Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 37955
Docket No. MW-38279
06-3-04-3-211

The Third Division consisted of the regular members and in addition Referee Gerald E. Wallin when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Form 1 Award No. 37955
Page 2 Docket No. MW-38279
06-3-04-3-211





This case is one of ten dockets considering the propriety of the Carrier's use of outside contractors to perform work allegedly covered by the Scope Rule of the applicable Agreement. These dockets had not been pending before the Board as long as other cases also awaiting hearing. As a result, a controversy arose over whether it would be procedurally proper to have these cases heard out of chronological order. The controversy was resolved on a non-precedent setting basis by the Board Members and these cases were heard with the parties present on September 27, 2005. Because of that resolution by the Board Members, we have made no procedural findings regarding the order in which cases should be heard by the Board and nothing in this Award should be construed as making any such findings.


The instant dispute arose under the parties' June 1, 1999 Agreement. That Agreement replaced some 13 prior Agreements that existed on the various component railroads that have been merged over time into the present Carrier. The resulting Scope Rule was significantly different from any of the previous Scope Rules. In the years after the Agreement became effective, the Organization filed a number of claims to contest the Carrier's use of outside contractor forces to perform work believed to be covered by the new Scope Rule. It quickly became apparent that the parties had widely divergent views of how the new Scope Rule applied to the contracting of work.


The parties established a series of Public Law Boards to resolve the pending claims. Public Law Board No. 6508 issued its consolidated Award on eight claims on October 7, 2003. Five more Awards were issued by Public Law Board No. 6510 in January 2005.


The Awards of both PLBs provide extensive discussion about the evidentiary analysis they conducted on voluminous records to determine the proper meaning of the Scope Rule. As we read their Awards, both reached essentially the same conclusion. Nonetheless, the parties remain at odds about the permissible situations in which the Carrier may contract out scope covered work under the new Scope Rule. We understand that, as PLB No. 6508 said at page 42, ". . . scores of other similar disputes remain unresolved by the parties. . ." and are presently at the Board awaiting adjudication.

Form 1 Award No. 37955
Page 3 Docket No. AM-38279
06-3-04-3-211

This paragraph and the following paragraph are preliminary comments offered for clarification at the outset of this decision. At the Referee Hearing, both parties stated that they were presenting essentially the same evidence and argument that they presented to PLB Nos. 6508 and 6510. The parties' Submissions in this case are voluminous. The Organization's Submission consists of 872 pages; the Carrier's consists of 223 pages. After careful review of the Submissions and the Awards of PLB Nos. 6508 and 6510, we agree that, although the parties may have emphasized their various contentions differently before us here and there, they did present substantially the same evidence, contentions, and interpretive issue to us that they presented to PLB Nos. 6508 and 6510.


In addition, the consolidated Award of PLB No. 6508 and the first Award of PLB No. 6510 are lengthy, consisting of 96 and 46 pages, respectively. Both set forth the entire text of the pertinent Agreement language including the contents of relevant Appendices and Letters of Agreement. In addition, both provide extensive detail about the contentions of the parties concerning the proper application of the new Scope Rule. PLB No. 6508 described each party's position in 26 pages (pp. 16-41). PLB No. 6510 used some 16 pages to do the same (pp. 17-32). In the interest of brevity and cost efficiency, we see no need to rewrite herein what has already been written twice before in great detail. Instead, we refer interested readers to the Awards of PLB Nos. 6508 and 6510 for the complete text of pertinent Agreement language as well as a thorough description of the parties' respective positions and supporting .contentions. Accordingly, we incorporate by reference those portions of the Awards of PLB Nos. 6508 and 6510 as though fully set forth herein.


Although we have incorporated relevant Award portions from PLB Nos. 6508 and 6510, we offer the following statements of each party's position. They are intentionally condensed into a few sentences for purposes of our analysis. According to the Organization, the new Scope Rule established an "iron-clad" bar to contracting out any work covered by the Scope Rule unless the involved General Chairman approved; the inclusion of the National Agreements on subcontracting did not diminish the General Chairman's authority in any way. According to the Carrier, however, no such absolute bar was created by the new Scope Rule and the ability to contract out work was preserved by inclusion of the National Agreements. As a result, the Carrier need only give notice of the proposed contracting transaction and conference on it with the General Chairman if requested; it could nonetheless properly proceed with contracting out the work as long as it had a "legitimate" business reason to do so.

