The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
The Claimants established seniority in the Maintenance of Way and Structures Department, Water Service Subdepartment on the Sacramento-West Division. At the time of the instant dispute, they were regularly assigned to a water service crew headquartered at Roseville, California.
Beginning December 6 through 17, 1999, the Carrier assigned Advanced Technology Cleaning, Inc., to install track matting between the diesel ramp and the service track in the Roseville Yard. Four employees of the outside contractor expended a total of 96 hours unrolling approximately 3000 feet of track matting and positioning it between the diesel ramp and the service track.
On February 4, 2000, the Organization filed the initial claim alleging that the contractor's installation of the matting constituted a violation of Article IV of the 1968 National Agreement. The claim also alleged that the Organization's members had historically performed said work.
According to the Organization, the Carrier's Maintenance of Way employees were fully qualified and capable of performing the designated work. Said work falls within the jurisdiction of the Organization and, therefore, the Claimants should have been assigned. In addition, before contracting out, it was the Carrier's responsibility to provide proper advance notice. Therefore, the Organization argues that the Claimants should be compensated for the lost work opportunity.
Conversely, the Carrier takes the position that the Organization cannot meet its burden of proof in this matter. It contends that the work was beyond the capabilities of Form 1 Award No. 37720
the Carrier's forces. In addition, the Carrier contends that it has the right to contract out such work, based on longstanding arbitral precedent. Further, the Carrier contends that because there is a history of a mixed practice of using contractors and Bl\IWE-represented employees to perform the relevant work, it is allowed to contract out said work.
The Board finds that the Carrier did not provide the required advance notice of the proposed contracting to the General Chairman. Such a requirement must have been fulfilled by the Carrier in order to sustain its position. As the Board held in Third Division Award 36516:
In the instant case, there is no question that the Carrier did not provide the advance notice required. The work in question was arguably scope-covered and at a minimum, notice should have been provided to the Organization before contracting out by the Carrier. Thus, the claim will be sustained.
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.