This case is one of ten dockets considering the propriety of the Carrier's use of outside contractors to perform work allegedly covered by the Scope Rule of the applicable Agreement. These dockets had not been pending before the Board as long as other cases also awaiting hearing. As a result, a controversy arose over whether it would be procedurally proper to have these cases heard out of chronological order. The controversy was resolved on a non-precedent setting basis by the Board Members and these cases were heard with the parties present on September 27, 2005. Because of that resolution by the Board Members, we have made no procedural findings regarding the order in which cases should be heard by the Board and nothing in this Award should be construed as making any such findings.
The instant dispute arose under the parties' June 1, 1999 Agreement. That Agreement replaced some 13 prior Agreements that existed on the various component railroads that have been merged over time into the present Carrier. The resulting Scope Rule was significantly different from any of the previous Scope Rules. In the years after the Agreement became effective, the Organization filed a number of claims to contest the Carrier's use of outside contractor forces to perform work believed to be covered by the new Scope Rule. It quickly became apparent that the parties had widely divergent views of how the new Scope Rule applied to the contracting of work.
The parties established a series of Public Law Boards to resolve the pending claims. Public Law Board No. 6508 issued its consolidated Award on eight claims on October 7, 2003. Five more Awards were issued by Public Law Board No. 6510 in January 2005.
The Awards of both PLBs provide extensive discussion about the evidentiary analysis they conducted on voluminous records to determine the proper meaning of the Scope Rule. As we read their Awards, both reached essentially the same conclusion. Nonetheless, the parties remain at odds about the permissible situations in which the Carrier may contract out scope covered work under the new Scope Rule. We understand that, as PLB No. 6508 said at page 42, ". . . scores of other similar disputes remain unresolved by the parties. . ." and are presently at the Board awaiting adjudication. Form 1 Award No. 37954
This paragraph and the following paragraph are preliminary comments offered for clarification at the outset of this decision. At the Referee Hearing, both parties stated that they were presenting essentially the same evidence and argument that they presented to PLB Nos. 6508 and 6510. The parties' Submissions in this case are voluminous. The Organization's Submission consists of 885 pages; the Carrier's consists of 279 pages. After careful review of the Submissions and the Awards of PLB Nos. 6508 and 6510, we agree that, although the parties may have emphasized their various contentions differently before us here and there, they did present substantially the same evidence, contentions, and interpretive issue to us that they presented to PLB Nos. 6508 and 6510.
In addition, the consolidated Award of PLB No. 6508 and the first Award of PLB No. 6510 are lengthy, consisting of 96 and 46 pages, respectively. Both set forth the entire text of the pertinent Agreement language including the contents of relevant Appendices and Letters of Agreement. In addition, both provide extensive detail about the contentions of the parties concerning the proper application of the new Scope Rule. PLB No. 6508 described each party's position in 26 pages (pp. 16-41). PLB No. 6510 used some 16 pages to do the same (pp. 17-32). In the interest of brevity and cost efficiency, we see no need to rewrite herein what has already been written twice before in great detail. Instead, we refer interested readers to the Awards of PLB Nos. 6508 and 6510 for the complete text of pertinent Agreement language as well as a thorough description of the parties' respective positions and supporting contentions. Accordingly, we incorporate by reference those portions of the Awards of PLB Nos. 6508 and 6510 as though fully set forth herein.
Although we have incorporated relevant Award portions from PLB Nos. 6508 and 6510, we offer the following statements of each party's position. They are intentionally condensed into a few sentences for purposes of our analysis. According to the Organization, the new Scope Rule established an "iron-clad" bar to contracting out any work covered by the Scope Rule unless the involved General Chairman approved; the inclusion of the National Agreements on subcontracting did not diminish the General Chairman's authority in any way. According to the Carrier, however, no such absolute bar was created by the new Scope Rule and the ability to contract out work was preserved by inclusion of the National Agreements. As a result, the Carrier need only give notice of the proposed contracting transaction and conference on it with the General Chairman if requested; it could nonetheless properly proceed with contracting out the work as long as it had a "legitimate" business reason to do so.
The following is the text of the new Scope Rule. Although in the Agreement they are unnumbered, we have numbered the first five paragraphs for ease of discussion. Form 1 Award No. 37954
As previously noted, we have the same interpretive issue before us that confronted PLB Nos. 6508 and 6510. As we read the Award of PLB No. 6508, it saw ambiguity inherent in the new Scope Rule resulting from the combination of the use of the word "reserved" and the incorporation of language from Article IV of the May 17, 1968 National Agreement and the reference to other National Agreements. However, PLB No. 6508 recognized that the word "reserved" is a term of art and has a long history of interpretation in the railroad industry. Accordingly, when the word appeared in paragraph [2] of the new Scope Rule, PLB No. 6508 concluded at page 44 that it ". . . reflects a calculated and knowing decision to enhance the preexisting strong presumption that bargaining unit members must perform the subsequently enumerated work." The Award went on to state on the same page, "Thus the second paragraph of the Scope Rule clearly and plainly indicates that only BMWE members have a right to perform the enumerated work."
