Form I NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 37674
Docket No. MW-36576
06-3-01-3-79

The Third Division consisted of the regular members and in addition Referee Steven 1VI. Bierig when award was rendered.

(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(BNSF Railway Company (former Burlington
( Northern Railroad Company)

STATEMENT OF CLAIM:





Form 1 Award No. 37674
Page 2 Docket No. MW-36576
06-3-01-3-79

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The Claimants have all established and hold seniority as Group 2 Machine Operators within the Roadway Equipment Sub-department of the Maintenance of Way and Structures Department. On the dates in question, the Claimants were regularly assigned and working as such on the Roadway Equipment District 4 in the vicinity of Colgate, Montana.


On December 12, 1996, the Carrier sent a notice to the General Chairman regarding its plan to contract the construction of roadbed from Mile Post 7.3 to Mile Post 7.64 for an extension of the Colgate siding track at Colgate, Montana. On December 17, 1996, the General Chairman requested a conference to discuss the matter. The conference was held on January 9, 1997, during which, the Carrier explained that the actual track construction on the extension (installation of ties, rails, etc.) would be performed by BMWE employees. However, on January 3, 1997, the Carrier had contracted with an outside contractor to construct the roadbed.


In the Carrier's letter of January 26, 1997, it was noted that an additional 700 feet of "upgrade" work beyond that originally identified in the December 10, 1996 contracting notice had been added to the project. The combined amount of work in this project totaled more than 9,000 feet.

Form 1 Award No. 37674
Page 3 Docket No. MW-36576
06-3-01-3-79

Pursuant to that notice and subsequent discussions, the Organization contends that the Agreement was violated when the Carrier assigned Baltrich Construction to construct roadbed from Mile Post 7.3 to Mile Post 7.64 for an extension of the Colgate siding track at Colgate, Montana, on May 5, 6, 7, 8, 9, 27, 30, 31 and June 1, 1997. First, it claims that the Carrier did not provide proper notice to the General Chairman and thus did not act in good faith in that at the time of the conference, the Agreement with the contractor had already been reached; therefore, the conference was futile. Second, the Organization claims that it was improper for the Carrier to contract out the above-mentioned work. This is work that is properly reserved to the Organization.


The subject work consisted of the construction of roadbed from Mile Post 7.3 to Mile Post 7.4 for an extension of the Colgate siding track at Colgate, Montana. According to the Organization, the Carrier had customarily assigned work of this nature to be performed by the Carrier's Maintenance of Way employees. The Organization further claims that this work is consistent with the Scope Rule. According to the Organization, the Carrier's Maintenance of Way employees were fully qualified and capable of performing the designated work. The work done by Baltrich Construction is within the jurisdiction of the Organization and, therefore, the Claimants should have performed said work. Because the Claimants were denied the right to perform the relevant work, the Organization argues that the Claimants should be compensated for the lost work opportunity.


Conversely, the Carrier takes the position that the Organization cannot meet its burden of proof in this matter. The Carrier contends that the work that was contracted out was that of roadbed construction, which the Carrier claims does not belong to the Carrier's BMWE-represented employees under either the express language of the Scope Rule or any binding past practice. According to the Carrier, controlling precedent involving these very same parties and identical issues has upheld the Carrier's position. Further, as to the alleged violation of Rule 55, the Carrier claims that while it is obligated to conference with the Organization, it is not precluded from reaching an agreement with the contractor prior to that conference.


First, as to the alleged Rule 55 violation, we find that the Carrier did give proper notice to the Organization of the proposed contracting. While the Organization has argued that the Carrier cannot reach an agreement with a

Form I Award No. 37674
Page 4 Docket No. MW-36576
06-3-01-3-79

contractor prior to a conference, we must reject this contention. We find, rather, that the Carrier is not precluded from reaching an agreement with the contractor. We note that the applicable rule, the note to Rule 55, does not bar signing up a contractor prior to a conference held after the 15-day window expires. It requires only a 15-day notice that in this case, the Carrier gave on December 12, 1996. In this case, the conference was held and the agreement with the contractor executed after the expiration of the 15-day window.


In support of this position, Arbitrator Bern, in Public Law Board No. 4402, Award 20, held:






Next, we reach the question of whether the work in question has been traditionally and customarily performed by the Organization. In Special Board of Adjustment No 1016, Award 150, the Board framed the scope issue as follows:


Form I Award No. 37674
Page 5 Docket No. MW-36576




In the instant case, we have carefully reviewed all evidence regarding whether the Organization has proven that the work involved belongs to the Organization. First, we note that the work of constructing roadbed is not specifically identified in the Scope Rule.


We next turn to whether there is sufficient evidence for the Organization to have proven that it has customarily, traditionally and historically performed the disputed work. In the instant case, while the Organization has presented some evidence to show that the work in question belonged to the Organization, that evidence is insufficient for the Organization to meet its burden of proof. See Public Law Board No. 6537 above. See Also Third Division Award 37365, Public Law Board No. 4402, Award 20, Case 20 and Award 28, Case 28.


Further, in Award 1 of Public Law Board No. 6537, between the same parties, Referee Brent indicated as follows:



Form 1 Award No. 37674
Page 6 Docket No. MW-36576
06-3-01-3-79




Based on the evidence in this matter as well as the above-cited precedent, we cannot find that the work of constructing roadbed is either definitively encompassed within the plain language of the Scope Rule or that the Organization has been able to prove that this work has historically and traditionally been performed by members of the Organization.

Thus, having determined that the notice was proper and that the work was not within the scope of the Organization, we find that the Organization has not met its burden of proof and the claim is, therefore, denied.
Form 1 Award No. 37674
Page 7 Docket No. MW-36576
06-3-01-3-79







This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 30th day of January 2006.
LABOR MEMLER'S DISSENT
TO
AWARD 376%4 DOCKET MW-36576
(Referee Bierig)

The Majority was not content with erring in Docket MW-36598, Award 37618 and opted for a cameo appearance in this case. Rather than burdening the record with another lengthy Dissent, we invite attention to the Dissent filed by the Organization attached to Award 37618.

Inasmuch as the Majority premised its denial of this claim on the same misguided basis as was present in Award 37618, this award is erroneous and can have no precedential value.

Respectfully submitted,

Roy C. Robinson
Labor Member