the record establishes scope coverage of the disputed work.
Regarding the Carrier's reasons for contracting the work, it is unrefuted in
the record that the concrete work needed to be completed before freeze-up to allow
track forces to replace and tamp nearby track. Concerns about freeze-up in the
Duluth, Minnesota, area after late October are not unfounded or unreasonable.
Moreover, it is undisputed that all Carrier forces were fully employed on other
work at the time the Carrier saw the need for contracting the work and while the
disputed work was performed. Finally, it is unrefuted that BMWE-represented
employees have historically refused to use Carrier-owned steel concrete forms and
instead preferred to construct wooden forms, which would have taken longer to
erect. The General Chairman's only proffered plan for using Carrier forces to do
the work was to delay other on-going projects via the diversion of personnel.
Whether the Carrier has exhausted every reasonable effort to hold the
contracting of new construction work to a minimum is a question of fact to be
determined upon consideration of all relevant circumstances. Thus, the analysis
must be conducted on a case-by-case basis. On the record before us, we find the
Carrier's reasons for contracting the work were reasonable. Accordingly, no
violation of the Agreement has been proven.
AWARD
Claim denied.
Form 1 Award No. 37397
Page 4 Docket No. MW-37173
05-3-02-3-151
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 24th day of February 2005.