Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 38195
Docket No. MW-38988
07-3-05-3-432

The Third Division consisted of the regular members and in addition Referee Edwin H. Benn when award was rendered.

(Brotherhood of Maintenance of Way Employes Division -
( IBT Rail Conference
PARTIES TO DISPUTE:
(National Railroad Passenger Corporation (Amtrak)

STATEMENT OF CLAIM:





Form 1. Award No. 38195
Page 2 Docket No. MW-38988


FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act as approved June 21, 1934.



invntveft herein



By letter dated February o, 2004, the Carrier notified the Organization of its intent to use an outside contractor for work in the Chicago Yards. The work identified to be contracted out was installation of 15 turnouts and the rebuilding of 8500 feet of yard track, including rails, ties and ballast. Although the record is not precisely clear, the evidence shows that the Carrier and the Organization met on several occasions after the Carrier's notice was given and up through March 10, 2004 concerning the Carrier's stated intent to contract out the work. However, agreement was not reached and the Carripr rnntrartPd not tha work Nn crnna covered employees were furloughed as a result of the contracting of the work.



Zri
Lhe cla,

The Carrier contracted out work covered by the Scope Rule (Rule 1). The work described in the claim and in the record is typical work performed by Maintenance of Way, forces.




V===t ~ Award No. 38195
Page 3 Docket No. MW-38988
07-3-05-3-432
date of the contracting transaction as is practicable and in any
event not less than 15 days prior thereto.





















Notwithstanding the provisions of the Scope Rule, the Carrier has the right to contract out work. If the Carrier did not have that right, Rule 24 would have no meaning.

The Carrier met its obligations under Rule 24. Timely advance notice was given to the Organization by the Carrier of its intent to contract out the work and
Form 1 Award No. 38195
Page 4 Docket No. MW-38988


the parties met on several occasions in an effort to reach agreement concerning the Carrier's stated intent. Further, no employee was furloughed as a result of the contracting out of the work in dispute. The parties' inability to reach agreement in their discussions concerning the Carrier's decision to contract out work does not amount to a showing by the Organization that the Carrier failed to meet its obligations under Rule 24 or any other requirements as being indicative of bad faith on the Carrier's part.


Based on the above, the Organization has not carried its burden. The claim will therefore be denied.




      %C

      -!aim denied.


                          ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimants) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 18th day of May 2007.