Form 1 Award No. 37955
Page 4 Docket No. MW-38279
06-3-04-3-211

The following is the text of the new Scope Rule. Although in the Agreement they are unnumbered, we have numbered the first five paragraphs for ease of discussion. The numbers reflect the same numbering the parties used in their presentations to the Board.





Form 1 Award No. 37955
Page 5 Docket No. MW-38279
06-3-04-3-211




Form 1 Award No. 37955
Page 6 Docket No. MW-38279
06-3-04-3-211
nevertheless proceed with said contracting, and the organization may
tile and progress claims in connection therewith.
All National Contracting Agreements apply, see Appendix `M'













As previously noted, we have the same interpretive issue before us that confronted PLB Nos. 6508 and 6510. As we read the Award of PLB No. 6508, it saw ambiguity inherent in the new Scope Rule resulting from the combination of the use of the word "reserved" and the incorporation of language from Article IV of the May 17, 1968 National Agreement and the reference to other National Agreements. However, PLB No. 6508 recognized that the word "reserved" is a term of art and has a long history of interpretation in the railroad industry. Accordingly, when the word appeared in paragraph [2] of the new Scope Rule, PLB No. 6508 concluded at page 44 that it ". . . reflects a calculated and knowing decision to enhance the preexisting strong presumption that bargaining unit members must perform the subsequently enumerated work." The Award went on to state on the same page, "Thus the second paragraph of the Scope Rule clearly and plainly indicates that only BMWE members have a right to perform the enumerated work."

Form 1 Award No. 37955
Page 7 Docket No. MW-38279
06-3-04 3-211

Despite the strong presumption flowing from the use of reservation of work terminology, PLB No. 6508 determined that General Chairmen were not vested with the sole authority to bar the Carrier from contracting out work if they failed to reach an understanding at the applicable conference. Instead, PLB No. 6508 found that the parties, by the language they used in their new Scope Rule, preserved the ability to submit disputes to arbitral review to be decided on a case-by-case basis as their facts dictate. In this regard, however, PLB No. 6508 went on to find, at page 46, that ". . . the Carrier must demonstrate a highly compelling reason to rebut the very strong presumption that the work covered by the second paragraph of the Scope Rule will be performed by BMWE members." At page 47, PLB No. 6508 determined that any arbitral review should subject the Carrier's justification for contracting out scope covered work to "strict scrutiny." PLB No. 6508 also rejected full employment and/or lack of employees on furlough as sufficient reasons to deny a compensation remedy.


PLB No. 6510 approached its interpretive task by breaking down the overall dispute into four issue areas for discussion. First, it addressed the question of whether the Award of PLB No. 6508 was palpably erroneous in part, as the . Organization argued, after it rejected the contention that General Chairmen were vested with veto authority. As its second and third issues, PLB No. 6510 dealt with the respective burdens of proof that the parties must satisfy to prevail in the arbitration of any given contracting dispute. Finally, PLB No. 6510 discussed the effect of past practice in light of the new Scope Rule language.


As we read the Award of PLB No. 6510, it did not find any portion of the Award of PLB No. 6508 to be palpably erroneous or repugnant to the parties' new Agreement. Indeed, it echoed the determination of PLB No. 6508 that the use of the word "reserved" in paragraph 2 was significant. It said, at page 35, that ". . . the inclusion of the term `reserved' in Paragraph 2 of the Scope Rule represented the informed decision by the negotiators of the current System Agreement to strengthen the current Scope Rule as to its application and meaning." PLB No. 6510 went on to find that the parties had not intended to totally prohibit contracting of scope covered work even when the General Chairmen did not consent. At page 39, PLB No. 6510 rejected the Organization's contention that the new Scope Rule represented an absolute bar on the Carrier's ability to contract out work.


