Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 37397
Docket No. MW-37173
05-3-02-3-151

The Third Division consisted of the regular members and in addition Referee Gerald E. Wallin when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.
Form 1 Award No. 37397
Page 2 Docket No. MW-37173
05-3-02-3-151

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




Contracting of work on this property is governed by Supplement No. 3 to the parties' Agreement. It reads as follows:







Form 1 Award No. 37397
Page 3 Docket No. NTW-37173
05-3-02-3-151

Paragraphs (a) and (b) of Supplement No. 3 recognize that even new construction work that is reserved to BMWE-represented employees can still be properly contracted out if the Carrier has made every reasonable effort to have it performed with Carrier forces. While there was some early skirmishing over scope coverage of the work in dispute, due to the general nature of the applicable Scope Rule, the Organization asserted that BMWE-represented employees had historically and traditionally performed the work in dispute as part of its March 22, 2001 appeal on the property. Thiis assertion was not refuted by the Carrier. Indeed, the Carrier conceded that its forces would have been used on the project in question had they not been fully employed elsewhere, and that time was of the essence. Thus, the record establishes scope coverage of the disputed work.


Regarding the Carrier's reasons for contracting the work, it is unrefuted in the record that the concrete work needed to be completed before freeze-up to allow track forces to replace and tamp nearby track. Concerns about freeze-up in the Duluth, Minnesota, area after late October are not unfounded or unreasonable. Moreover, it is undisputed that all Carrier forces were fully employed on other work at the time the Carrier saw the need for contracting the work and while the disputed work was performed. Finally, it is unrefuted that BMWE-represented employees have historically refused to use Carrier-owned steel concrete forms and instead preferred to construct wooden forms, which would have taken longer to erect. The General Chairman's only proffered plan for using Carrier forces to do the work was to delay other on-going projects via the diversion of personnel.


Whether the Carrier has exhausted every reasonable effort to hold the contracting of new construction work to a minimum is a question of fact to be determined upon consideration of all relevant circumstances. Thus, the analysis must be conducted on a case-by-case basis. On the record before us, we find the Carrier's reasons for contracting the work were reasonable. Accordingly, no violation of the Agreement has been proven.





Form 1 Award No. 37397
Page 4 Docket No. MW-37173
05-3-02-3-151



This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 24th day of February 2005.