NATIONAL RAILROAD ADJUSTMENT BOARD
Award No. 38174 Award No. 38175 Award No. 38176
Docket No. MW-37718 Docket No. MW-37958 Docket No. MW-38006
07-3-03-3-69 07-3-03-3-374 07-3-03-3-427
Award No. 38177 Award No. 38178 Award No. 38179
Docket No. MW-38383 Docket No. MW-38395 Docket No. MW-38409
07-3-04-3-307 07-3-04-3-312 07-3-04-3-349
Award No. 38180 Award No. 38181 Award No. 38182
Docket No. MW-38698 Docket No. MW-38992 Docket No. MW-39582
07-3-04-3-527 07-3-05-3-457 07-3-06-3-67
(Brotherhood of Maintenance of Way Employes Division -
( IBT Rail Conference
PARTIES TO DISPUTE: (
(Union Pacific Railroad Company
STATEMENT OF CLAIM: As shown in Docket Nos. MW-37718, MW-37958, MW38006, MW-38383, MW-38395, MW-38409, MW-38698, MW-38992, and MW-39582
and not repeated herein.
FINDINGS
: The Third Division of the Adjustment Board finds:
That the disputes were certified to the Third Division of the Adjustment Board
ex parte by the petitioning party; and
Under date of March 19, 2007, the petitioning party addressed a formal
communication to the Arbitration Assistant requesting withdrawal of these cases from
further consideration by the Division which request is hereby granted.
AWARD
Claims withdrawn.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 23rd day of April 2007.