Turning to the Organization's burden of proof, PLB No. 6510 said, at page 39, °`. . . all that is necessary is proof that the specific work falls within the categories enumerated under Paragraph 2 as reserved to members of this Organization." At page

Form 1 Award No. 37955

Page 8 Docket No. MW-38279
06-3-04-3-211

11 of its Award 6, PLB No. 6510 also described this burden as a "low standard of proof."


As to the Carrier's respective burden of proof, PLB No. 6510 observed, at page 40, that the ". . . Organization and these claimants cannot effectively grieve unless they are made aware of the business justifications for contracting out, the reasons why management has invoked its ability to contract out in the specific instance . . . ." PLB No. 6510 went on to find that, "Persuasive specific evidence must be presented from the Carrier that °a compelling reason exists to contract out the disputed work.'" Finally, PLB No. 6510 said, at page 41, that ". . . the Carrier is now obligated to present its affirmative defenses at the conference and in the handling of the dispute on the property."


Finally, as to the effect of any past practices, PLB No. 6510 determined, at page 42, "Past practices may not trump the right of claimants to do the enumerated work `reserved to members of the BMWE' by paragraph 2, after the negotiation of the current Scope Rule."


As we read the first Award of PLB No. 6510, it entirely endorsed the interpretive findings of PLB No. 6508 .and followed them without change. Taken together, the findings of these two PLBs determined that when the sophisticated and experienced negotiators for the instant parties used explicit reservation of work terminology, they were recognizing, as PLB No. 6508 said at page 46, that ". . . the pendulum is now further on the side of the Organization." When work is reserved to an Organization, it will be performed by the members of the Organization unless truly compelling circumstances, that can pass strict scrutiny in arbitration, exist to the contrary. This effectively means that the Carrier must use due diligence to inspect its property to detect the need for project work covered by the new Scope Rule and, where the need for such work is or should have been identified through the exercise of due diligence, the Carrier will plan for performing the work with its own employees represented by the Organization. Such planning should include any necessary hiring, training,. equipping, and scheduling of such forces. Full employment and/or lack of furloughed employees does not suffice as a defense to a compensation remedy if a violation of the Agreement is determined. However, where circumstances arise that provide the Carrier with truly compelling reasons to use a contractor to perform the work, the Carrier should be able to do so. If the justification is disputed by the General Chairman and cannot be resolved by the parties, whether compelling reasons were demonstrated by the Carrier is a question of fact to be decided in arbitration after due consideration of all relevant circumstances shown by the parties' Submissions.

Form 1 Award No. 37955
Page 9 Docket No. MW-38279
06-3-04-3-211

After careful consideration of the evidence in the record before us, we find no basis to quarrel with the interpretive findings of either PLB No. 6508 or PLB No. 6510. Accordingly, we endorse those findings in their entirety and adopt them as our own. In addition, however, we provide two additional considerations in support of those findings. They both respond to the Organization's contention that the new Scope Rule is an absolute bar to the contracting of scope covered work unless the involved General Chairman approves. First, it is clear from Article IV of the 1968 National Agreement as well as the 1981 Berge-Hopkins Letter of Understanding, that the parties intended to establish a contracting review process based on good faith and fair dealing with each other. However, the Organization's position leaves the door open to allow the General Chairman to unreasonably withhold approval. Thus, despite the unlikelihood of its occurrence, it is conceivable that a contracting situation could arise that is compelling by any objective standard of review, but the involved General Chairman could nevertheless unreasonably withhold approval out of pique, retaliation for some other perceived transgression, or simply as a show of power. Such a possibility is such an affront to the obligations of good faith and fair dealing that an opportunity for objective arbitral acceptance of the compelling reasons must be available.


Our second consideration arises from the non sequitur embedded in the Organization's position. According to the Organization, the new Scope Rule prohibits the contracting of scope covered work unless there is a stated exception. The Organization says there are only three: First, there is an exception for billboards in paragraph 2. Second, there is also an exception in the same paragraph for asphalt paving of road crossings if required by outside agencies. Finally, paragraph 3 provides an exception for scope covered work performed by other craft employees on the effective date of the Agreement; those employees may continue to perform it. Significantly, the Scope Rule does not explicitly provide an exception for contracting work when required by genuine emergency circumstances. The parties did, however, provide for an emergency exception to the notice requirement in paragraph 4. Indeed, such. an exception was not part of the text of Article IV of the 1968 National Agreement so it was deliberately added by these parties. However, central to the Organization's position is that paragraph 4 of the new Scope Rule, like its corresponding paragraph in Article IV of the 1968 National Agreement, pertains only to the notice procedure and does not confer any substantive right to contract work. It simply does not follow that the Carrier would be entirely excused from giving notice before contracting out work in true emergencies but should thereafter be found to have violated the Agreement if it actually did contract out the emergency work because there was no stated exception giving it the substantive right to do so.