Despite the strong presumption flowing from the use of reservation of work terminology, PLB No. 6508 determined that General Chairmen were not vested with the sole authority to bar the Carrier from contracting out work if they failed to reach an understanding at the applicable conference. Instead, PLB No. 6508 found that the parties, by the language they used in their new Scope Rule, preserved the ability to submit disputes to arbitral review to be decided on a case-by-case basis as their facts Form 1 Award No. 37954
dictate. In this regard, however, PLB No. 6508 went on to find, at page 46, that ". . . the Carrier must demonstrate a highly compelling reason to rebut the very strong presumption that the work covered by the second paragraph of the Scope Rule will be performed by BMWE members." At page 47, PLB No. 6508 determined that any arbitral review should subject the Carrier's justification for contracting out scope covered work to "strict scrutiny." PLB No. 6508 also rejected full employment and/or lack of employees on furlough as sufficient reasons to deny a compensation remedy.
PLB No. 6510 approached its interpretive task by breaking down the overall dispute into four issue areas for discussion. First, it addressed the question of whether the Award of PLB No. 6508 was palpably erroneous in part, as the Organization argued, after it rejected the contention that General Chairmen were vested with veto authority. As its second and third issues, PLB No. 6510 dealt with the respective burdens of proof that the parties must satisfy to prevail in the arbitration of any given contracting dispute. Finally, PLB No. 6510 discussed the effect of past practice in light of the new Scope Rule language.
As we read the Award of PLB No. 6510, it did not find any portion of the Award of PLB No. 6508 to be palpably erroneous or repugnant to the parties' new Agreement. Indeed, it echoed the determination of PLB No. 6508 that the use of the word "reserved" in paragraph 2 was significant. It said, at page 35, that ". . . the inclusion of the term `reserved' in Paragraph 2 of the Scope Rule represented the informed decision by the negotiators of the current System Agreement to strengthen the current Scope Rule as to its application and meaning." PLB No. 6510 went on to find that the parties had not intended to totally prohibit contracting of scope covered work even when the General Chairmen did not consent. At page 39, PLB No. 6510 rejected the Organization's contention that the new Scope Rule represented an absolute bar on the Carrier's ability to contract out work.
Turning to the Organization's burden of proof, PLB No. 6510 said, at page 39, ". . . all that is necessary is proof that the specific work falls within the categories enumerated under Paragraph 2 as reserved to members of this Organization." At page 11 of its Award 6, PLB No. 6510 also described this burden as a "low standard of proof."
As to the Carrier's respective burden of proof, PLB No. 6510 observed, at page 40, that the ". . . Organization and these claimants cannot effectively grieve unless they are made aware of the business justifications for contracting out, the reasons why management has invoked its ability to contract out in the specific instance. . . :' PLB No. 6510 went on to find that, "Persuasive specific evidence must be presented from the Form 1 Award No. 37954
Carrier that °a compelling reason exists to contract out the disputed work." Finally, PLB No. 6510 said, at page 41, that ". . . the Carrier is now obligated to present its affirmative defenses at the conference and in ,the handling of the dispute on the property."
Finally, as to the effect of any past practices, PLB No. 6510 determined, at page 42, "Past practices may not trump the right of claimants to do the enumerated work `reserved to members of the BMWE' by paragraph 2, after the negotiation of the current Scope Rule."
As we read the first Award of PLB No. 6510, it entirely endorsed the interpretive findings of PLB No. 6508 and followed them without change. Taken together, the findings of these two PLBs determined that when the sophisticated and experienced negotiators for the instant parties used explicit reservation of work terminology, they were recognizing, as PLB No. 6508 said at page 46, that ". . . the pendulum is now further on the side of the Organization." When work is reserved to an Organization, it will be performed by the members of the Organization unless truly compelling circumstances, that can pass strict scrutiny in arbitration, exist to the contrary., This effectively means that the Carrier must use due diligence to inspect its property to detect the need for project work covered by the new Scope Rule and, where the need for such work is or should have been identified through the exercise of due diligence, the Carrier will plan for performing the work with its own employees represented by the Organization. Such planning should include any necessary hiring, training, equipping, and scheduling of such forces. Full employment and/or lack of furloughed employees does not suffice as a defense to a compensation remedy if a violation of the Agreement is determined. However, where circumstances arise that provide the Carrier with truly compelling reasons to use a contractor to perform the work, the Carrier should be able to do so. If the justification is disputed by the General Chairman and cannot be resolved by the parties, whether compelling reasons were demonstrated by the Carrier is a question of fact to be decided in arbitration after due consideration of all relevant circumstances shown by the parties' Submissions.
