The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
The instant claim arose in connection with the Carrier's installation of new gear boxes on its No. 3 conveyor belt assembly at its Duluth Lakehead Storage Facility. According to the record, a new gear box with shaft and pulley already installed and a new hub for the shaft were received from the manufacturer. Instead of installing the hub onto the shaft while the parts were on the Carrier's property, the Carrier sent them off the property to Industrial Welders to have the hub pressed onto the shaft. Upon return of the gearbox assembly from the contractor, scopecovered employees then mounted it onto the No. 3 conveyor belt.
It is undisputed that the Carrier did not provide written notice to the General Chairman of its plans to contract the work pursuant to Supplement No. 3, which reads, in pertinent part, as follows:
The claim herein alleges a violation of both Supplement No. 3 and Supplement No. 9 when the Carrier contracted the hub installation as it did. The claim went on to make the following assertions:
The Carrier's initial reply to the claim, by letter dated April 27, 2000, did not refute the assertions about past performance in any manner whatsoever. Instead, it contended that timeliness of the installation was an important factor and proceeded to deny the claim.
The Organization's May 22, 2000 appeal made similar assertions about past performance of the work by scope-covered employees. . Once again, by its denial letter of July 18, 2000, the Carrier did not refute the assertions about past performance. The denial only advanced the timeliness contention as the basis for the contracting.
It was not until its third piece of correspondence on the property that the Carrier raised two additional contentions. First, it contended that Supplement No. 3 did not apply at the Ore Docks per the findings of Third Division Award 29162. , Second, it justified the contracting on the basis of a mixed practice of using the same contractor for the same work in the past.
The Carrier's work forces at its Duluth ore dock facilities are represented by two different Organizations. As a result, Supplement No. 9 was developed to guide work assignments at the docks by providing general descriptions of the kind of work that would be performed by each group of employees. Supplement No. 9 reads, in pertinent part, as follows: Form 1 Award No. 37952
Award does not produce the same conclusion. Third Division Award 29162 dealt with a. three-hour job of installing window shades in the cabs of the "Stacker" and "Shuttle Conveyor No. 5." The Award does not provide any details about the two pieces of equipment. As a result, we are unable to determine where this type of window shade maintenance would fall under Supplement No. 9. It is clear, however, that the instant dispute involves the No. 3 conveyor belt at the Duluth ore dock. Supplement No. 9 explicitly allocates the maintenance and repair of conveyor systems to BMWE-represented employees. Indeed, B&B employees, not ore dock employees, actually installed the gearbox assembly on the conveyor system when it came back from the contractor. This is strong evidence of how Supplement No. 9 applied to the equipment involved. On the record before us, therefore, we conclude that the disputed work was allocated to covered employees by Supplement No. 9.
The record also fails to provide sufficient support to the Carrier's mixed practice contention. While the Carrier supplied examples of past usage of the contractor in question, the evidence is sporadic at best. It shows only four instances where the contractor was used. None of the instances occurred more than 15 months prior to the incident in question. In addition, it is not clear from the Carrier's records that the instances involved the same work. Moreover, there is no evidence that the Organization was aware that the Carrier was using the contractor for the same work. Absent such evidence of awareness, it cannot be said that the Organization acquiesced in the practice.
When a past practice is claimed as an affirmative defense, the party so claiming bears the burden of to prove all requisite elements necessary to perfect the defense. On this record, the Carrier failed to establish the elements of clarity, consistency and longevity, as well as the Organization's knowledge of and acceptance of the claimed practice.
Given the foregoing circumstances, we find, on this record, that the disputed work was reserved to BMWE-represented employees by both material assertions of historical past performance that were not effectively refuted, as well as the text of Supplement No. 9. Accordingly, the Carrier was required to provide notice to the General Chairman pursuant to Supplement No. 3. It violated the Agreement when it failed to do so.
As we turn to the discussion of remedy for the violation, it must be remembered that the general purpose of the notice requirement is to provide the Form i Award No. 37952
Organization with the opportunity to confer with the Carrier about the contemplated project. This provides the Organization with the opportunity to convince the Carrier to have the work in question performed by the employees it represents. When the lack of notice denies the Organization this conference opportunity, as a practical matter, the employees it represents are denied the opportunity to perform the work. Accordingly, we must sustain the claim. We must clarify, however, that the remedy is limited to the hours expended by the contractor to do the hub installation in question. We do not provide any remedy for any other work that may have been performed by the contractor that (s outside the parameters of the instant claim.
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.