Form 1 Award No. 37955
Page 10 Docket No. MW-38279
06-3-04-3-211

Given the rationale expressed by PLB Nos. 6508 and 6510 and the .two considerations described above, we also find that the new Scope Rule does permit, by implication, an exception for contracting out scope covered work for compelling reasons that will satisfy a "strict scrutiny" standard of review.


Turning to the specific facts of this dispute, the Carrier's September 23, 2002 notice of intent to contract the work described the work in question as follows:




At the Referee Hearing on September 27, 2005, the Carrier conceded that the disputed work was reserved to covered employees. The new Scope Rule is quite explicit on this point in that it specifically reserves asphalting of road crossing unless an outside agency requires the work to be performed by others. The Carrier does not contend that such an outside agency requirement was a factor in this dispute.


Given the fact that the work was reserved by the new Scope Rule, the Carrier may not contract for its performance by outsiders unless compelling reasons require it. The Carrier bears the burden of proof to establish those compelling reasons.


The Carrier did not provide evidence to establish compelling reasons for the contracting. The Chief Regional Engineer's initial denial dated May 27, 2003 raised only two factors in support of the Carrier's action: first, that there had been a past practice of contracting the paving of road crossings and, second, that the Claimants

Form 1 Award No. 37955
Page 11 Docket No. MW-38279
06-3-04-3-211

were engaged in their normal duties and were appropriately compensated. The September 17, 2003 response from the Carrier's highest designated officer made only generic assertions about the Carrier's perceived rights to contract work. There was no evidence specific to the instant claim to justify the contracting.


The instant dispute is quite similar to Case No. 1 decided by Public Law Board No. 6510 which sustained that claim. There, as here, the Carrier relied on various general assertions about its rights to contract scope-covered work. It alleged a past practice of contracting such work. It also noted full employment of its forces with no employees on furlough. There, as here, such contentions were found to be insufficient to establish compelling reasons. When the parties agreed to explicitly include "asphalting of road crossings" within the listing of work reserved to covered employees, the Carrier effectively relinquished any pre-Agreement right it may have had to contract such work except for compelling reasons.


In this dispute, the Carrier did not challenge the Organization's assertion that the work did not begin until some four months after the date of the notice. Thus, there was no urgency shown by the record. Nor did the Carrier refute the Organization's assertion that the only equipment used by the contractor was cold patch asphalt, a bobcat loader, a dump truck, and a vibrating plate hand tamper. Lack of suitable equipment was, therefore, not established by the record.


Given the state of the record, no circumstances have been established by the Carrier to demonstrate that it could not have leased the necessary equipment and scheduled its own forces to do the work. Accordingly, we must find that the Agreement was violated.


In its defense to the awarding of a compensatory remedy, the Carrier raised only the generic contention that its forces were fully employed in other important work. Both Public Law Board Nos. 6508 and 6510 rejected this defense. As we have in the other cases, we also do not find it to be persuasive here. A compensatory Award is . appropriate, under the circumstances, to preserve the integrity of the Agreement. Otherwise the Carrier could violate the Agreement with impunity and entirely escape accountability merely by keeping its force structure low and engaged in other work.


Though there was some concern expressed by the Carrier about the identities of the named Claimants because they were B&B Department forces instead of Track Department forces, we make no findings about work jurisdictional rights intra-craft.

Instead, we accept the view that the Organization has latitude to name claimants for
Form 1 Award No. 37955
Page 12 Docket No. MW-38279
06-3-04-3-211

Agreement enforcement purposes in disputes of this kind where individual qualifications are not a significant issue.








This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 19th day of September 2006.