After careful consideration of the evidence in the record before us, we find no basis to quarrel with the interpretive findings of either PLB No. 6508 or PLB No. 6510. Accordingly, we endorse those findings in their entirety and adopt them as our own. In addition, however, we provide two additional considerations in support of those findings. They both respond to the Organization's contention that the new Scope Rule is an absolute bar to the contracting of scope covered work unless the involved General Chairman approves. First, it is clear from Article IV of the 1968 National Agreement as well as the 1981 Berge-Hopkins Letter of Understanding, that the parties intended to Form 1 Award No. 37954
establish a contracting review process based on good faith and fair dealing with each other. However, the Organization's position leaves the door open to allow the General Chairman to unreasonably withhold approval. Thus, despite the unlikelihood of its occurrence, it is conceivable that a contracting situation could arise that is compelling by any objective standard of review, but the involved General Chairman could nevertheless unreasonably withhold approval out of pique, retaliation for some other perceived transgression, or simply as a show of power. Such a possibility is such an affront to the obligations of good faith and fair dealing that an opportunity for objective arbitral acceptance of the compelling reasons must be available.
Our second consideration arises from the non sequitur embedded in the Organization's position. According to the Organization, the new Scope Rule prohibits the contracting of scope covered work unless there is a stated exception. The Organization says there are only three: First, there is an exception for billboards in paragraph 2. Second, there is also an exception in the same paragraph for asphalt paving of road crossings if required by outside agencies. Finally, paragraph 3 provides an exception for scope covered work performed by other craft employees on the effective date of the Agreement; those employees may continue to perform it. Significantly, the Scope Rule does not explicitly provide an exception for contracting work when required by genuine emergency circumstances. The parties did, however, provide for an emergency exception to the notice requirement in paragraph 4. Indeed, such an exception was not part of the text of Article IV of the 1968 National Agreement so it was deliberately added by these parties. However, central to the Organization's position is that paragraph 4 of the new Scope Rule, like its corresponding paragraph in Article IV of the 1968 National Agreement, pertains only to the notice procedure and does not confer any substantive right to contract work. It simply does not follow that the Carrier would be entirely excused from giving notice before contracting out work in true emergencies but should thereafter be found to have violated the Agreement if it actually did contract out the emergency work because there was no stated exception giving it the substantive right to do so.
Given the rationale expressed by PLB Nos. 6508 and 6510 and the two considerations described above, we also find that the new Scope Rule does permit, by implication, an exception for contracting out scope covered work for compelling reasons that will satisfy a "strict scrutiny" standard of review.
The events leading to the instant dispute began with the Carrier's November 21, 2002 notice of intent to contract the work. It described the work in question as follows: Form 1 Award No. 37954
The Organization voiced its objection to the Carrier's plan by its letter dated December 2, 2002. The letter claimed scope coverage by means of citations to the text of the new Scope Rule. It also asserted there was no evidence of emergency or lack of capability of B&B forces. The letter also requested to see a copy of the contracting document.
At the Referee Hearing on September 27, 2005, the Carrier conceded that all of the disputed work was reserved to covered employees except for the building design and any electrical work. The Organization in turn, declared that its claim did not seek either the desien work or the electrical work.
According to the March 14, 2003 claim, the construction work did not actually begin until February 3, 2003. This was nearly two months later than the start date projected in the notice. In addition to assertions about scope coverage as well as the qualification and availability of Carrier forces to have performed the work, the Organization requested to review a copy of the contract between the Carrier and the contractor.
The claim was denied by the Chief Regional Engineer on May 9, 2003. The denial provided no reasons whatsoever to explain why the work was contracted out. After asserting that notice was properly served, the letter said only, "We find no violation of the CSXT/BMWE Agreement. Claim is denied." Form 1 Award No. 37954
The Organization's appeal dated June 5, 2003 began by again requesting to review ". . . relevant management records in regards to instant claim, including copy of contract with contractor(s)." It went on to assert that the Carrier could have used employees from five seniority districts within the Albany Service Lane. The letter also included employee statements pertaining to allegations that the Carrier was constantly reducing its forces.
The Carrier's final correspondence in the on-property record is an October 22, 2003 letter from the highest designated officer. While it contains general assertions about the Carrier's perceived rights in contracting situations, the context is general and provides no reasons specific to the instant dispute to show why the Carrier was compelled to contract the work as it did. At most, the letter asserted that all Carrier forces were working on equally important projects and that there were no employees on furlough in the seniority district. But such is not a suitable explanation to establish why the Carrier could not have staffed, equipped, and scheduled its own forces to perform the work instead of contracting it to outsiders. Because the Carrier failed to satisfy its burden to establish compelling reasons for its action, we must find that it violated the Agreement.
It also appears from the record that the Carrier never complied with its obligation under Rule 24(i) to permit inspection of Carrier records pertaining to the claim. This is an independent violation of the Agreement.
The Carrier advanced the same full employment contentions to oppose a compensatory remedy that it did in the earlier disputes within this slate of ten contracting cases. The contention is rejected. A compensatory remedy is appropriate for two reasons: (1) it compensates the Claimants for a lost work opportunity that they could have enjoyed had the Carrier properly scheduled them to perform the work and (2) compensation is appropriate to preserve the integrity of the Agreement.
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.